Arvind Skycrest

By Arvind Smart Homes Private Limited

RG-KA-81205 · RERA PRM/KA/RERA/1251/310/PR/230326/008543 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2031Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Earth work and other leveling..., 70%
136 of 333Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 122 documents Report an error

Arvind Skycrest is a Residential/Group Housing project by Arvind Smart Homes Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/230326/008543 on 23 Mar 2026. Possession is promised by 31 Mar 2031. 197 of the 333 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.

At a glance

Project

  • NameArvind Skycrest
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560080
  • Pincode560080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/230326/008543
  • ReraGenie IDRG-KA-81205

Builder

  • NameArvind Smart Homes Private Limited
  • Entity typeCompany
  • CINU70109GJ2022PTC134678
  • GSTIN29AAXCA4716D1ZE
  • Authorized SignatoryManoj Chellani
  • DirectorsManoj Chellani, Prakash Bhogi Makwana, Sharvil Saurabh Shah
  • Project HeadSundaresha GM
  • Other registrations1 more →

Key dates

this monthRegisteredMar 2026PromisedMar 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 Mar 2026
  • Promised completion31 Mar 2031
  • Revised completionNone
  • Buildings5 building records
  • Documents filed122 files

Current status

59%197 of 333 units booked
15.3%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---67067
Tower B---66066
Tower C---66066
Tower D---67067
Tower E---67067

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 70%.

Building: 4% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work70%
Foundation footing work0%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,576 sq m
Named landowners2
LandownerVillageDistrict
M/s. Arvind Smart Homes Private Limited--
M/s. Arvind Smart Homes Private Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 154.04 cr
Cost incurredRs 23.55 cr
Spent of the estimate15.29%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 107.80 crRs 5.10 cr
Payment of taxesRs 19.40 crRs 4.00 cr
On-site expenditure-Consultants FeesRs 16.67 crRs 14.45 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 10.17 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectApurva Amin Architects
EngineerB.E. Pruthviraja
Chartered AccountantAmit R. Jain

