Home / Browse projects / Bengaluru Urban, Karnataka / AMIGO ESTELLA
AMIGO ESTELLA
RG-KA-66962 · RERA PRM/KA/RERA/1251/472/PR/181103/002128
Source: official RERA Karnataka filing
Red flags
- 1 complaint at RERA Karnataka
- Completion date moved by 33 months
- 3 extensions taken
Clear
- Separate project account declared
Saved.
AMIGO ESTELLA is a Residential/Group Housing project by AMIGOESTELLA INDIA LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/181103/002128 on 3 Nov 2018. Possession is promised by 30 Jun 2023. The completion date has moved by 33 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameAMIGO ESTELLA
- TypeResidential/Group Housing
- Location
- Yelahanka
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/472/PR/181103/002128
- ReraGenie IDRG-KA-66962
Builder
- NameAMIGOESTELLA INDIA LLP
- Entity typeCompany
- Authorized SignatoryMOHAMMED HAMZA ALI
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on3 Nov 2018
- Promised completion30 Jun 2023
- Revised completionRevised to 30 Jun 2023 (originally 30 Sep 2020)
- Buildings7 building records
- Documents filed62 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING-A | - | - | - | 16 | 0 | 16 |
| WING -B | - | - | - | 20 | 0 | 20 |
| WING-C | - | - | - | 25 | 0 | 25 |
| WING-D | - | - | - | 19 | 0 | 19 |
| WING-E | - | - | - | 25 | 0 | 25 |
| WING-F | - | - | - | 25 | 0 | 25 |
| WING-G | - | - | - | 25 | 0 | 25 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterForce Majeure
No reason recorded in the filing
Complaints filed with RERA Karnataka1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 01022/2024 | - | AMIGOESTELLA INDIA LLP | 18/10/2024 |
Documents filed62
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/181103/002128 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Certificate of LLP Incorporation.PDF | - |
| Project Details | - |
| Architect Certificate for Work Completion Schedule till DateFile: Arc Certificate - Status of Work.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Eng Certificate - Status of Work.pdf | - |
| CA Certificate for Funds UtilizationFile: CA Certificate- Fund Utilization.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Arc Certificate - Pending Work.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Eng Certificate - Pending Work.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: CA Certificate- Funds Required.pdf | - |
| AffidavitFile: Form B.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: Sold and Unsold Unit Details.xlsx | - |
| Document 1File: BWSSB NOC.pdf | - |
| Document 2File: OC - Amigo Estella.pdf | - |
| Document 3File: CFO - KSPCB (Estella).pdf | - |
| Document 4File: SEIAA - AMIGO ESTELLA.pdf | - |
| Untitled-2 | - |
| PLOTTING PLAN | - |
| Site Plan | - |
| Sale Deed Draft | - |
| AGREEMENT DRAFT | - |
| SALE DEED | - |
| PLOTTING PLAN | - |
| Village Map | - |
| ALLOTMENT letter | - |
| Amigo Estella - E-Brochure | - |
| Specifications | - |
| EC_01-04-2004 To 11-09-2018 (2) | - |
| KATHA | - |
| JDA Agreement | - |
| Site Plan | - |
| Section Plan | - |
| CONVERSATION ORDER (2) | - |
| Balance Sheet 2016 - 2017File: Untitled-1.pdf | - |
| Balance Sheet 2015 - 2016File: Untitled-1.pdf | - |
| Balance Sheet 2014 - 2015File: Untitled-1.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: Untitled-1.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: Untitled-1.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Untitled-1.pdf | - |
| Director's Report 2016 - 2017File: Untitled-1.pdf | - |
| Director's Report 2015 - 2016File: Untitled-1.pdf | - |
| Director's Report 2014 - 2015File: Untitled-1.pdf | - |
| Cash Flow Statement 2016 - 2017File: Untitled-1.pdf | - |
| Cash Flow Statement 2015 - 2016File: Untitled-1.pdf | - |
| Auditor's Report 2016 - 2017File: Untitled-1.pdf | - |
| Auditor's Report 2015 - 2016File: Untitled-1.pdf | - |
| Auditor's Report 2014 - 2015File: Untitled-1.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: Untitled-1.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: Untitled-1.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: Untitled-1.pdf | - |
| scan | - |
| Prospectus/BrochureFile: Brochure.pdf | - |
| Advertisement Copy 1File: Advertisement.JPG | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_472_PR_181103_002128.xlsx | - |
| Loan raised documentFile: Mortgage Closure NOC.PDF | - |
| Occupancy CertificateFile: OC - Amigo Estella.pdf | - |
| Consent for operation issued by KSPCBFile: KSPCB CFO.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM NOC.pdf | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: BWSSB NOC.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Estella Arch Closure 2023-2024.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: FORM 4 C C (Closure) - Estella.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Closure Affidavit Estella.pdf | - |
| Estella Eng Closure 2023-2024File: Estella Eng Closure 2023-2024.pdf | - |
| SEIAA NOCFile: SEIAA NOC.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep AMIGO ESTELLA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 46 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: AMIGOESTELLA INDIA LLP
AMIGOESTELLA INDIA LLP has 1 registration on RERA Karnataka, including AMIGO ESTELLA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if AMIGO ESTELLA is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of AMIGO ESTELLA?
The registered promoter entity is AMIGOESTELLA INDIA LLP, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in AMIGO ESTELLA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AMIGO ESTELLA?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
What should I check before booking in AMIGO ESTELLA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback