ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / AMBHAVILAS RESIDENCY

Registration approved No litigation declared Residential/Group Housing project

AMBHAVILAS RESIDENCY

By SHREE JNANAKSHI BUILDERS AND DEVELOPERS

RG-KA-38132 · RERA PRM/KA/RERA/1251/310/PR/281022/005367 · Last updated on RERA Karnataka portal: 6 Oct 2022

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2024Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 85 documents Report an error

AMBHAVILAS RESIDENCY is a Residential/Group Housing project by SHREE JNANAKSHI BUILDERS AND DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/281022/005367 on 28 Oct 2022. Possession is promised by 24 Jun 2024.

At a glance

Project

  • NameAMBHAVILAS RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/281022/005367
  • ReraGenie IDRG-KA-38132

Builder

  • NameSHREE JNANAKSHI BUILDERS AND DEVELOPERS
  • Entity typeProprietorship Firm
  • GSTIN29AEEPC5287M2Z0
  • Authorized SignatoryCHAKRAVARTHI D
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2022PromisedJun 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Oct 2022
  • Promised completion24 Jun 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed85 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AMBHAVILAS RESIDENCY---16016

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 6 Oct 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 6 Oct 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
R SOMASHEKAR--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.66 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 5.62 cr-
On-site expenditure-Consultants FeesRs 4.50 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANTHOSH B SHETTY
EngineerROSHAN
Chartered AccountantT R MAHESH

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed85

As listed on the registration, under the names the promoter filed them with; the newest 80 of 85 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/281022/005367 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
BWSSB Noc with fee receiptFile: BWSSB Noc with fee receipt.pdf6 Oct 2022
GSTFile: 1 GST.pdf13 Sep 2022
BS 2020 21File: 2 BS 2020 21.pdf13 Sep 2022
PL 2020 21File: 2 PL 2020 21.pdf13 Sep 2022
BS 2018 19File: 3 BS 2018 19.pdf13 Sep 2022
PL 2018 19File: 3 PL 2018 19.pdf13 Sep 2022
MR 27 2004 05File: 4 MR 27 2004 05.pdf13 Sep 2022
Sale deedFile: 5 Sale deed.pdf13 Sep 2022
Title FlowFile: 5 Title Flow.pdf13 Sep 2022
Non LitigationFile: 6 Non Litigation.pdf13 Sep 2022
ConversionFile: 7 Conversion.pdf13 Sep 2022
Single Plot Layout DeclarationFile: 8 Single Plot Layout Declaration.pdf13 Sep 2022
Single Plot Layout Order DeclarationFile: 9 Single Plot Layout Order Declaration.pdf13 Sep 2022
KSPCB Noc DeclarationFile: 10 KSPCB Noc Declaration.pdf13 Sep 2022
Water Noc with Fee ReceiptFile: 11 Water Noc with Fee Receipt.pdf13 Sep 2022
RTC, survey 20/12-
Mutation, survey 20/12-
Encumbrance Certificate, survey 20/12-
Conversion/Alienation Order, survey 20/12-
Sale/Title/Gift Deed, survey 20/12-
JDA, survey 20/12-
Khatha, survey 20/12-
Registration CertificateFile: GST.pdf-
Certificate issued by CA Form 1File: Form 1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form 2 Architect.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engineer certi.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation.pdf-
Certificate from Chartered AccountFile: Form 1 CA Certificate.pdf-
Balance Sheet 2019 - 2020File: BS.pdf-
Balance Sheet 2018 - 2019File: BS.pdf-
Audited Profit and Loss Statement 2019 - 2020File: PL.pdf-
Audited Profit and Loss Statement 2018 - 2019File: PL.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR.pdf-
COMMENSEMENT CERTI-
BESCOM NOC-
WATER-
APPROVED BUILDING PLAN-
SECTION PLAN AND SPECIFICATION-
APPROVED BUILDING PLAN-
SPECIFICATION-
APPROVED BUILDING PLAN-
CDP PLAN-
STRUCTURAL STABILITY-
LEGAL REPORT-
JDA-
CONVERSION-
PROFORMA OF AOS-
Allotment Letter-
Form B-
Section 3 1-
JDA Affidavit-
BESCOM NOC-
WATER-
AAKARBAND-
DEATH CERTI MUTHAIA-
DEATH CERTI RUDHRAIA-
FAMILY TREE-
HIMBHARAHA-
HISSA PHODY-
SINGLE PLOT-
GUIDANCE VALUE-
STP DRAWING, SEWER LINE AND WATER LINE-
GPA-
No Mortgage-
BUILDING LICENSE-
PROFORMA OF SALE DEED-
MASTER PLAN-
VILLAGE MAP-
COPY OF ENDORSEMENT-
SHARING AGREEMENT-
ABSTRACT ESTIMATION-
Stability CertificateFile: STRUCTURAL STABILITY.pdf-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: BWSSB Noc.pdf-
Occupancy CertificateFile: OCCUPANCY CERTIFICATE.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: BESCOM NOC.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM NOC.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep AMBHAVILAS RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SHREE JNANAKSHI BUILDERS AND DEVELOPERS

SHREE JNANAKSHI BUILDERS AND DEVELOPERS has 2 registrations on RERA Karnataka, including AMBHA BHAVANI RESIDENCY and AMBHAVILAS RESIDENCY. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if AMBHAVILAS RESIDENCY is delayed beyond 24 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of AMBHAVILAS RESIDENCY?

The registered promoter entity is SHREE JNANAKSHI BUILDERS AND DEVELOPERS, a proprietorship firm as per the filing. Its GSTIN 29AEEPC5287M2Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in AMBHAVILAS RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AMBHAVILAS RESIDENCY?

The professionals named in the filing: Architect: SANTHOSH B SHETTY; Engineer: ROSHAN; Chartered Accountant: T R MAHESH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AMBHAVILAS RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AMBHAVILAS RESIDENCY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AMBHAVILAS RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.