Registration approved Residential/Group Housing project

Adithya Lujoso

By Adithya Constructions

RG-KA-31030 · RERA PRM/KA/RERA/1251/446/PR/190614/002600

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Sep 2022Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 43 documents Report an error

Adithya Lujoso is a Residential/Group Housing project by Adithya Constructions in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/190614/002600 on 14 Jun 2019. Possession is promised by 30 Sep 2022. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameAdithya Lujoso
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/190614/002600
  • ReraGenie IDRG-KA-31030

Builder

  • NameAdithya Constructions
  • Other registrations3 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2019First promiseDec 2021Revised toSep 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Jun 2019
  • Promised completion30 Sep 2022
  • Revised completionRevised to 30 Sep 2022 (originally 31 Dec 2021)
  • Buildings2 building records
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A bLOCK---52052
B BLOCK---72072

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,925 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 28.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectFWD ARCHITECTS
EngineerBHASKAR Y

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2021 → Sep 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/190614/002600 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CC-
All Floor Plan Section and Elvation Plan-
All Floor Plan Site Plan and Sanction Letter-
To be upload during PR-
To be upload during PR-
Motherdeed Plaintiff and RTC-
All Floor Plan Section and Elvation Plan-
To be upload during PR-
To be Upload during PR-
All NOCS-
Project Specifications-
EC-
Sec 3(1) Affidvait-
JDA Affidavit-
RTC KHATAH-
JDA GPA Sharing Agreement-
RTC MR TIPPANY AKARBAND-
CONVERSION ORDER-
VILLAGE MAP-
BWSSB-
KSPCB-
Unnamed document-
Balance Sheet 2017 - 2018File: Balance Sheet 2018.pdf-
Balance Sheet 2016 - 2017File: Balance Sheet 2017.pdf-
Balance Sheet 2015 - 2016File: Balance sheet 2016.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Profit and Loss 2018.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit and Loss 2017.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Profit and Loss Account 2016.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: Income tax Acknowledgement-2017 & 18.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: Income tax Acknowledgement-2016 & 17.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: Income tax Acknowledgement-2015 & 16.pdf-
Form B-
Prospectus/Brochure-
Advertisement Copy 1File: rera pic-converted.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_190614_002600 (1).xlsx-
Stability CertificateFile: STRUCTURAL STABILITY CERTIFICATE.pdf-
Occupancy CertificateFile: Lujoso OC.pdf-
Consent for operation issued by KSPCBFile: KSPCB.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Chief of Department of electrical inspectorate.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM.pdf-
Architect certificate for having completed the work(in format no 5)File: Completion Certificate.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: CA-4 CC.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: AFFIDAVIT CUM DECLARATION.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Adithya Lujoso on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Adithya Constructions

ADITHYA CONSTRUCTIONS has 4 registrations on RERA Karnataka, including ADITHYA RICA and ADITHYA VALIOSO. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Adithya Lujoso is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Adithya Lujoso?

The registered promoter entity is Adithya Constructions. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Adithya Lujoso?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Adithya Lujoso?

The professionals named in the filing: Architect: FWD ARCHITECTS; Engineer: BHASKAR Y. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Adithya Lujoso?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Adithya Lujoso. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Adithya Lujoso to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.