RG-KA-41591 · RERA PRM/KA/RERA/1251/472/PR/160623/005992 · Last updated on RERA Karnataka portal: 12 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2027Possession promisedno revision filed
11 of 15Construction stages donefurthest along: Dadoing, 90%
102 of 276Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 148 documents Report an error

ARYAN KRISHNAA DIVINE is a Residential/Group Housing project by Aryan Ventures in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/160623/005992 on 16 Jun 2023. Possession is promised by 30 Jun 2027. 174 of the 276 units on this registration are recorded sold or booked, and 11 of 15 construction stages are filed complete.

At a glance

Project

  • NameARYAN KRISHNAA DIVINE
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
    • 560064
  • Pincode560064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/472/PR/160623/005992
  • ReraGenie IDRG-KA-41591

Builder

  • NameAryan Ventures
  • Entity typePartnership Firm
  • Authorized SignatoryK VENKATESH NAIDU

Key dates

this monthRegisteredJun 2023PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Jun 2023
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed148 files

Current status

63%174 of 276 units booked
22.0%Of the estimated cost spent so far

Figures as on 12 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ARYAN---2760276

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 12 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 15 construction stages are filed complete. The stage furthest along is Dadoing, at 90%.

Building: 96% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)90%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing90%
Painting90%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings75%

Progress on shared amenities40

As on 12 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes75%
Sewage and Drainage SystemNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes95%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes90%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes75%
Storm water drainsYes85%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes95%
Parks & Tree plantingYes25%
Street LightingNoNot applicable
ElectricityYes80%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes25%
Club HouseYes95%
Community HallYes95%
Outdoor Sports facilityYes50%
Indoor Sports facilityYes95%
Swimming PoolYes85%
GymYes90%
ParksNoNot applicable
Power BackupYes75%
Piped GasNoNot applicable
Water and SanitationYes75%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,536 sq m
Named landowners2
LandownerVillageDistrict
P VENKATESH--
G VENKATACHAMLAM REDDY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 90.90 cr
Cost incurredRs 20.00 cr
Spent of the estimate22.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 90.00 crRs 10.81 cr
On-site expenditure-Site OverheadRs 50.00 lakh-
On-site expenditure-Consultants FeesRs 20.00 lakh-
Payment of taxesRs 20.00 lakh-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)-Rs 9.19 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectG BHANUMATHI
EngineerSRINIVAS RAO B
Chartered AccountantC VENKATESHULU

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed148

As listed on the registration, under the names the promoter filed them with; the newest 80 of 148 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/160623/005992 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Aryan Ventures RERA.pdf12 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: ARYAN VENTURES-FORM-5_0001 (3).pdf12 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: ARYAN VENTURES-FORM-6_0001 (3).pdf12 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Aryan ventures RERA CERTIFICATE (2).pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: ARYAN VENTURES- FORM- 5_0001.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: ARYAN VENTURES- FORM- 6_0001.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: ARYAN VENTURES RERA CERTIFICATE (1).pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: ARYAN VENTURES-FORM-6_0001 (2).pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: ARYAN VENTURES-FORM-5_0001 (2).pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA_compressed.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: ARYAN VENTURES-FORM-5_0001 (1).pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: ARYAN VENTURES-FORM-6_0001 (1).pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Devarajulu Financials FY 2021-22File: 1 Devarajulu Financials FY 2021-22.pdf3 Jun 2023
Devarajulu Financials FY 2020-21File: 2 Devarajulu Financials FY 2020-21.pdf3 Jun 2023
Devarajulu Financials FY 2019-20File: 3 Devarajulu Financials FY 2019-20.pdf3 Jun 2023
ASHOK NAIDU FINANCIALS FY 2021-22File: 4 ASHOK NAIDU FINANCIALS FY 2021-22.pdf3 Jun 2023
ASHOK NAIDU FINANCIALS FY 2020-21File: 5 ASHOK NAIDU FINANCIALS FY 2020-21.pdf3 Jun 2023
VENKATESH NAIDU FY 2020-21File: 7 VENKATESH NAIDU FY 2020-21.pdf3 Jun 2023
ASHOK NAIDU FINANCIALS FY 2019-20File: 8 ASHOK NAIDU FINANCIALS FY 2019-20.pdf3 Jun 2023
Saiprakruth FY 2021-22File: 9 Saiprakruth FY 2021-22.pdf3 Jun 2023
Saiprakruth FY 2020-21File: 10 Saiprakruth FY 2020-21.pdf3 Jun 2023
Saiprakruth FY 2019-20File: 11 Saiprakruth FY 2019-20.pdf3 Jun 2023
Jagadish pathi FY 2021-22File: 12 Jagadish pathi FY 2021-22.pdf3 Jun 2023
Jagadish pathi FY 2020-21File: 13 Jagadish pathi FY 2020-21.pdf3 Jun 2023
Jagadish pathi FY 2019-20File: 14 Jagadish pathi FY 2019-20.pdf3 Jun 2023
CHETHAN VENKATESH ITR 2021-22File: 15 CHETHAN VENKATESH ITR 2021-22.pdf3 Jun 2023
CHETHAN VENKATESH ITR 2020-21File: 16 CHETHAN VENKATESH ITR 2020-21.pdf3 Jun 2023
CHETHAN VENKATESH ITR 2019-20File: 17 CHETHAN VENKATESH ITR 2019-20.pdf3 Jun 2023
NITIN V FINANCIALS FY 2021-22File: 18 NITIN V FINANCIALS FY 2021-22.pdf3 Jun 2023
NITIN V FINANCIALS FY 2020-21File: 19 NITIN V FINANCIALS FY 2020-21.pdf3 Jun 2023
NITIN V FINANCIALS FY 2019-20File: 20 NITIN V FINANCIALS FY 2019-20.pdf3 Jun 2023
VENKATESH NAIDU FY 2019-20File: 21 VENKATESH NAIDU FY 2019-20.pdf3 Jun 2023
Loan Sanction LetterFile: 23 Loan Sanction Letter.pdf3 Jun 2023
Source of Funds Aryaan Krishnaa Divine with balance sheetFile: 22 Source of Funds Aryaan Krishnaa Divine with balance sheet.pdf3 Jun 2023
Form-B AffidavitFile: 1 Form-B Affidavit.pdf3 Jun 2023
JDA AffidavitFile: 2 JDA Affidavit.pdf3 Jun 2023
Sec 3(1) AffidavitFile: 3 Sec 3(1) Affidavit.pdf3 Jun 2023
Non-Litigation AffidavitFile: 4 Non-Litigation Affidavit.pdf3 Jun 2023
YALHANKA Guideline ValuesFile: 1 YALHANKA Guideline Values.pdf3 Jun 2023
Zonal Regulation 2007File: 2 Zonal Regulation 2007.pdf3 Jun 2023
Copy of Nala Clarification LetterFile: 3 Copy of Nala Clarification Letter.pdf3 Jun 2023
Relinquishment Deed clarificationFile: 4 Relinquishment Deed clarification.pdf3 Jun 2023
Approved planFile: 1 Approved plan.pdf3 Jun 2023
Location and DemarcationFile: 2 Location and Demarcation.pdf3 Jun 2023
CDP Master ExtractFile: 3 CDP Master Extract.pdf3 Jun 2023
Village Map DemarcationFile: 4 Village Map Demarcation.pdf3 Jun 2023
BESCOM NOC with fee paid receiptFile: 5 BESCOM NOC with fee paid receipt.pdf3 Jun 2023
Structural Safety CertificateFile: 6 Structural Safety Certificate.pdf3 Jun 2023
BWSSB NOC with fee paid receiptFile: 7 BWSSB NOC with fee paid receipt.pdf3 Jun 2023
Estimation SummaryFile: 8 Estimation Summary.pdf3 Jun 2023
Area StatementFile: 9 Area Statement.pdf3 Jun 2023
Clarification on Single layout Map and OrderFile: 10 Clarification on Single Layout Map and Order.pdf3 Jun 2023
Clarification on Commencement CertificateFile: 11 Clarification on Commencement Certificate.pdf3 Jun 2023
Project SpecificationFile: 12 Project Specification.pdf3 Jun 2023
STP DemarcationFile: 13 STP Demarcation.pdf3 Jun 2023
STP DrawingFile: 14 STP Drawing.pdf3 Jun 2023
Proforma Allotment LetterFile: 1 Proforma Allotment Letter.pdf3 Jun 2023
Updated Proforma Agreement of SaleFile: 2 Updated Proforma Agreement of Sale.pdf3 Jun 2023
Clarification on Height of the building mentioned in the development details pageFile: 14 Clarification on Height of the building mentioned in the development details page.pdf3 Jun 2023
RTC, survey 28-
Mutation, survey 28-
Encumbrance Certificate, survey 28-
Conversion/Alienation Order, survey 28-
Sale/Title/Gift Deed, survey 28-
JDA, survey 28-
Khatha, survey 28-
Registration CertificateFile: Aryan Ventures Partnership Deed.pdf-
Partnership DeedFile: Aryan Ventures Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: FORM-1 CA CERTIFICATE.pdf-
Certificate issued by Architect Form 2File: FORM 2.pdf-

How this compares with Bengaluru Urban

63%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ARYAN KRISHNAA DIVINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmARYAN KRISHNAA DIVINEOther 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: Aryan Ventures

Aryan Ventures has 1 registration on RERA Karnataka, including ARYAN KRISHNAA DIVINE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ARYAN KRISHNAA DIVINE is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ARYAN KRISHNAA DIVINE?

The registered promoter entity is Aryan Ventures, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ARYAN KRISHNAA DIVINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ARYAN KRISHNAA DIVINE?

The professionals named in the filing: Architect: G BHANUMATHI; Engineer: SRINIVAS RAO B; Chartered Accountant: C VENKATESHULU. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARYAN KRISHNAA DIVINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARYAN KRISHNAA DIVINE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARYAN KRISHNAA DIVINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.