Registration approved No litigation declared Residential/Group Housing project

ADARSH STRATUSS PHASE 1

By M/s Adarsh Developers

RG-KA-56881 · RERA PRM/KA/RERA/1251/310/PR/200305/003328 · Last updated on RERA Karnataka portal: 30 Jan 2026

Source: official RERA Karnataka filing

Red flags

  • 15 complaints at RERA Karnataka
  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Nov 2025Possession promisedmoved 21 months from the original
1 of 16Construction stages donefurthest along: Earth work and other leveling..., 97%
4 of 54Units unsoldnot recorded sold or booked
15Complaints at RERA Karnatakaon this registration
Jump to the 79 documents Report an error

ADARSH STRATUSS PHASE 1 is a Residential/Group Housing project by M/s Adarsh Developers in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/200305/003328 on 5 Mar 2020. Possession is promised by 28 Nov 2025. The completion date has moved by 21 months from the original filing. 50 of the 54 units on this registration are recorded sold or booked, and 1 of 16 construction stages are filed complete. 15 complaints are on record with the regulator.

At a glance

Project

  • NameADARSH STRATUSS PHASE 1
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/200305/003328
  • ReraGenie IDRG-KA-56881

Builder

  • NameM/s Adarsh Developers
  • Entity typePartnership Firm
  • Authorized SignatoryBM Jayeshankar
  • OthersT.S.Rajagopalan, Sitaram.A
  • Other registrations2 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredMar 2020First promiseFeb 2024Revised toNov 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on5 Mar 2020
  • Promised completion28 Nov 2025
  • Revised completionRevised to 28 Nov 2025 (originally 28 Feb 2024)
  • Buildings1 building record
  • Documents filed79 files

Current status

93%50 of 54 units booked
53.0%Of the estimated cost spent so far

Figures as on 30 Jan 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Adarsh Stratuss Phase 1---54054

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 30 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 97%.

Building: 77% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work97%
Foundation footing work95%
Retaining wall (All types)95%
Plinth level Beam0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)70%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc92%
Plastering inside , outside & Ceiling92%
Joinery: Doors, Windows, Ventilators etc80%
Basic work of Water supply, Sanitary and Electrification93%
Dadoing, Skirting, Flooring, Tiles work (All types)88%
Railing and Grill fixing68%
Electrification, Water supply and Sanitary Finishing53%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network80%
Weather Proof work(tile,concrete)85%
Painting40%
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 30 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes0%
Parks & Tree plantingYes0%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservationYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes0%
Smart Home AutomationYes0%
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
GasYes0%
Water and SanitationYes0%
Air Conditioning And incerntionNoNot applicable
StaircasesYes0%
LiftsYes0%
Staircases and Lift lobbies, corridor,lobbies, corridorYes0%
Fire escapesYes0%
Common entrance and exit for the building / common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,876 sq m
Named landowners2
LandownerVillageDistrict
S M VIMALA--
Madan SR--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 109.88 cr
Cost incurredRs 58.26 cr
Spent of the estimate53.02%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 109.88 crRs 58.26 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShymala Bharadwaj
EngineerChetana Engineering Consultants Pvt. Ltd

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionFeb 2024 → Nov 2024

No reason recorded in the filing

EX/PRM/KA/RERA/1251/310/PR/250129/003328Nov 2024 → Nov 2025

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka15

Case no.ComplainantRespondentFiled
00563/2026-M/s Adarsh Developers20/05/2026
00564/2026-M/s Adarsh Developers20/05/2026
00566/2026-M/s Adarsh Developers20/05/2026
00567/2026-M/s Adarsh Developers20/05/2026
00570/2026-M/s Adarsh Developers21/05/2026
00576/2026-M/s Adarsh Developers25/05/2026
00597/2026-M/s Adarsh Developers26/05/2026
00602/2026-M/s Adarsh Developers26/05/2026
00606/2026-M/s Adarsh Developers27/05/2026
00681/2026-M/s Adarsh Developers09/06/2026
00723/2026-M/s Adarsh Developers23/06/2026
00773/2026-M/s Adarsh Developers02/07/2026
00780/2026-M/s Adarsh Developers03/07/2026
00781/2026-M/s Adarsh Developers03/07/2026
00921/2026-M/s Adarsh Developers29/07/2026

Documents filed79

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/200305/003328 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Stratuss_merged.pdf30 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Stratuss PH 1.pdf30 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Stratuss PH 1.pdf30 Jan 2026
Q3 2025-26 Water supply and sewage board30 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)30 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)30 Jan 2026
Q3 2025-26 KPTCL- BESCOM30 Jan 2026
Q3 2025-26 Fire and Safety30 Jan 2026
Q3 2025-26 Airport Authority of India30 Jan 2026
Stratus ECFile: Stratus EC.pdf18 Dec 2024
Stratuss CC 28-04-2023File: Stratuss CC 28-04-2023.pdf18 Dec 2024
Engg status of workFile: Engg status of work.pdf18 Dec 2024
Engg pendingFile: Engg pending.pdf18 Dec 2024
AIRPORT NOC The NOC issued by Air port authorityFile: AIA NOC.pdf17 Feb 2020
Affidavit under sec 3(1) of Rera ActFile: Affidavit under Rule 3 (1).pdf17 Feb 2020
FORM BFile: Form B (1).pdf17 Feb 2020
JOINT AFFIDAVITFile: Joint Affidavit cum undertaking.pdf17 Feb 2020
Architect Certificate for Work Completion Schedule till DateFile: Arch status of work startuss.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engg status of work.pdf-
CA Certificate for Funds UtilizationFile: 26 CA certificate - fund utilized-Stratuss.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Arch pending work Stratuss.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engg pending.pdf-
CA Certificate for Funds required for Project CompletionFile: 27 CA certificate - funds required Stratuss.pdf-
AffidavitFile: FORM -7_compressed.pdf-
Latest Encumbrance CertificateFile: Supporting document.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails (1).xlsx-
Document 1File: 20-03-2024 to 26-06-2024- Stratuss.pdf-
Document 2File: EC 1-2-2023 to 31-12-2023 - Stratuss.pdf-
Document 3File: EC 12-10-2022 to 12-02-2023- Stratuss.pdf-
9Commencement certificate-
10-Typical floor plan-
11-Site plan layout plan_compressed-
18-Proforma sale deed-
12- Proforma Sale Agreement-
Saledeed & RTC-
42-Sectional elevation_compressed (1)-
11-Site plan layout plan_compressed-
16-Allotment letter - Adarsh Stratuss - 06022020-
19 Final Specification-
EC-
23Section 3(1) Notarized Affidavit-
Joint Affidavit cum Declaration-
merged Khatha-
Collabration agreement-
Any Other Document-
27 Conversion order_compressed-
52-24th Main Reliquishment Deed_compressed (1)-
29-FIRE NOC-
30 Airport NOC_-
31-BESCOM NOC-
32-BWSSB-
33KSPCB-CFE_compressed-
34SEIAA NOC-
42-Section AA - Development phases-
37-Site plan layout plan_compressed-
29-24th Main Fire NOC-
27 Conversion order_compressed-
49-Advocate Search Report_compressed-
Balance Sheet 2018 - 2019File: 2018-19.pdf-
Balance Sheet 2017 - 2018File: 2017-18.pdf-
Balance Sheet 2016 - 2017File: 2016-17.pdf-
Audited Profit and Loss Statement 2018 - 2019File: PL2018-19.pdf-
Audited Profit and Loss Statement 2017 - 2018File: PL2017-18.pdf-
Audited Profit and Loss Statement 2016 - 2017File: PL2016-17.pdf-
Director's Report 2018 - 2019File: 3- NA.pdf-
Director's Report 2017 - 2018File: 3- NA.pdf-
Director's Report 2016 - 2017File: 3- NA.pdf-
Cash Flow Statement 2018 - 2019File: 4- NA.pdf-
Cash Flow Statement 2017 - 2018File: 4- NA.pdf-
Auditor's Report 2018 - 2019File: AR 2018-19.pdf-
Auditor's Report 2017 - 2018File: AR 2017-18.pdf-
Auditor's Report 2016 - 2017File: AR 2016-17.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: 19-20.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: 18-19.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: 17-18.pdf-
Form B-
Prospectus/BrochureFile: Adarsh Stratuss Brochure.pdf-
Advertisement Copy 1File: Stratuss - Ad.jpg-
Tower Excel SheetFile: to uploadof 20200701 PRM_KA_RERA_1251_310_PR_200305_003328 final.xlsx-

How this compares with Bengaluru Urban

93%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ADARSH STRATUSS PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmADARSH STRATUSS PHASE 1Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: M/s Adarsh Developers

M/s Adarsh Developers has 3 registrations on RERA Karnataka, including Adarsh Citrine and ADARSH LAKE RESERVA Phase 1. Its filings declare 4 earlier projects, none of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ADARSH STRATUSS PHASE 1 is delayed beyond 28 Nov 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ADARSH STRATUSS PHASE 1?

The registered promoter entity is M/s Adarsh Developers, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ADARSH STRATUSS PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ADARSH STRATUSS PHASE 1?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at ADARSH STRATUSS PHASE 1?

The professionals named in the filing: Architect: Shymala Bharadwaj; Engineer: Chetana Engineering Consultants Pvt. Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ADARSH STRATUSS PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADARSH STRATUSS PHASE 1. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADARSH STRATUSS PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.