Home / Browse projects / Bengaluru Urban, Karnataka / ANTALIEA HOMES 1
ANTALIEA HOMES 1
By C Satish Kumar, C Raghavendra and B V Sreenivasulu
RG-KA-24727 · RERA PRM/KA/RERA/1251/309/PR/190829/002839
Source: official RERA Karnataka filing
Red flags
- 2 complaints at RERA Karnataka
- Completion date moved by 9 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
ANTALIEA HOMES 1 is a Residential/Group Housing project by C Satish Kumar, C Raghavendra and B V Sreenivasulu in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/190829/002839 on 29 Aug 2019. Possession is promised by 15 Dec 2024. The completion date has moved by 9 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameANTALIEA HOMES 1
- TypeResidential/Group Housing
- Location
- Bengaluru North
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/309/PR/190829/002839
- ReraGenie IDRG-KA-24727
Builder
- NameC Satish Kumar, C Raghavendra and B V Sreenivasulu
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on29 Aug 2019
- Promised completion15 Dec 2024
- Revised completionRevised to 15 Dec 2024 (originally 15 Mar 2024)
- Buildings1 building record
- Documents filed52 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ANTALIEA HOMES 1 | - | - | - | 68 | 0 | 68 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Akanksha Kher |
| Engineer | HARISH REDDY B |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 01316/2024 | - | C Satish Kumar, C Raghavendra and B V Sreenivasulu | 19/12/2024 |
| 01376/2024 | - | C Satish Kumar, C Raghavendra and B V Sreenivasulu | 31/12/2024 |
Documents filed52
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/190829/002839 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| SIZE OF COMMENCEMENT CERTIFICATE IS ABOUT 10 MB | - |
| Marked Layout Plan 68 Plots | - |
| ALL VILLA PLANS | - |
| Proforma - Absolute Sale Deed | - |
| Proforma - Agreement to Sell | - |
| PD SD COURT ORDER RD RTC | - |
| CLUB HOUSE PLOTS PLAN 1MB | - |
| Land Owners - Agreement | - |
| Proforma - Allotment Letter | - |
| Plan Approval | - |
| VILLA SPECIFICATIONS | - |
| SIZE OF EC IS ABOUT 27 MB and is uploaded in JD AFFIDAVIT CUM DECLARATION | - |
| SECTION 3(1) AFFIDAVIT Notarized | - |
| EC 27MB | - |
| SIZE OF KHATA IS ABOUT 27 MB | - |
| COURT ORDERS and LAND OWNER AGREEMENT MOU | - |
| MR RTC AKARBAND TIPPANY | - |
| CONVERSION ORDER | - |
| RELINQUISHMENT DEED | - |
| BESCOM NOC | - |
| BWSSB NOC | - |
| Unnamed document | - |
| KHATA RTC | - |
| ALL EC 27MB | - |
| CC 10MB | - |
| CONVERSION ORDER | - |
| Balance Sheet 2017 - 2018File: SATISH BS 17 18.pdf | - |
| Balance Sheet 2016 - 2017File: SATISH ITR 16 17.pdf | - |
| Balance Sheet 2015 - 2016File: SATISH BS 15 16.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: SATISH PL 17 18.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: SATISH PL 16 17.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: SATISH PL 15 16.pdf | - |
| Cash Flow Statement 2017 - 2018File: ALL 2017 18.pdf | - |
| Cash Flow Statement 2016 - 2017File: ALL 2016 17.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: ALL SATISH ITR.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ALL SRINIVASULU ITR.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ALL RAGHU ITR.pdf | - |
| FORM B AFFIDAVIT | - |
| Prospectus/BrochureFile: Brochure.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_190829_002839_68 Units.xlsx | - |
| Occupancy CertificateFile: Villa 06 OC.pdf | - |
| Consent for operation issued by KSPCBFile: Refusal Order (NOC) for CTO.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: C Satish BESCOM NOC.pdf | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: BWSSB NOC .pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Form-5 Architect Certificate.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Form-4 CA Completion certificate.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit.pdf | - |
| BESCOM NOCFile: C Raghavendra BESCOM NOC.pdf | - |
| BESCOM NOCFile: B V Sreenivasulu BESCOM.pdf | - |
| OCFile: Villa 13 OC.pdf | - |
| OCFile: Villa 93 OC.pdf | - |
| OCFile: Villa 12 OC.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep ANTALIEA HOMES 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 41 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: C Satish Kumar, C Raghavendra and B V Sreenivasulu
C Satish Kumar, C Raghavendra and B V Sreenivasulu has 1 registration on RERA Karnataka, including ANTALIEA HOMES 1. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if ANTALIEA HOMES 1 is delayed beyond 15 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of ANTALIEA HOMES 1?
The registered promoter entity is C Satish Kumar, C Raghavendra and B V Sreenivasulu. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in ANTALIEA HOMES 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ANTALIEA HOMES 1?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at ANTALIEA HOMES 1?
The professionals named in the filing: Architect: Akanksha Kher; Engineer: HARISH REDDY B. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ANTALIEA HOMES 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback