ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / ADITYARAJ ROYALE

Registration lapsed No litigation declared Others project

ADITYARAJ ROYALE

By ADITYARAJ ROYALE

RG-MH-77256 · RERA P51800032024 · Last updated on MahaRERA portal: 4 Aug 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
0Complaints at MahaRERAon this registration
Jump to the 66 documents Report an error

ADITYARAJ ROYALE is a Others project by ADITYARAJ ROYALE in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800032024 on 3 Dec 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date.

At a glance

Project

  • NameADITYARAJ ROYALE
  • TypeOthers
  • Location
    • TAGORE NAGAR
    • VIKHROLI EAST
    • Kurla
    • Mumbai Suburban
    • 400083
  • Pincode400083
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800032024
  • ReraGenie IDRG-MH-77256

Builder

  • NameADITYARAJ ROYALE
  • Entity typePartnership
  • PartnersROCKY RAJKUMAR KHUSHALANI, KISHOR MANJI PATEL, HITESH LILADHAR SHAHANAND

Key dates

10 months past promisethis monthRegisteredDec 2021PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 Dec 2021
  • Promised completion31 Dec 2025
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed66 files

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Progress on shared amenities15

As on 4 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area965 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Aug 2025
LandownerVillageDistrict
TAGORE NAGAR SHIV CHHAYA CHSKurlaMumbai Suburban

Approvals and building plan

Sanctioning authoritymhada
Permissible FSI7897.09
Proposed, not sanctioned6,526 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKANNAMWAR NAGAR VIKHROLI EAST MUMBAI 400083

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANKIT MAKANI
EngineerNAVINDERPAL SINGH
EngineerNAVINDER PAL SINGH
Chartered AccountantCHIRAG SURANA
Chartered Accountantpulkit porwal
PartnerRole in project
ADITYARAJ ROYALE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Nov 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Nov 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed66

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2023-2024)File: Form 5 2023 24.pdf4 Aug 2025
Form 5 (FY 2024-2025)File: FORM 5.pdf4 Aug 2025
Form 2A (FY 2024-2025)File: FORM - 2A.pdf2 Aug 2025
Form 2A (FY 2023-2024)File: FORM 2A.pdf2 Aug 2025
Form 1File: FORM - 1.pdf1 Aug 2025
Form 2File: FORM - 2.pdf1 Aug 2025
Form 3File: Form 3.pdf1 Aug 2025
Disclosure of Sold and Booked InventoryFile: discloser.pdf1 Aug 2025
Self-declaration of Quarterly ProgressFile: declaration.pdf1 Aug 2025
Form 1File: FORM 1.pdf24 May 2025
Form 2File: Form 2.pdf24 May 2025
Form 3File: FORM 3.pdf24 May 2025
Disclosure of Sold and Booked InventoryFile: Declaration Of Sold.pdf24 May 2025
Self-declaration of Quarterly ProgressFile: Self Declaration.pdf24 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf12 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 com.pdf19 Dec 2024
Deviation Report with respect to Allotment letterFile: Deviation Allotment.pdf19 Dec 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Sale Agreement.pdf19 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf17 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf17 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BLDG NO 29.pdf10 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf16 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSER INTEREST OF RRK.pdf16 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf28 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 COMPRESS.pdf28 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED COMPRESS.pdf28 Feb 2024
Details of encumbrances concerned to FinanceFile: NO Encumbrances ON DATED 16 02 24.pdf16 Feb 2024
Details of encumbrances concerned to LegalFile: NO Encumbrances ON DATED 16 02 24.pdf16 Feb 2024
Declaration about Commencement CertificateFile: DECLARATION CC 29.pdf11 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: bldg no 29 form 2 sep 23.pdf11 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 BLDG NO 29 JUNE 23.pdf4 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BLDG NO 29.pdf4 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: FullCC of bldg No 29 Tagore Nagar.pdf27 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf27 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf27 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 29 TN FORM 2A QUALITY ASSURANCES.pdf27 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BLDG NO 29 MAR 23.pdf25 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 29.pdf25 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Mar 22.pdf26 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31122022.pdf27 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31122022.pdf27 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf27 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf9 Dec 2022
Declaration about Commencement CertificateFile: CC Declaration new.pdf9 Dec 2022
Declaration in FORM BFile: Form B 29 d_compressed.pdf29 Nov 2021
Building plan approvalFile: building plan.pdf27 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: building plan.pdf27 Nov 2021
Details of encumbrancesFile: Encumbrances.pdf26 Nov 2021
Proforma of Allotment letterFile: AGREEMENT FOR SALE 29 RERA.pdf26 Nov 2021
Proforma of Allotment letterFile: BOOKING LETTER RERA.pdf26 Nov 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate of Bldg no-29,Tagore Nagar dt-25-21-2021(1).pdf25 Nov 2021
Declaration about Commencement CertificateFile: CC Declaration scan.pdf25 Nov 2021
CERSAI detailsFile: CERSAI_scan.pdf25 Nov 2021
Layout approvalFile: layout.pdf24 Nov 2021
Copy of Layout Approval (in case of layout)File: layout.pdf24 Nov 2021
Building plan approvalFile: Binder2 6_11zon_merged_11zon.pdf23 Nov 2021
PAN CardFile: Adityaraj Royale Pan Card.pdf23 Nov 2021
Copy of the legal title reportFile: Title Clearacne Certificate 29.pdf23 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: Binder2 6_11zon_merged_11zon.pdf23 Nov 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf23 Nov 2021

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ADITYARAJ ROYALE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIKHROLI EAST6,700+ in Mumbai Suburban

2 kmADITYARAJ ROYALECompleted 26Lapsed / revoked 24Other 93Dot size: filed unitsN

Filed coordinates, straight-line distance. 143 registered projects within 2 km.

Builder: ADITYARAJ ROYALE

ADITYARAJ ROYALE has 1 registration on MahaRERA, including ADITYARAJ ROYALE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that ADITYARAJ ROYALE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ADITYARAJ ROYALE is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ADITYARAJ ROYALE?

The registered promoter entity is ADITYARAJ ROYALE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ADITYARAJ ROYALE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ADITYARAJ ROYALE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ADITYARAJ ROYALE?

The professionals named in the filing: Architect: ANKIT MAKANI; Engineer: NAVINDERPAL SINGH; Engineer: NAVINDER PAL SINGH; Chartered Accountant: CHIRAG SURANA; Chartered Accountant: pulkit porwal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ADITYARAJ ROYALE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADITYARAJ ROYALE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADITYARAJ ROYALE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.