Registration approved Residential/Group Housing project

Arvind Oasis

By Arvind Infracon LLP

RG-KA-66115 · RERA PRM/KA/RERA/1251/309/PR/180425/001543

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2023Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 76 documents Report an error

Arvind Oasis is a Residential/Group Housing project by Arvind Infracon LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180425/001543 on 25 Apr 2018. Possession is promised by 31 Dec 2023. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameArvind Oasis
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/180425/001543
  • ReraGenie IDRG-KA-66115

Builder

  • NameArvind Infracon LLP
  • Entity typePartnership Firm
  • Authorized SignatorySharath Fasalkar
  • OthersSailendra Punukollu

Key dates

this monthRegisteredApr 2018First promiseMar 2023Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on25 Apr 2018
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 31 Mar 2023)
  • Buildings6 building records
  • Documents filed76 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---76076
B---76076
C---74074
D---74074
E---76076
F---76076

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,770 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 129.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectApurva Amin Architects
EngineerDUCON Consultants Pvt. Ltd. through Dr. Shantaraju K.

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2023 → Dec 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed76

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180425/001543 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Incorporation certificate.pdf-
9Comencement Certi-
Sanctioned-Drawing_Typical--
Layout plan Sanctioned Drawing_Site Plan2-
18Sale Deed-
12Agreement to Sell -
13Sale deed of land-
Sanctioned-Drawibng_Section-
15Area Development Plan of Project-
16Allotment Letter-
17Arvind Oasis Brochure-
19Specifications-
Encumbrance Certificate-
22Khata-
20Collaboration Agreement-
23Khatha & Extract-
25Conversion Certificate-
26NOC KTCP-
49Utilisation certificate-
50Transfer of development rights certificate-
51Relinquishment Deed-
27FIRE NOC-
28Airport authority of India NOC-
29BESCOM NOC-
30BWSSB NOC-
31KSPCB- NOC-
32SEIAA NOC-
33BSNL NOC-
47NOC neighbouring properties-
Unnamed document-
40Urban Land Ceiling-
39BMRCL NOC-
42Bangalore Urban Arts Commission-
43Inspector Of Factories Controller Of Explosives Railways-
44Dist Magistrate-
45Coastal Regulation Zone Authority-
46structural safety of the building-
41SanctionedSection and Elevation-
36Layout plan Sanctioned Site Plan-
37Sanctioned Section and Elevation-
38changeofland use co-
Title TCR-
Balance Sheet 2016 - 2017File: 1Balance Sheet20162017.pdf-
Balance Sheet 2015 - 2016File: 1Balance Sheet20152016.pdf-
Balance Sheet 2014 - 2015File: 1Balance Sheet20142015.pdf-
Audited Profit and Loss Statement 2016 - 2017File: 2Profit & Loss Account Statement201162017.pdf-
Audited Profit and Loss Statement 2015 - 2016File: 2Profit & Loss Account Statement20152016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: 2Profit & Loss Account Statement20142015.pdf-
Director's Report 2016 - 2017File: 3Directors Report201720162015.pdf-
Director's Report 2015 - 2016File: 3Directors Report201720162015.pdf-
Director's Report 2014 - 2015File: 3Directors Report201720162015.pdf-
Cash Flow Statement 2016 - 2017File: 4Cash Flow Statement 201720162015.pdf-
Cash Flow Statement 2015 - 2016File: 4Cash Flow Statement 201720162015.pdf-
Auditor's Report 2016 - 2017File: 5annual report audited 20162017.pdf-
Auditor's Report 2015 - 2016File: 5annual report audited20152016.pdf-
Auditor's Report 2014 - 2015File: 5annual report audited 20142015.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: 6Income Tax Ack20172018.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: 6Income Tax Ack20162017.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: 6income tax Ack20152016.pdf-
21Declaration-
Prospectus/BrochureFile: 17Arvind Oasis Brochure.pdf-
Advertisement Copy 1File: Oasis-jacket Ad Back-01.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_180425_001543.xlsx-
Change in inventory/specification detailsFile: Change in Inventory details.pdf-
Stability CertificateFile: Stability Certificate.jpg-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: BWSSB NOC.pdf-
NOC issued by the Fire Force department after completion of workFile: FIRE Clearence certificate.pdf-
Occupancy CertificateFile: Occupancy certificate.pdf-
Consent for operation issued by KSPCBFile: KSPCB NOC.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM NOC.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: BWSSB NOC.pdf-
Architect certificate for having completed the work(in format no 5)File: Architect Certificate.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: CA Certificate.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Project Completion Affidavit.pdf-
Engineer CertificateFile: Engineer Certificate.pdf-
Sanction DrawingFile: Sanction Drawing.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Arvind Oasis on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Arvind Infracon LLP

Arvind Infracon LLP has 1 registration on RERA Karnataka, including Arvind Oasis. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Arvind Oasis is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Arvind Oasis?

The registered promoter entity is Arvind Infracon LLP, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Arvind Oasis?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Arvind Oasis?

The professionals named in the filing: Architect: Apurva Amin Architects; Engineer: DUCON Consultants Pvt. Ltd. through Dr. Shantaraju K.. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Arvind Oasis?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Arvind Oasis. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Arvind Oasis to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.