Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Aug 2020Possession promisedmoved 12 months from the original
1Complaints at RERA Karnatakaon this registration
Jump to the 60 documents Report an error

Adonai Glory is a Residential/Group Housing project by Adonai Shelters Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/180120/001718 on 20 Jan 2018. Possession is promised by 2 Aug 2020. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAdonai Glory
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/180120/001718
  • ReraGenie IDRG-KA-08920

Builder

  • NameAdonai Shelters Pvt Ltd
  • Entity typeCompany
  • CINU45202AA2008PTC047079
  • Authorized SignatoryS.Balakrishnan

Key dates

this monthRegisteredJan 2018First promiseAug 2019Revised toAug 2020

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Jan 2018
  • Promised completion2 Aug 2020
  • Revised completionRevised to 2 Aug 2020 (originally 2 Aug 2019)
  • Buildings1 building record
  • Documents filed60 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Adonai Glory---56056

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 28 Sep 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 28 Sep 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationYes-
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,501 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 12.22 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRamesh . R
EngineerDr.Pranesh R N

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/446/PR/220620/001718Aug 2019 → Aug 2020

Reason as filed by the promoterApplied for modification

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
CMP/210127/0007463-Adonai Shelters Pvt Ltd27/01/2021

Documents filed60

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/180120/001718 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Bank statement mentioned in CA certificateFile: Bank Statement.PDF28 Sep 2020
Sold and Unsold UnitsFile: Sold & Unsold details.PDF28 Sep 2020
CertificateFile: Registration certificate - OFF.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate Work completed till date.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate Work completed Till date.pdf-
CA Certificate for Funds UtilizationFile: CA Funds utilized uploaded.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate Pending work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate Work Pending.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Funds Required uploaded.pdf-
AffidavitFile: Form B and Affidavit uploaded.pdf-
Latest Encumbrance CertificateFile: Till date EC.pdf-
Consent letter from 2/3rd of Allottees-
Details Of Sold/ Un-sold UnitsFile: RERA agreement details.pdf-
Document 1File: Consent Letter.pdf-
Document 2File: Flat No 306.PDF-
Document 3File: Flat No 307.PDF-
Document 4File: Flat No 603.PDF-
Document 5File: Flat No 605.pdf-
Document 6File: Flat No 706.PDF-
Document 7File: Flat No. 407.pdf-
Commencement Certificate-
Plan-
Performa for Sale deed-
Profoma of Sale Agreement-
Section Plan-
JD Agreement Uploaded-
Plan-
Plan-
Proforma Allotment letter-
Project Brochures-
NOC - AIRPORT-
Project Specification-
EC-
KATHA latest-
JD Agreement Uploaded-
Land Conversion uploaded-
NOC - AIRPORT-
NOC - Electricals-
NOC - BSNL-
Balance Sheet 2015 - 2016File: Balance Sheet - AS16-17.PDF-
Balance Sheet 2014 - 2015File: ITR 2015-16.pdf-
Balance Sheet 2013 - 2014File: Balance Sheet.JPG-
Audited Profit and Loss Statement 2015 - 2016File: audited P&L- AS16-17.PDF-
Audited Profit and Loss Statement 2014 - 2015File: Audited P&L.PDF-
Audited Profit and Loss Statement 2013 - 2014File: P and L.JPG-
Director's Report 2015 - 2016File: Directors Report.pdf-
Director's Report 2014 - 2015File: Directors Report_2015-16_Adonai-uploaded.pdf-
Director's Report 2013 - 2014File: Notice and Director's Report adonai 2014-15.pdf-
Cash Flow Statement 2015 - 2016File: ITR 2016-17- Cash Flow.pdf-
Cash Flow Statement 2014 - 2015File: Cash Flow.pdf-
Auditor's Report 2015 - 2016File: Independent Audit Report.pdf-
Auditor's Report 2014 - 2015File: Audit report-adonai 2015-16-uploaded.pdf-
Auditor's Report 2013 - 2014File: Auditor's Report- adonai 2014-15-uploaded.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 2016-17 - Acknowledgement.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR 2015-16.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: IT Ack.JPG-
Form b-
Prospectus/BrochureFile: Brouchure.jpg-
Advertisement Copy 1File: Advertisement.jpeg-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_180120_001718.xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Adonai Glory on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Adonai Shelters Pvt Ltd

Adonai Shelters Pvt Ltd has 1 registration on RERA Karnataka, including Adonai Glory. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Adonai Glory is delayed beyond 2 Aug 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Adonai Glory?

The registered promoter entity is Adonai Shelters Pvt Ltd, a company as per the filing. Its CIN U45202AA2008PTC047079 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Adonai Glory?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Adonai Glory?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Adonai Glory?

The professionals named in the filing: Architect: Ramesh . R; Engineer: Dr.Pranesh R N. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Adonai Glory?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Adonai Glory. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Adonai Glory to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.