ADARSH PINECOURT

By Varin Infra Projects Private Limited

RG-KA-10622 · RERA PRM/KA/RERA/1251/446/PR/181210/002198 · Last updated on RERA Karnataka portal: 15 Apr 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 1 case
  • Completion date moved by 49 months
  • 3 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Mar 2026Possession promisedmoved 49 months from the original
15 of 17Construction stages donefurthest along: Weather Proof work(tile, 95%
59 of 201Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 91 documents Report an error

ADARSH PINECOURT is a Residential/Group Housing project by Varin Infra Projects Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/181210/002198 on 10 Dec 2018. Possession is promised by 6 Mar 2026. The completion date has moved by 49 months from the original filing. 142 of the 201 units on this registration are recorded sold or booked, and 15 of 17 construction stages are filed complete.

At a glance

Project

  • NameADARSH PINECOURT
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/181210/002198
  • ReraGenie IDRG-KA-10622

Builder

  • NameVarin Infra Projects Private Limited
  • Entity typeCompany
  • CINU45200KA2011PTC059980
  • Authorized SignatoryB M Jayeshankar
  • OthersYadav Kumar H R
  • Other registrations2 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredDec 2018First promiseFeb 2022Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on10 Dec 2018
  • Promised completion6 Mar 2026
  • Revised completionRevised to 6 Mar 2026 (originally 28 Feb 2022)
  • Buildings10 building records
  • Documents filed91 files

Current status

71%142 of 201 units booked
140.3%Of the estimated cost spent so far

Figures as on 15 Apr 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---20020
B---20020
C---20020
D---23023
E---20020
F---20020
G---20020
H---18018
J---20020
K---20020

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 17 construction stages are filed complete. The stage furthest along is Weather Proof work(tile, at 95%.

Building: 99% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)95%
Painting100%
Elevation work100%
Internal and External work including landscapes as per santioned drawings95%

Progress on shared amenities41

As on 15 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes0%
Sewage and Drainage SystemYes90%
Parks & Tree plantingYes80%
Street LightingYes80%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes75%
Solid waste management and disposalYes0%
Water conservationYes50%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesYes0%
Storm water drainsYes10%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes60%
Community HallYes60%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes50%
GymYes60%
ParksYes0%
Power BackupYes60%
GasYes0%
Water and SanitationYes10%
Air Conditioning And incerntionYes0%
StaircasesYes90%
LiftsYes85%
Staircases and Lift lobbies, corridor,lobbies, corridorYes75%
Fire escapesYes0%
Common entrance and exit for the building / common portico/foyer/verandahYes75%
BasementYes0%
TerraceYes0%
Outer WallYes90%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,693 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 128.20 cr
Cost incurredRs 179.84 cr
Spent of the estimate140.28%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 86.99 crRs 85.33 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 35.71 crRs 72.99 cr
On-site expenditure-Salaries of workersRs 2.32 crRs 14.18 cr
On-site expenditure-Consultants FeesRs 1.53 crRs 1.33 cr
Approval CostRs 1.50 cr-
On-site expenditure-Site OverheadRs 7.74 lakhRs 5.19 cr
RERA FeesRs 3.34 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 3.13 lakhRs 80.86 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectC B Vivek Uthaiah
EngineerDesigntree Service Consultants Pvt Ltd

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionFeb 2022 → not stated

No reason recorded in the filing

EX/PRM/KA/RERA/1251/446/PR/221206/002198not stated → Nov 2023

Reason as filed by the promoterothers

ExtensionNov 2023 → Mar 2026

No reason recorded in the filing

Litigation declared1

CaseCourtStatus
W P No. 9691/2018/2018High Court of karnataka-

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed91

As listed on the registration, under the names the promoter filed them with; the newest 80 of 91 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/181210/002198 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Pinecourt _.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Pinecourt.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Pinecourt.pdf15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Pincourt_merged.pdf31 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Pinecourt.pdf31 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: ENG Pinecourt.pdf31 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)31 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)31 Jan 2026
CertificateFile: Varin Infra Projects-incorporation certificate.pdf-
Project Details-
Already registered project ongoing detailsFile: CA_merged.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: 10-Approved BuildingPlotting Plan (2)_compressed.pdf-
Elevation, Sections, Specifications ( If changes are there )File: 19-Specification.pdf-
List Of AllotteesFile: reason.pdf-
List Of ComplaintsFile: NO.pdf-
Consent LetterFile: reason.pdf-
List Of Pending LitigationsFile: NO.pdf-
Chartered Accountant CertificateFile: CA_merged.pdf-
Notarized AffidavitFile: AFFIDAVIT - ADARSH PINECOURT.pdf-
Engineer CertificateFile: ENGG certificate.PDF-
Architect CertificateFile: ARCH.pdf-
Structural Engineer Certificate for stability of structureFile: Stability certificate.pdf-
Modification of Plan DetailsFile: 10.pdf-
Modification of Plan DetailsFile: 11- Layout PLAN.pdf-
Modification of Plan DetailsFile: CC.pdf-
Modification of Plan DetailsFile: CC.pdf-
Modification of Plan DetailsFile: merged.pdf-
Modification of Plan DetailsFile: merged.pdf-
Document 1File: kspcb renewed.pdf-
Document 2File: SEIAA.pdf-
Approved BuildingPlotting PlanFile: 10-Approved BuildingPlotting Plan (2).pdf-
Section PLANFile: 14- Section PLAN.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Arct certificate- Work completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engg certificate- Work completed.PDF-
CA Certificate for Funds UtilizationFile: CA certificate - fund utilized-Pine Court.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Arct certificate- Pending Work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engg certificate - Pending work.PDF-
CA Certificate for Funds required for Project CompletionFile: CA certificate - fund required PineCourt.pdf-
AffidavitFile: Notarised Extn Affidavit-Pinecourt.pdf-
Latest Encumbrance CertificateFile: Relevant docs.pdf-
Consent letter from 2/3rd of AllotteesFile: Relevant document.pdf-
Details Of Sold/ Un-sold UnitsFile: sold unsold units.xlsx-
Document 1File: Notarised Form-B-Pinecourt.pdf-
Document 2File: EC Merged.pdf-
Document 3File: Pine court CFE 21-02-18.pdf-
Document 4File: Pince court SEIAA 28-04-17.pdf-
Document 5File: Pinecourt 25 consents.pdf-
Document 6File: Pinecourt 27 consents.pdf-
9 CC-
11- Layout PLAN-
18-Proforma Sale Deed-
12-Sale Agreement-
13 Gift deed and RTC-
14- Section PLAN-
15- Area Dev Plan-
16-Allotment Letter-
PINECOURT specification R1-
8 EC-
22-Khata-
20 JDA & GPA-
23 other title doc-
25 Conversion order-
KSPCB-
SEIAA-
10-Approved BuildingPlotting Plan (2)-
11- Layout PLAN-
14- Section PLAN-
25 Conversion order-
Balance Sheet 2017 - 2018File: BS-2016-2017.pdf-
Balance Sheet 2016 - 2017File: BS-2015-2016.pdf-
Balance Sheet 2015 - 2016File: BS-2014-2015.pdf-
Audited Profit and Loss Statement 2017 - 2018File: 1-NA.pdf-
Audited Profit and Loss Statement 2016 - 2017File: 2-NA.pdf-
Audited Profit and Loss Statement 2015 - 2016File: 3-NA.pdf-
Director's Report 2017 - 2018File: varin infra projects DIR report FY 2016-17.pdf-
Director's Report 2016 - 2017File: varin infra projects DIR report FY 2015-2016.pdf-
Director's Report 2015 - 2016File: varin infra projects DIR report FY 2014-2015.pdf-
Cash Flow Statement 2017 - 2018File: 2016-17.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
ADARSH WISTERIA PHASE 1-OngoingNov 2021Not delivered

How this compares with Bengaluru Urban

71%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 49 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ADARSH PINECOURT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmADARSH PINECOURTOther 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 36 registered projects within 2 km.

Builder: Varin Infra Projects Private Limited

VARIN INFRA PROJECTS PRIVATE LIMITED has 3 registrations on RERA Karnataka, including ADARSH WISTERIA PHASE 1 and ADARSH PINECOURT. Its filings declare 2 earlier projects, none of them declared completed. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ADARSH PINECOURT is delayed beyond 6 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ADARSH PINECOURT?

The registered promoter entity is Varin Infra Projects Private Limited, a company as per the filing. Its CIN U45200KA2011PTC059980 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ADARSH PINECOURT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ADARSH PINECOURT?

The professionals named in the filing: Architect: C B Vivek Uthaiah; Engineer: Designtree Service Consultants Pvt Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ADARSH PINECOURT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADARSH PINECOURT. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADARSH PINECOURT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.