Home / Browse projects / Bengaluru Urban, Karnataka / ADITHYA TRANQUIL

Registration approved Residential/Group Housing project

ADITHYA TRANQUIL

By ADITHYA DEVELOPERS

RG-KA-94839 · RERA PRM/KA/RERA/1251/309/PR/180319/002441 · Last updated on RERA Karnataka portal: 19 May 2022

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • Separate project account declared
Jan 2023Possession promisedmoved 18 months from the original
1Complaints at RERA Karnatakaon this registration
Jump to the 69 documents Report an error

ADITHYA TRANQUIL is a Residential/Group Housing project by ADITHYA DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180319/002441 on 19 Mar 2018. Possession is promised by 31 Jan 2023. The completion date has moved by 18 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameADITHYA TRANQUIL
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/180319/002441
  • ReraGenie IDRG-KA-94839

Builder

  • NameADITHYA DEVELOPERS
  • Entity typePartnership Firm
  • Authorized SignatoryM.CHANDRASEKHAR
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredMar 2018First promiseJul 2021Revised toJan 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Mar 2018
  • Promised completion31 Jan 2023
  • Revised completionRevised to 31 Jan 2023 (originally 31 Jul 2021)
  • Buildings1 building record
  • Documents filed69 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A B C D-----128

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 19 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 19 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,436 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 28.80 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDESIGN PLUS
EngineerBASE Engineering Services

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJul 2021 → Apr 2022

No reason recorded in the filing

EX/PRM/KA/RERA/1251/309/PR/221231/002441Apr 2022 → Jan 2023

Reason as filed by the promoterShortage of Labour

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
01226/2026-ADITHYA DEVELOPERS14/10/2026

Documents filed69

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180319/002441 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA certificate Form EX-3File: Form Ex 3 C A Certificate for Funds Utilization.pdf19 May 2022
CA Certificate Form EX-4File: Form EX 4 C A Certificate for Funds Required.pdf19 May 2022
Building LicenseFile: BBMP Sanction Plan to upload.pdf19 May 2022
commencement certificateFile: Commencement Certificate.pdf19 May 2022
KSPCBFile: Karnataka state pollution control board.pdf19 May 2022
List of alloteesFile: Adithya Tranquil List of allottees.pdf19 May 2022
BHK Wise BreakupFile: Adithya Tranquil Project BHK Wise details.pdf19 May 2022
Project member detailsFile: Project Member Details Reconstitution Deed with Form D.pdf19 May 2022
Bescom NOCFile: Bescom Intimation Letter & Payment Certificate.pdf19 May 2022
Project specificationFile: Self Attested Specification of Apartment.pdf19 May 2022
STP DrawingsFile: STP drawing-Model.pdf19 May 2022
Proforma Agreement of SaleFile: Sale Agreement Draft.pdf19 May 2022
Allotment letterFile: Adithya Tranquil-Allotment Letter-Draft.pdf19 May 2022
BrochureFile: Adithya Tranquil_Brochure 02.pdf19 May 2022
Title Search ReportFile: Advocate Report.pdf19 May 2022
Structural certificateFile: Structural Certificate.pdf19 May 2022
AffidavitFile: Affidavit as per Sec 18(1).pdf19 May 2022
Bank statementFile: Adithya Developers-Statement -Tranquil Escrow- Apri 2021 to Jan 2022.pdf19 May 2022
Reply letterFile: Reply to the Project Extension Notice.pdf19 May 2022
CertificateFile: Company Registration.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Form Ex1 Architect's Certificate for Status of Work.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form Ex 5 Enginner's Certificate Status of Work.pdf-
CA Certificate for Funds UtilizationFile: Form Ex 3 C A Certificate for Funds Utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form Ex 2 Architect's Certificate for Pending Work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form Ex6 Engineer's Certificate for Pending Work.pdf-
CA Certificate for Funds required for Project CompletionFile: Form EX 4 C A Certificate for Funds Required.pdf-
AffidavitFile: Form Ex 7 Affidavit for Seeking Extension of Registered Projects.pdf-
Latest Encumbrance CertificateFile: E C copy-compressed.pdf-
Details Of Sold/ Un-sold UnitsFile: Adithya Tranquil Project Sold and Unsold Units Inventory.pdf-
Document 1File: Form B Affidavit cum Declaration.pdf-
Document 2File: Adithya Tranquil Delay letter.pdf-
Document 3File: NOC BWSSB.pdf-
Document 4File: MOEF, CLEARANCE.pdf-
Document 5File: BBMP Sanction Plan to upload.pdf-
Document 6File: Karnataka state pollution control board.pdf-
Document 7File: Partial Occupancy Certificate.pdf-
Document 8File: Commencement Certificate.pdf-
UNDER PROCESS-
Adithya Tranquil - Approved plan-
UNDER PROCESS-
UNDER PROCESS-
Partition deed lrf and rtc-
Tranquil Plan-
UNDER PROCESS-
Tranquil brochure-
TRANQUIL SPECIFICATIONS-
Adithya Tranquil - E C-
Katha Certificate & Extract-
Adithya Tranquil - JDA-
Adithya Tranquil - Conversion Order-
Balance Sheet 2016 - 2017File: Balance Sheet 2016-17.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet 2015-16.pdf-
Balance Sheet 2014 - 2015File: Balance Sheet 2014-15.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P & L 2016-17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P & L 2015-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P & L 2014-15.pdf-
Cash Flow Statement 2016 - 2017File: cash flow 2016-17.pdf-
Cash Flow Statement 2015 - 2016File: cash flow 2015-16.pdf-
Auditor's Report 2016 - 2017File: P & L 2016-17.pdf-
Auditor's Report 2015 - 2016File: Audit Report 15- 16.pdf-
Auditor's Report 2014 - 2015File: Audit Report 2014-15.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR V 2016-17.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR V 2015-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR V 2014-15.pdf-
Prospectus/BrochureFile: Adithya Tranquil - Brochure.pdf-
Advertisement Copy 1File: Advertisement in Newspaper.jpeg-
Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_180319_002441.xlsx-
Occupancy CertificateFile: OC Copy.pdf-
Completion certificate issued by the competent authorityFile: OC Copy.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Adithya Celestial-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 18 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ADITHYA TRANQUIL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmADITHYA TRANQUILOther 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: ADITHYA DEVELOPERS

ADITHYA DEVELOPERS has 2 registrations on RERA Karnataka, including ADITHYA TRANQUIL and ADITHYA GREEN GARDENS. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ADITHYA TRANQUIL is delayed beyond 31 Jan 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ADITHYA TRANQUIL?

The registered promoter entity is ADITHYA DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ADITHYA TRANQUIL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ADITHYA TRANQUIL?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at ADITHYA TRANQUIL?

The professionals named in the filing: Architect: DESIGN PLUS; Engineer: BASE Engineering Services. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ADITHYA TRANQUIL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADITHYA TRANQUIL. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADITHYA TRANQUIL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.