Home / Browse projects / Bengaluru Urban, Karnataka / ADITRRI LOTUS

Registration approved Residential/Group Housing project

ADITRRI LOTUS

By ADITRRI BUILDERS AND DEVELOPERS

RG-KA-03755 · RERA PRM/KA/RERA/1251/472/PR/200624/003471 · Last updated on RERA Karnataka portal: 29 Nov 2024

Source: official RERA Karnataka filing

Red flags

  • 6 complaints at RERA Karnataka
  • Completion date moved by 54 months
  • 2 extensions taken

Clear

  • Separate project account declared
Dec 2026Possession promisedmoved 54 months from the original
6Complaints at RERA Karnatakaon this registration
Jump to the 94 documents Report an error

ADITRRI LOTUS is a Residential/Group Housing project by ADITRRI BUILDERS AND DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/200624/003471 on 24 Jun 2020. Possession is promised by 20 Dec 2026. The completion date has moved by 54 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameADITRRI LOTUS
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/472/PR/200624/003471
  • ReraGenie IDRG-KA-03755

Builder

  • NameADITRRI BUILDERS AND DEVELOPERS
  • Entity typeProprietorship Firm
  • Authorized SignatoryKemparaja. K.M

Key dates

this monthRegisteredJun 2020First promiseJun 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on24 Jun 2020
  • Promised completion20 Dec 2026
  • Revised completionRevised to 20 Dec 2026 (originally 30 Jun 2022)
  • Buildings1 building record
  • Documents filed94 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ADITRRI LOTUS---38038

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 29 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 29 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes-
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,023 sq m
Named landowners2
LandownerVillageDistrict
N Nagaveni--
Varalakshmi C--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSrimathi J Adiga
EngineerVishnu Kumar

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/472/PR/241231/003471Jun 2022 → Jun 2023

Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc

ExtensionJun 2023 → Dec 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka6

Case no.ComplainantRespondentFiled
CMP/221114/0010297-ADITRRI BUILDERS AND DEVELOPERS14/11/2022
CMP/221114/0010298-ADITRRI BUILDERS AND DEVELOPERS14/11/2022
CMP/221114/0010299-ADITRRI BUILDERS AND DEVELOPERS14/11/2022
CMP/221114/0010306-ADITRRI BUILDERS AND DEVELOPERS14/11/2022
CMP/221114/0010307-ADITRRI BUILDERS AND DEVELOPERS14/11/2022
CMP/221114/0010308-ADITRRI BUILDERS AND DEVELOPERS14/11/2022

Documents filed94

As listed on the registration, under the names the promoter filed them with; the newest 80 of 94 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/200624/003471 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA EXTENSION 3File: CA form 3x new.pdf29 Nov 2024
CA EXTENSION 4File: CA Form 4x new.pdf29 Nov 2024
ARCH EXTENSION 1File: ARCH FORM EXT 1.pdf29 Nov 2024
ARCH EXTENSION 2File: ARCH FORM EXT 2.pdf29 Nov 2024
ENGG EXT 5File: ENGG FORM EX 5.pdf29 Nov 2024
ENGG EXT 6File: ENGG FORM EX 6.pdf29 Nov 2024
ANNUAL AUDIT REPORTFile: ANNUAL AUDIT REPORT.pdf29 Nov 2024
BWSSB NOCFile: BWSSB NEW.jpeg29 Nov 2024
BESCOM NOCFile: BESCOM.jpeg29 Nov 2024
CA Q1 2024-25File: Form 4 Q1 NEW.pdf29 Nov 2024
CA Q2 2024-25File: Form 4 Q2 NEW.pdf29 Nov 2024
ENGG Q1 2024-25File: ENG FORM 6 Q1.pdf29 Nov 2024
ENGG Q2 24-25File: ENG FORM 6 Q2 NEW.pdf29 Nov 2024
ARC Q1File: ARCH Q1 30 JUN 2024.pdf29 Nov 2024
ARC Q2File: ARCH FORM EXT 2.pdf29 Nov 2024
Approved PlanFile: Approved Plan organized.pdf20 Jun 2020
Commencement CertificateFile: Commencement Certificate.pdf20 Jun 2020
Initial Plan Approval letterFile: Initial Plan Approval.pdf20 Jun 2020
Permission letterFile: Permission to continue constructions.pdf20 Jun 2020
NOC BESCOMFile: BESCOM NOC.pdf20 Jun 2020
NOC BWSSBFile: BWSSB NOC.pdf20 Jun 2020
NOC PCBFile: PCB NOC.pdf20 Jun 2020
CertificateFile: GST Certificate.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: ARCH FORM EXT 1.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: ENGG FORM EX 5.pdf-
CA Certificate for Funds UtilizationFile: CA form 3x new.pdf-
Architect Certificate for Pending Work Completion Schedule.File: ARCH FORM EXT 2.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: ENGG FORM EX 6.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Form 4x new.pdf-
AffidavitFile: Form Ex 7 affidavit _compressed.pdf-
Latest Encumbrance CertificateFile: ECC-10072024-2765759.pdf-
Details Of Sold/ Un-sold UnitsFile: sale proceed details.pdf-
Document 1File: ANNUAL AUDIT REPORT.pdf-
Commencement Certificate, approval & permission letter_compressed-
Approved_Plan_organized-
CC Plan Specifications-
court order WILL and MR-
Approved_Plan_organized-
Approved_Plan_organized-
Brochure-
Specifications-
UPTO DATE EC-
Sec 3(1) non-violation Affidavit-
Joint Declration Affidavit_compressed-
khatha MR and Death Certificate-
JDA AND GPA-
Death Certificate Sahadeva Krishna-
Conversion order (3)-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
BESCOM-NOC-
BWSSB NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Approved_Plan_organized-
CC Plan Specifications-
Unnamed document-
Balance Sheet 2018 - 2019File: ACCOUNT-CLARIFICATION.pdf-
Balance Sheet 2017 - 2018File: ACCOUNT-CLARIFICATION.pdf-
Balance Sheet 2016 - 2017File: ACCOUNT-CLARIFICATION.pdf-
Audited Profit and Loss Statement 2018 - 2019File: ACCOUNT-CLARIFICATION.pdf-
Audited Profit and Loss Statement 2017 - 2018File: ACCOUNT-CLARIFICATION.pdf-
Audited Profit and Loss Statement 2016 - 2017File: ACCOUNT-CLARIFICATION.pdf-
Director's Report 2018 - 2019File: ACCOUNT-CLARIFICATION.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 54 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ADITRRI LOTUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: ADITRRI BUILDERS AND DEVELOPERS

ADITRRI BUILDERS AND DEVELOPERS has 1 registration on RERA Karnataka, including ADITRRI LOTUS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ADITRRI LOTUS is delayed beyond 20 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ADITRRI LOTUS?

The registered promoter entity is ADITRRI BUILDERS AND DEVELOPERS, a proprietorship firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ADITRRI LOTUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ADITRRI LOTUS?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at ADITRRI LOTUS?

The professionals named in the filing: Architect: Srimathi J Adiga; Engineer: Vishnu Kumar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ADITRRI LOTUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADITRRI LOTUS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADITRRI LOTUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.