Red flags
- No red flags in this filing
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
ASN Gardenia is a Residential/Group Housing project by ASN DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/211005/004336 on 5 Oct 2021. Possession is promised by 30 Sep 2024.
At a glance
Project
- NameASN Gardenia
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/211005/004336
- ReraGenie IDRG-KA-38874
Builder
- NameASN DEVELOPERS
- Entity typePartnership Firm
- Authorized SignatoryRAMESH V
- OthersBALASUBRAMNYAM P
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on5 Oct 2021
- Promised completion30 Sep 2024
- Revised completionNone
- Buildings5 building records
- Documents filed83 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Block A | - | - | - | 100 | 0 | 100 |
| Block B | - | - | - | 108 | 0 | 108 |
| Block C | - | - | - | 48 | 0 | 48 |
| Block D | - | - | - | 52 | 0 | 52 |
| Block E | - | - | - | 40 | 0 | 40 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 29 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 29 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | Yes | - |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership10
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M. YATHISH | - | - |
| R. Girija | - | - |
| C. JAMUNA | - | - |
| M. Krishnappa | - | - |
| R. Manjula | - | - |
| R. Bhagyalakshmi | - | - |
| M. MAHESH | - | - |
| C. NARAYANAMMA | - | - |
| M. SRIRAMAIAH | - | - |
| Ammayamma | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHUBHASHINI.T |
| Engineer | KUMAR C.G |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed83
As listed on the registration, under the names the promoter filed them with; the newest 80 of 83 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/211005/004336 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| BWSSB NOCFile: BWSSB NOC.pdf | 29 Sep 2021 |
| KSPCB NOCFile: KSPCB NOC.pdf | 29 Sep 2021 |
| AffidavitFile: AFFIDAVIT.pdf | 18 Aug 2021 |
| Construction ImageFile: IMAGE.pdf | 18 Aug 2021 |
| Construction ImageFile: IMAGE 1.pdf | 18 Aug 2021 |
| Construction ImageFile: IMAGE 2.pdf | 18 Aug 2021 |
| Construction ImageFile: IMAGE 3.pdf | 18 Aug 2021 |
| Construction ImageFile: IMAGE 4.pdf | 18 Aug 2021 |
| Construction ImageFile: IMAGE 5.pdf | 18 Aug 2021 |
| Construction ImageFile: IMAGE 6.pdf | 18 Aug 2021 |
| BWSSB Demand letterFile: DemandNote.pdf | 18 Aug 2021 |
| ASN Payment ReceiptFile: ASN Online payment Receipt.pdf | 18 Aug 2021 |
| KSPCB AckFile: ASN_KSPCB Ack.pdf | 18 Aug 2021 |
| BESCOM NOCFile: BESCOM.jpeg | 30 Jun 2021 |
| KSPCB NOCFile: ASN_KSPCB Ack.pdf | 30 Jun 2021 |
| BWSSB NOCFile: BWSSBNOC-2021 6-21-061708373858 .pdf | 30 Jun 2021 |
| Request for extension of timelimit to submit queried documentsFile: Request for time extension.pdf | 21 May 2021 |
| Notarised Form BFile: Notarised Form B.pdf | 19 Apr 2021 |
| Notarised Joint Affidavit Cum DeclarationFile: Notarised Joint Affidavit Cum Declaration.pdf | 19 Apr 2021 |
| Bescom Connection billFile: Bescom Temporary Connection Bill.jpeg | 19 Apr 2021 |
| Sale deed for Sy No 7/1File: Sale deed.pdf | 12 Apr 2021 |
| Mutation Copy for Sy No 13/4File: Mutation register copy.pdf | 12 Apr 2021 |
| EC from Apr-2004 to Mar-21. As no entry in EC from Jan-21 to Mar-21, it is in Namune/Form 16File: EC Merged ASN Gardenia_1.pdf | 12 Apr 2021 |
| Notarised Form BFile: Scan 10 Apr 2021 (1).pdf | 12 Apr 2021 |
| Notarised Joint DeclarationFile: Scan 10 Apr 2021 (2).pdf | 12 Apr 2021 |
| License Condition LetterFile: License Conditions.pdf | 12 Apr 2021 |
| Reply to First NoticeFile: Reply to First Notice.pdf | 12 Apr 2021 |
| CertificateFile: Registration & Form D & PAN.pdf | - |
| ASN Gardenia Licence | - |
| Approved Plan ASN Gardenia | - |
| Willbeprovided | - |
| Willbeprovided | - |
| Merged RTC | - |
| Approved Section Plan Gardenia | - |
| Willbeprovided | - |
| ASN Gardenia Brochure | - |
| Gardenia Specifications | - |
| EC Merged ASN Gardenia | - |
| Affidavit | - |
| Affidavit Cum Declaration | - |
| Gardenia khatha | - |
| JDA 1 and JDA 2 | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Environment Certificate_compressed | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Approved Section Plan Gardenia | - |
| Conversion Order 1 and 2 | - |
| GARDENIA Legal Openion | - |
| Balance Sheet 2019 - 2020File: Yet to prepare audited financials and file IT returns for 2021.pdf | - |
| Balance Sheet 2018 - 2019File: BS 1920.pdf | - |
| Balance Sheet 2017 - 2018File: BS 2018-2019.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: Yet to prepare audited financials and file IT returns for 2021.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: PL 1920.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: PL 2018-2019.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: Yet to prepare audited financials and file IT returns for 2021.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: Income Tax Return Ack.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: ITR Ack 18-19_compressed.pdf | - |
| Form B | - |
| Prospectus/BrochureFile: ASN Multifolder_06-11-2021-1-2.pdf | - |
| Advertisement Copy 1File: ASN Gardenia in Horamavu, Bangalore - Price, Reviews & Floor Plan.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep ASN Gardenia on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: ASN DEVELOPERS
ASN DEVELOPERS has 1 registration on RERA Karnataka, including ASN Gardenia. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if ASN Gardenia is delayed beyond 30 Sep 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of ASN Gardenia?
The registered promoter entity is ASN DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in ASN Gardenia?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at ASN Gardenia?
The professionals named in the filing: Architect: SHUBHASHINI.T; Engineer: KUMAR C.G. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ASN Gardenia?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback