Home / Browse projects / Pune, Maharashtra / AKSHA CASA PALLADIUM

Registered No litigation declared Others project

AKSHA CASA PALLADIUM

By ACCURATE REALITIES

RG-MH-98339 · RERA P52100048337 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
May 2027Possession promisedmoved 12 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 60%
106 of 160Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 133 documents Report an error

AKSHA CASA PALLADIUM is a Others project by ACCURATE REALITIES in Pune, Maharashtra, registered with MahaRERA as P52100048337 on 26 Dec 2022. Possession is promised by 31 May 2027. The completion date has moved by 12 months from the original filing. 54 of the 160 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameAKSHA CASA PALLADIUM
  • TypeOthers
  • Location
    • BOPKHEL
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411031
  • Pincode411031
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100048337
  • ReraGenie IDRG-MH-98339

Builder

  • NameACCURATE REALITIES
  • Entity typePartnership
  • PartnersAKRAM ZIKRULLAH CHAUDHARY, ANAND TARACHAND JAIN, BHARAT MOHANLAL JAIN, IMRAN ABDULREHMAN CHAUDHARY, MAHAVEER MOHANLAL JAIN, MANISH KAPOORCHAND RANKA, SANTOSH LALARAM CHOUDHARY, SHANTILAL LALCHAND JAIN, SUNIL CHAMPALAL MANDOT, SURESH GHISULAL CHOUDHARY, ZIKRULLAH ABBASALI CHAUDHARY
  • PartnerBHARAT LALARAM CHOUDHARY

Key dates

this monthRegisteredDec 2022First promiseMay 2026Revised toMay 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Dec 2022
  • Promised completion31 May 2027
  • Revised completionRevised to 31 May 2027 (originally 31 May 2026)
  • Buildings1 building record
  • Documents filed133 files

Current status

34%54 of 160 units booked
80.1%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AKSHA CASA PALLADIUMNA161514020160

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 60%.

AKSHA CASA PALLADIUM: 60% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed286

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots286
Closed/Covered91
Open Space195

Land and ownership21

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,500 sq m
Land owned byNot the promoter
Named landowners21
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Jun 2025
LandownerVillageDistrict
Santosh Sahebrao SatavPimpri Chinchawad (M Corp.)Pune
Dnyaneshwar Ganpat GhulePimpri Chinchawad (M Corp.)Pune
Sushila Vitthal GhulePimpri Chinchawad (M Corp.)Pune
Omkar Vitthal GhulePimpri Chinchawad (M Corp.)Pune
Pandurang Ganpat GhulePimpri Chinchawad (M Corp.)Pune
Anita Ganpat GhulePimpri Chinchawad (M Corp.)Pune
Lilabai Ramchandra GhulePimpri Chinchawad (M Corp.)Pune
Yamuna Sahebrao SatavPimpri Chinchawad (M Corp.)Pune
Sangita Manohar KatePimpri Chinchawad (M Corp.)Pune
Sopan Ramchandra GhulePimpri Chinchawad (M Corp.)Pune
SWATI SOPAN GHULEPimpri Chinchawad (M Corp.)Pune
SOURABH SOPAN GHULEPimpri Chinchawad (M Corp.)Pune
DHANSHREE ALIAS DIVYA SOPAN GHULEPimpri Chinchawad (M Corp.)Pune
SUNITA SAMPAT SATHEPimpri Chinchawad (M Corp.)Pune
JAYSHREE JANARDAN DABHADEPimpri Chinchawad (M Corp.)Pune
BHARTI ROHIDAS RANVADEPimpri Chinchawad (M Corp.)Pune
SHOBHA PANDURAN INGAVALEPimpri Chinchawad (M Corp.)Pune
SUSHMA PANDURANG GHULEPimpri Chinchawad (M Corp.)Pune
NIRANJAN PANDURANG GHULEPimpri Chinchawad (M Corp.)Pune
VRUSHABH DHYANESHAWAR GHULEPimpri Chinchawad (M Corp.)Pune
MANDAR DNYANESHWAR GHULEPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNICIPAL CORPORATION
Permissible FSI11325.65
Proposed, not sanctioned11,325 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPimpri Branch,Lower Ground Floor,Unit No19,20, and 21, Pune 411018
Estimated costRs 26.86 cr
Cost incurredRs 21.53 cr
Work done80.13%
BuildingWingEstimatedIncurred
AKSHA CASA PALLADIUMNARs 25.86 crRs 21.53 cr
-NARs 1.00 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDREAM SPACE ARCHITECS
EngineerSHAILESH OSWAL
EngineerRAJU SATHE
Chartered AccountantPGMJ & ASSOCIATES
Chartered AccountantNITISH VAIDYA & ASSOCIATES
PartnerRole in project
ACCURATE REALITIES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA31032620511May 2026 → May 2027

Reason as filed by the promoterThe project has been extended due to the sanction for the upper floors was received at a later stage owing to delays in obtaining the necessary TDR permissions from the competent authority. Additionally, the landscaping and garden development work is yet to be completed.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Sep 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Sep 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 May 2027

Documents filed133

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 133 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3.pdf20 Jul 2026
Form 2A (FY 2024-2025)File: Form 2A FY 2024-25.pdf16 May 2026
Form 2A (FY 2025-2026)File: Form 2A FY 2025-26.pdf16 May 2026
Form 2A (FY 2022-2023)File: Form 2A FY 2022-23.pdf16 May 2026
Form 2A (FY 2023-2024)File: Form 2A FY 2023-24.pdf16 May 2026
Withdrawal Update Form 1File: FORM 1 Q4 FY 25-26.pdf19 Apr 2026
Withdrawal Update Form 2File: FORM 2 Q4 FY 25-26.pdf19 Apr 2026
Withdrawal Update Form 3File: Form 3 Q4 FY 25-26.pdf19 Apr 2026
Withdrawal Update Form 1File: Form 1 Q3 FY 25-26.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 Q3 FY 25-26.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 Q3 FY 25-26.pdf20 Jan 2026
Withdrawal Update Form 1File: Q2 FORM 1 AKSHA CASA PALLADIUM ARCHITECT CERTIFICATE.pdf16 Oct 2025
Withdrawal Update Form 2File: Q2 FORM 2 ACCURATE CASA ENGINEER CERTIFICATE (1).pdf16 Oct 2025
Withdrawal Update Form 3File: Q2 FORM 3 ACCURATE CASA CA CERTIFICATE.pdf16 Oct 2025
Withdrawal Update Form 1File: CASA PALLADIUM FORM 1 ARCHITECT CERTIFICATE.pdf15 Oct 2025
Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE AKSHA CASA PALLADIUM.pdf15 Oct 2025
Withdrawal Update Form 3File: CASA PALLADIUM FORM 3 CA CERTIFICATE.pdf15 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 Final.pdf30 Sep 2025
Layout approvalFile: Layout Plan Highlighted.pdf4 Sep 2025
Building plan approvalFile: Building Plan 1.pdf4 Sep 2025
Building plan approvalFile: Building Plan 2.pdf4 Sep 2025
Building plan approvalFile: Building Plan 3.pdf4 Sep 2025
Building plan approvalFile: Building Plan 4.pdf4 Sep 2025
Building plan approvalFile: Building Plan 5.pdf4 Sep 2025
Building plan approvalFile: Building Plan 6.pdf4 Sep 2025
Building plan approvalFile: Building Plan 7.pdf4 Sep 2025
Building plan approvalFile: Building Plan 8.pdf4 Sep 2025
Building plan approvalFile: Building Plan 9.pdf4 Sep 2025
Building plan approvalFile: Building Plan 10.pdf4 Sep 2025
Form 1File: FORM 1 CASA PALLADIUM.pdf17 Jul 2025
Form 2File: FORM 2 CASA PALLADIUM.pdf17 Jul 2025
Form 3File: Form 3 CASA Palladium.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD INVENTORY CASA PALLADIUM A WING.pdf17 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 CASA PALLADIUM.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 CASA PALLADIUM.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY CASA PALLADIUM A WING.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE AKSHA CASA PALLADIUM.pdf6 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 Final.pdf6 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENG CERTIFICATE AKSHA CASA PALLADIUM.pdf6 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf6 Mar 2025
Layout approvalFile: SANCTION LAYOUT Final.pdf25 Feb 2025
Building plan approvalFile: BASEMENT FLOOR PARKING PLAN.pdf25 Feb 2025
Building plan approvalFile: GROUND FLOOR PARKING PLAN.pdf25 Feb 2025
Building plan approvalFile: GROUND FLOOR PLAN.pdf25 Feb 2025
Building plan approvalFile: 1st FLOOR PLAN.pdf25 Feb 2025
Building plan approvalFile: 2nd FLOOR PLAN.pdf25 Feb 2025
Building plan approvalFile: 3rd FLOOR PLAN.pdf25 Feb 2025
Building plan approvalFile: 4,5,6,8,9,10 FLOOR PLAN.pdf25 Feb 2025
Building plan approvalFile: 7th FLOOR PLAN.pdf25 Feb 2025
Building plan approvalFile: TERRACE FLOOR PLAN.pdf25 Feb 2025
Building plan approvalFile: ELEVATION PLAN.pdf25 Feb 2025
Copy of Layout Approval (in case of layout)File: SANCTION LAYOUT Final.pdf25 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencment Certificate.pdf25 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 1st FLOOR PLAN.pdf25 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: ELEVATION PLAN.pdf25 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: TERRACE FLOOR PLAN.pdf25 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 7th FLOOR PLAN.pdf25 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 4,5,6,8,9,10 FLOOR PLAN.pdf25 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 3rd FLOOR PLAN.pdf25 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 2nd FLOOR PLAN.pdf25 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: GROUND FLOOR PLAN.pdf25 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: GROUND FLOOR PARKING PLAN.pdf25 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: BASEMENT FLOOR PARKING PLAN.pdf25 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Final.pdf31 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 final.pdf18 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE CASA PALLADIUM A WING.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE ACCURATE REALITIES.pdf20 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD CIRCULAR.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 upload_compressed.pdf25 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE ACCURATE REALITIES.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 uploaded.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 final.pdf20 Mar 2024

How this compares with Pune

34%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AKSHA CASA PALLADIUM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BOPKHEL13,700+ in Pune

2 kmAKSHA CASA PALLADIUMCompleted 8Lapsed / revoked 6Other 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: ACCURATE REALITIES

ACCURATE REALITIES has 1 registration on MahaRERA, including AKSHA CASA PALLADIUM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if AKSHA CASA PALLADIUM is delayed beyond 31 May 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AKSHA CASA PALLADIUM?

The registered promoter entity is ACCURATE REALITIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AKSHA CASA PALLADIUM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AKSHA CASA PALLADIUM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AKSHA CASA PALLADIUM?

The professionals named in the filing: Architect: DREAM SPACE ARCHITECS; Engineer: SHAILESH OSWAL; Engineer: RAJU SATHE; Chartered Accountant: PGMJ & ASSOCIATES; Chartered Accountant: NITISH VAIDYA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AKSHA CASA PALLADIUM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AKSHA CASA PALLADIUM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AKSHA CASA PALLADIUM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.