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed122

As listed on the registration, under the names the promoter filed them with; the newest 80 of 122 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/230326/008543 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Skycrest_Form-4_CA Certificate.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Architect CERTIFICATE - SKYCREST.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q2 2026-27 Fire and Safety13 Oct 2026
Q2 2026-27 Airport Authority of India13 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Arvind Skycrest Form -4-CA-JUNE-26_V3.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 - Arvind Skycrest Architect Certificate.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 - Arvind Skycrest Engineer Certificate.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Q4-CA Certificate Arvind Skycrest 310326.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 - Arvind Skycrest (1).pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 - Arvind Skycrest (1).pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Conversion OrderFile: Conversion documents.pdf20 Mar 2026
Order passed in WP No 7508-2016File: Order passed in WP No 7508-2016.pdf20 Mar 2026
BDA NOCFile: BDA- NOC.pdf20 Mar 2026
STP DRAWINGFile: STP DRAWING.pdf20 Mar 2026
STRUCTURAL STABILITY CERTIFICATEFile: Structure Stability Certificate - Bannerghatta.pdf20 Mar 2026
APPROVED TYPICAL SANCTIONED PLANFile: Plans Site Typical Terrace.pdf20 Mar 2026
AREA STATEMENT MARKEDFile: AREA STATEMENT AS PER PLAN.png20 Mar 2026
Engineer LicenceFile: Engineer Licence.pdf20 Mar 2026
Form-1 CA Certificate UpdatedFile: CA Certificate Arvind Skycrest_Updated.pdf29 Jan 2026
Self Attested PANFile: Arvind SmartHomes - PAN - Self Attested.pdf29 Jan 2026
Section 3 AffidavitFile: Affidavit - Section-3.pdf29 Jan 2026
Non Litigation AffidavitFile: Affidavit - Non-Litigation.pdf29 Jan 2026
EC till dateFile: ECC-from 01-04-2011 To 02-01-2026.pdf29 Jan 2026
BBMP E KathaFile: E-Khatha - Bannerghatta Road-Gottigere.pdf29 Jan 2026
Single Plot layout planFile: Approved Development Plan.pdf29 Jan 2026
Single Plot layout plan orderFile: DP Work Order.pdf29 Jan 2026
Building LicenseFile: License.pdf29 Jan 2026
ADLR Certified survey sketch 11-3File: Conversion sketch- Sy No 11-3.pdf29 Jan 2026
ADLR Certified survey sketch 11-7File: Conversion sketch- Sy No 11-7.pdf29 Jan 2026
Demarcation of Land - Gottigere ProjectFile: Demarcation of Land - Gottigere Project.pdf29 Jan 2026
Location - Longitude-LatitudeFile: Location - Longitude-Latitude.pdf29 Jan 2026
Realignment Order sketchFile: Realignment Order sketch (color) - Gottigere.pdf29 Jan 2026
Google MapFile: Gotigere-Goggle.pdf29 Jan 2026
Sanctioned DrawingsFile: Approved Development Plan.pdf29 Jan 2026
Approved Master planFile: Demarcation of Land - Gottigere Project.pdf29 Jan 2026
Village Map DemarcatedFile: Gotigere-Village Map.pdf29 Jan 2026
Structural stability certificateFile: Structural Stability Certificate.PDF29 Jan 2026
Engineer LicenceFile: Pruthivraja- BBMP.PDF29 Jan 2026
Project specificationsFile: Project Specification.pdf29 Jan 2026
Proforma of agreement UpdatedFile: Arvind Agreement for Sale Updated.pdf29 Jan 2026
Proforma Allotment letterFile: Arvind Allotment Letter Updated.pdf29 Jan 2026
Amenities detailsFile: AMENITIES OF PROJECT ARVIND SKYCREST- Scan copy.pdf29 Jan 2026
STP drawingFile: PR_ARVIND UG SUMP & STP DRAWING.pdf29 Jan 2026
Water supply NOCFile: Arvind Smarthomes BWSSB NOC.pdf29 Jan 2026
BDA Plan Sanction LetterFile: BDA - Approval letter.pdf29 Jan 2026
Approved BDA Sanctioned Plan DrawingsFile: Approved - BDA - Plan.pdf29 Jan 2026
Sanctioned Plans - Site - Typical - TerraceFile: Plans - Site - Typical - Terrace.pdf29 Jan 2026
Sanctioned Section and Elevation DrawingsFile: Section & Elevation.pdf29 Jan 2026
PROJECT ESTIMATIONFile: Construction Estimate - Skycrest.pdf29 Jan 2026
LAND COST CALCULATIONFile: Land cost calculations.pdf29 Jan 2026
Guidance Value CertificateFile: Guidance - Jayanagar SR Value.pdf29 Jan 2026
RTC, survey 11/3-
Mutation, survey 11/3-
Encumbrance Certificate, survey 11/3-
Conversion/Alienation Order, survey 11/3-
Sale/Title/Gift Deed, survey 11/3-
Khatha, survey 11/3-
RTC, survey 11/7-
Mutation, survey 11/7-
Encumbrance Certificate, survey 11/7-

How this compares with Bengaluru Urban

59%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Arvind Skycrest on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmArvind SkycrestOther 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 34 registered projects within 2 km.

Builder: Arvind Smart Homes Private Limited

Arvind Smart Homes Private Limited has 2 registrations on RERA Karnataka, including ARVIND ORCHARDS and Arvind Skycrest. Its filings disclose no earlier RERA Karnataka projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Arvind Skycrest is delayed beyond 31 Mar 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Arvind Skycrest?

The registered promoter entity is Arvind Smart Homes Private Limited, a company as per the filing. Its CIN U70109GJ2022PTC134678 and GSTIN 29AAXCA4716D1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Arvind Skycrest?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Arvind Skycrest?

The professionals named in the filing: Architect: Apurva Amin Architects; Engineer: B.E. Pruthviraja; Chartered Accountant: Amit R. Jain. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Arvind Skycrest?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Arvind Skycrest. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Arvind Skycrest to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.