ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / ADISHAKTI CHS ADITYARAJ PRIME

Registration lapsed No litigation declared Others project

ADISHAKTI CHS ADITYARAJ PRIME

By ADITYARAJ BUILDERS & PROMOTERS

RG-MH-41931 · RERA P51800045695 · Last updated on MahaRERA portal: 19 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 91%
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

ADISHAKTI CHS ADITYARAJ PRIME is a Others project by ADITYARAJ BUILDERS & PROMOTERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800045695 on 6 Jun 2022. Possession was promised by 31 Mar 2026 and is now 7 months past that date.

At a glance

Project

  • NameADISHAKTI CHS ADITYARAJ PRIME
  • TypeOthers
  • Location
    • BUILDING NO 81 KANNAMWAR NAGAR VIKHROLI EAST
    • VIKHROLI EAST
    • Kurla
    • Mumbai Suburban
    • 400083
  • Pincode400083
  • RERA no.P51800045695
  • ReraGenie IDRG-MH-41931

Builder

  • NameADITYARAJ BUILDERS & PROMOTERS
  • Entity typePartnership
  • PartnerRAJKUMAR GYANCHAND KHUSHALANI
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

7 months past promisethis monthRegisteredJun 2022PromisedMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Jun 2022
  • Promised completion31 Mar 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed77 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ADITYARAJ PRIMENA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 91%.

ADITYARAJ PRIME: 59% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure91%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises69%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks91%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 19 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
ROOFTOP AMMINITESYes0%

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,027 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
ADITYARAJ BUILDERS AND PROMOTERSKurlaMumbai Suburban

Approvals and building plan

Permissible FSI7411.5
Proposed, not sanctioned1,027 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 13 AND 14 NEELKANTH REGENT R N NARKAR MARG PANT NAGAR GHATKOPAR E MUMBAI

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
ADITYARAJ BUILDERS & PROMOTERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 May 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1_ABP_81.pdf19 Jan 2026
Form 2File: Form 2_ABP_ 81.pdf19 Jan 2026
Form 3File: Form 3_ABP_81.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory ABP - 81.pdf19 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration 81.pdf19 Jan 2026
Form 1File: form 1-Adishakti.pdf27 Oct 2025
Form 2File: Form 2 Engineers Certificate.pdf27 Oct 2025
Form 3File: Form 3 81 - 30092025.pdf27 Oct 2025
Self-declaration of Quarterly ProgressFile: declaration.pdf27 Oct 2025
Disclosure of Sold and Booked InventoryFile: sold unsold_compressed.pdf27 Oct 2025
Other - FinanceFile: FORMAT B.pdf19 Jul 2025
Other - FinanceFile: Self Declaration 70.pdf19 Jul 2025
Other - FinanceFile: Self Declaration for bank.pdf19 Jul 2025
Form 1File: FORM 1.pdf16 Jul 2025
Form 2File: FORM 2.pdf16 Jul 2025
Form 3File: FORM 3 com.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf16 Jul 2025
Self-declaration of Quarterly ProgressFile: Declaration.pdf16 Jul 2025
Form 1File: FORM 1.pdf5 Jun 2025
Form 2File: FORM 2.pdf5 Jun 2025
Form 3File: FORM 3.pdf5 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold.pdf5 Jun 2025
Self-declaration of Quarterly ProgressFile: Self Declaration.pdf5 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf22 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf22 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf21 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 81 - REVISED - FORM 3.pdf10 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf4 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf4 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf4 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf4 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A.pdf4 Dec 2024
Deviation Report with respect to Allotment letterFile: Deviation Allotment Letter.pdf4 Dec 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Sale Agreement.pdf4 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B.pdf4 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf31 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: REVISED - FORM 3.pdf25 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 BLDG NO 81.pdf10 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-81.pdf30 Apr 2024
Details of encumbrances concerned to FinanceFile: 81 - RERA ENCUMBRANCE ABFL.pdf12 Apr 2024
Details of encumbrances concerned to LegalFile: 81 - RERA ENCUMBRANCE ABFL.pdf12 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf16 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SIGNED COMPRESS.pdf16 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A RGK.pdf16 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSER INTEREST OF RRK.pdf16 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: Buildig No 81.pdf27 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: BLDG NO 81 2A QUALITY ASSURANCES.pdf27 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: CC upto 18th Floor.pdf21 Dec 2023
Proforma of Agreement for saleFile: AGREEMENT FOR SALE BLDG NO 81 PDF.pdf21 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: BLDG NO 81 JUNE 23.pdf29 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf29 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JUNE 23.pdf20 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BLDG NO 81 JUNE 23.pdf8 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BLDG NO 81 SEP 23.pdf8 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf1 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - ADITYARAJ 22-23.pdf30 Oct 2023
PAN CardFile: PAN - Adityaraj Realty.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B81_FORM 1_21042023_AMA.pdf6 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf6 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_1_11zon.pdf6 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 BLDG NO 81 21-22.pdf11 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 81 - form 1.pdf25 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 81 - form 2.pdf23 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 81 - form 3.pdf23 Jan 2023
Details of encumbrancesFile: no encumbraces 81.pdf26 May 2022
Commencement Certificates / NA Order for plotted developmentFile: 81_firstcc_26052022.pdf26 May 2022
Declaration about Commencement CertificateFile: cc dECLARTION 81.pdf26 May 2022
Declaration in FORM BFile: 81 KN_compressed.pdf26 May 2022
CERSAI detailsFile: cersai 81.pdf26 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: fORM 3 81_compressed.pdf26 May 2022
Layout approvalFile: I OD 81.pdf25 May 2022
Building plan approvalFile: plan 81_ K.pdf25 May 2022
Copy of the legal title reportFile: Title Report A 81_.pdf25 May 2022
Copy of Layout Approval (in case of layout)File: I OD 81.pdf25 May 2022
Building Plan Approval / NA Order for plotted developmentFile: plan 81_ K.pdf25 May 2022
Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf25 May 2022

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ADISHAKTI CHS ADITYARAJ PRIME on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIKHROLI EAST6,700+ in Mumbai Suburban

Builder: ADITYARAJ BUILDERS & PROMOTERS

ADITYARAJ BUILDERS & PROMOTERS has 2 registrations on MahaRERA, including ADITYARAJ SQUARE and ADISHAKTI CHS ADITYARAJ PRIME. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that ADISHAKTI CHS ADITYARAJ PRIME shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ADISHAKTI CHS ADITYARAJ PRIME is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ADISHAKTI CHS ADITYARAJ PRIME?

The registered promoter entity is ADITYARAJ BUILDERS & PROMOTERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ADISHAKTI CHS ADITYARAJ PRIME?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ADISHAKTI CHS ADITYARAJ PRIME?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in ADISHAKTI CHS ADITYARAJ PRIME?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADISHAKTI CHS ADITYARAJ PRIME. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADISHAKTI CHS ADITYARAJ PRIME to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.