Alibaug Townhouses
RG-MH-23545 · RERA P52000078856 · Last updated on MahaRERA portal: 23 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 178 other registrations.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Alibaug Townhouses is a Others project by Lodha Developers Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000078856 on 15 Jan 2025. Possession is promised by 31 Aug 2029. 3 of the 36 units on this registration are recorded sold or booked, and 0 of 440 construction stages are filed complete.
At a glance
Project
- NameAlibaug Townhouses
- TypeOthers
- Location
- Dhokwade
- Dhokawade
- Alibag
- Raigarh
- 402208
- Pincode402208
- RERA no.P52000078856
- ReraGenie IDRG-MH-23545
Builder
- NameLodha Developers Limited
- Entity typeCompany
- CINL45200MH1995PLC093041
- GSTIN27AAACL1490J1ZG
- WtdRaunika Malhotra
- Other registrations178 more →
- Completed16 of 179
- No longer live3 lapsed, de-registered or revoked
- Past their filed date3
- Declared earlier projects22 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Jan 2025
- Promised completion31 Aug 2029
- Revised completionNone
- Buildings40 building records
- Documents filed44 files
Current status
Figures as on 23 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Villa 1 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 2 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 3 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 4 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 5 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 6 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 7 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 8 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 9 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 10 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 11 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 12 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 41 | NA | 5 | 0 | 0 | 0 | 0 |
| Villa 14 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 15 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 16 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 17 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 18 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 19 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 20 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 21 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 22 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 23 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 24 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 25 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 26 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 27 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 28 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 29 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 30 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 31 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 32 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 33 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 34 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 35 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 36 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 37 | NA | 4 | 4 | 1 | 0 | 1 |
| Villa 38 | NA | 4 | 0 | 0 | 0 | 0 |
| Villa 39 | NA | 4 | 0 | 0 | 0 | 0 |
| Villa 40 | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 40 buildings; the table lists the first 20.
0 of 440 construction stages are filed complete across 40 buildings. The stage furthest along is Excavation, at 80%.
Villa 17%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 27%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 37%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 47%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 57%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 67%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 77%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 87%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 97%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 107%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 117%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 127%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 417%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 147%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 157%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 167%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 177%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 187%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 197%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Villa 207%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed121
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Villa 1 | 0 | 3 | 3 |
| Villa 2 | 0 | 3 | 3 |
| Villa 3 | 0 | 3 | 3 |
| Villa 4 | 0 | 3 | 3 |
| Villa 5 | 0 | 3 | 3 |
| Villa 6 | 0 | 3 | 3 |
| Villa 7 | 0 | 3 | 3 |
| Villa 8 | 0 | 3 | 3 |
| Villa 9 | 0 | 3 | 3 |
| Villa 10 | 0 | 3 | 3 |
| Villa 11 | 0 | 3 | 3 |
| Villa 12 | 0 | 3 | 3 |
| Villa 41 | 1 | 3 | 4 |
| Villa 14 | 0 | 3 | 3 |
| Villa 15 | 0 | 3 | 3 |
| Villa 16 | 0 | 3 | 3 |
| Villa 17 | 0 | 3 | 3 |
| Villa 18 | 0 | 3 | 3 |
| Villa 19 | 0 | 3 | 3 |
| Villa 20 | 0 | 3 | 3 |
| Villa 21 | 0 | 3 | 3 |
| Villa 22 | 0 | 3 | 3 |
| Villa 23 | 0 | 3 | 3 |
| Villa 24 | 0 | 3 | 3 |
| Villa 25 | 0 | 3 | 3 |
| Villa 26 | 0 | 3 | 3 |
| Villa 27 | 0 | 3 | 3 |
| Villa 28 | 0 | 3 | 3 |
| Villa 29 | 0 | 3 | 3 |
| Villa 30 | 0 | 3 | 3 |
| Villa 31 | 0 | 3 | 3 |
| Villa 32 | 0 | 3 | 3 |
| Villa 33 | 0 | 3 | 3 |
| Villa 34 | 0 | 3 | 3 |
| Villa 35 | 0 | 3 | 3 |
| Villa 36 | 0 | 3 | 3 |
| Villa 37 | 0 | 3 | 3 |
| Villa 38 | 0 | 3 | 3 |
| Villa 39 | 0 | 3 | 3 |
| Villa 40 | 0 | 3 | 3 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Sobo Estate Development Private Limited | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Villa 1 | NA | Rs 4.02 cr | Rs 74.32 lakh |
| Villa 2 | NA | Rs 4.02 cr | Rs 74.32 lakh |
| Villa 3 | NA | Rs 4.02 cr | Rs 74.32 lakh |
| Villa 4 | NA | Rs 4.02 cr | Rs 74.32 lakh |
| Villa 5 | NA | Rs 4.02 cr | Rs 74.32 lakh |
| Villa 6 | NA | Rs 4.02 cr | Rs 74.32 lakh |
| Villa 7 | NA | Rs 4.02 cr | Rs 74.32 lakh |
| Villa 8 | NA | Rs 4.02 cr | Rs 74.32 lakh |
| Villa 9 | NA | Rs 4.02 cr | Rs 74.32 lakh |
| Villa 10 | NA | Rs 4.02 cr | Rs 74.32 lakh |
| Villa 11 | NA | Rs 4.02 cr | Rs 74.32 lakh |
| Villa 12 | NA | Rs 4.02 cr | Rs 74.32 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vilas Desai & Associate |
| Architect | Pradeep Kamble |
| Engineer | K C Shah Consultants |
| Engineer | Akash Palkar |
| Chartered Accountant | Chirag Sarvaiya & Co |
| Chartered Accountant | M S K A & Associates |
| Partner | Role in project |
|---|---|
| Lodha Developers Limited | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Dec 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Jun 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Aug 2029
Documents filed44
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A - Alibaug Townhouses - P52000078856.pdf | 23 Jun 2026 |
| Withdrawal Update Form 1File: Form1 - Alibaug Townhouses - P52000078856.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: Alibaug TH Form 2.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: Alibaug Townhouses Form 3.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: _fORM-1 tOWNHOUSES-.pdf | 23 Jan 2026 |
| Withdrawal Update Form 2File: Alibaug Townhouse Form 2.pdf | 23 Jan 2026 |
| Withdrawal Update Form 3File: Alibaug TH Form-3.pdf | 23 Jan 2026 |
| Withdrawal Update Form 1File: Form-1 Townhouses -Sep-25.pdf | 26 Oct 2025 |
| Withdrawal Update Form 2File: Alibaug Townhouses - Form 2.pdf | 26 Oct 2025 |
| Withdrawal Update Form 3File: Alibaug Townhouses - Form 3.pdf | 26 Oct 2025 |
| Form 5 (FY 2024-2025)File: Alibaug Townhouses.pdf | 13 Oct 2025 |
| Layout approvalFile: Townhouses RERA upload.pdf | 24 Jun 2025 |
| Form 1File: Form 1 -Mar 25-Alibaug Project.pdf | 27 May 2025 |
| Form 2File: Declaration Form 2 3 - alibaug Project.pdf | 27 May 2025 |
| Form 3File: Declaration Form 2 3 - alibaug Project.pdf | 27 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold - Alibaug Project.pdf | 27 May 2025 |
| Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate.pdf | 10 Jan 2025 |
| Other - TechnicalFile: 1 Other - Technical (1).pdf | 10 Jan 2025 |
| Other - TechnicalFile: Devki MDL Authority for RERA Registration.pdf | 10 Jan 2025 |
| Building plan approvalFile: 20241211 - Alibaug - Amended CC (Sheet No -18) - converted.pdf | 27 Dec 2024 |
| Layout approvalFile: Superimposed-Approved Layout-Model - converted.pdf | 27 Dec 2024 |
| PAN CardFile: 1 PAN Card (7).pdf | 27 Dec 2024 |
| Copy of the legal title reportFile: Title Report RERA New Format-Alibaug_Townhouse Final.pdf | 27 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Finace Encum.pdf | 27 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Legal Encum.pdf | 27 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: Superimposed-Approved Layout-Model - converted.pdf | 27 Dec 2024 |
| Proforma of Allotment letterFile: Proforma of Allotment letter.pdf | 27 Dec 2024 |
| Declaration in FORM BFile: 1 Declaration in FORM B.pdf | 27 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 27 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 27 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: 20241211 - Alibaug - Amended CC.pdf | 27 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 20241211 - Alibaug - Amended CC (Sheet No -18) - converted.pdf | 27 Dec 2024 |
| Other - LegalFile: 2 Other - Legal.pdf | 27 Dec 2024 |
| Other - LegalFile: 1 Other - Legal.pdf | 27 Dec 2024 |
| CERSAI detailsFile: Cersai Declaration.pdf | 27 Dec 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: 1 Declaration about all RERA Designated Bank Accounts (Format A) (5).pdf | 27 Dec 2024 |
| Deviation Report with respect to Allotment letterFile: ilovepdf_merged (13)_removed.pdf | 27 Dec 2024 |
| Details of encumbrances concerned to LegalFile: Finace Encum.pdf | 27 Dec 2024 |
| Details of encumbrances concerned to LegalFile: Legal Encum.pdf | 27 Dec 2024 |
| Deviation Report with respect to model copy of AgreementFile: Final - AFS Deviation -Alibaug Townhouses F.pdf | 27 Dec 2024 |
| Proforma of Agreement for saleFile: AFS Alibauug TownTownhouses F.pdf | 27 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations (9).pdf | 27 Dec 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Bank Declaration.pdf | 27 Dec 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Secure unsecure.pdf | 27 Dec 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Liana BP51700033964 | Dombivali, Thane | Mar 2022 | Completed | Feb 2026 | Jun 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 178 other registrations, which the RERA portal never shows together
- All 44 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Alibaug Townhouses on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dhokawade5,900+ in Raigarh
Coco Marina
Atharva Realty Private Limited
Alibaug Residential Project
Lodha Developers Limited
Embassy Serenity - Phase 1
FAMA PROPERTIES LIMITED
AVAS LIVING
AVAS LIVING ALIBAUG LLP
Alibaug Plots
Lodha Developers Limited
The Sands
JOYCE HAMPTONS BUILDCON LLP
See every Raigarh project, with the district possession charts
Builder: Lodha Developers Limited
LODHA DEVELOPERS LIMITED has 179 registrations on MahaRERA, including Lodha Adrina and Mhatre Compound. Its filings disclose 22 earlier MahaRERA projects: declares 9 of 10 past projects completed on time. Litigation is declared on 39 of its registrations. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Alibaug Townhouses is delayed beyond 31 Aug 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Alibaug Townhouses?
The registered promoter entity is Lodha Developers Limited, a company as per the filing. Its CIN L45200MH1995PLC093041 and GSTIN 27AAACL1490J1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Alibaug Townhouses?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Alibaug Townhouses?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Alibaug Townhouses?
The professionals named in the filing: Architect: Vilas Desai & Associate; Architect: Pradeep Kamble; Engineer: K C Shah Consultants; Engineer: Akash Palkar; Chartered Accountant: Chirag Sarvaiya & Co; Chartered Accountant: M S K A & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Alibaug Townhouses?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback