Adarsh Palm Retreat Mayberry-Phase 1

By Akarsh Residence Pvt Ltd

RG-KA-27039 · RERA PRM/KA/RERA/1251/310/PR/171207/002367 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 14 complaints at RERA Karnataka
  • Completion date moved by 64 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Mar 2027Possession promisedmoved 64 months from the original
4 of 17Construction stages donefurthest along: Earth work and other leveling..., 99%
139 of 312Units unsoldnot recorded sold or booked
14Complaints at RERA Karnatakaon this registration
Jump to the 119 documents Report an error

Adarsh Palm Retreat Mayberry-Phase 1 is a Residential/Group Housing project by Akarsh Residence Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/171207/002367 on 7 Dec 2017. Possession is promised by 31 Mar 2027. The completion date has moved by 64 months from the original filing. 173 of the 312 units on this registration are recorded sold or booked, and 4 of 17 construction stages are filed complete. 14 complaints are on record with the regulator.

At a glance

Project

  • NameAdarsh Palm Retreat Mayberry-Phase 1
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/171207/002367
  • ReraGenie IDRG-KA-27039

Builder

  • NameAkarsh Residence Pvt Ltd
  • Entity typeCompany
  • CINU45201KA2009PTC051265
  • Authorized SignatoryB M Jayeshankar
  • OthersT S Rajagopalan, Chandru D B
  • Other registrations2 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2017First promiseNov 2021Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 Dec 2017
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Nov 2021)
  • Buildings6 building records
  • Documents filed119 files

Current status

55%173 of 312 units booked
60.9%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---48048
Block B---48048
Block C---72072
Block D---48048
Block E---48048
Block F---48048

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 99%.

Building: 89% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work99%
Foundation footing work99%
Retaining wall (All types)100%
Plinth level Beam98%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling98%
Joinery: Doors, Windows, Ventilators etc95%
Basic work of Water supply, Sanitary and Electrification85%
Dadoing, Skirting, Flooring, Tiles work (All types)95%
Railing and Grill fixing92%
Electrification, Water supply and Sanitary Finishing80%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network80%
Weather Proof work(tile,concrete)Not applicable
Painting75%
Elevation work80%
Internal and External work including landscapes as per santioned drawings40%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes60%
Internal Roads & FootpathsYes30%
Sewage and Drainage SystemYes35%
Parks & Tree plantingNoNot applicable
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes50%
Water conservationYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes60%
Emergency Evacuation servicesYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes50%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes50%
GymYes50%
ParksNoNot applicable
Power BackupYes50%
GasNoNot applicable
Water and SanitationYes0%
Air Conditioning And incerntionNoNot applicable
StaircasesYes40%
LiftsYes0%
Staircases and Lift lobbies, corridor,lobbies, corridorYes35%
Fire escapesYes0%
Common entrance and exit for the building / common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes80%
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,749 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 314.38 cr
Cost incurredRs 191.44 cr
Spent of the estimate60.89%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 196.43 crRs 83.92 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 80.77 crRs 70.73 cr
On-site expenditure-Site OverheadRs 19.82 crRs 5.87 cr
On-site expenditure-Salaries of workersRs 12.56 crRs 28.07 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 3.14 crRs 1.39 cr
On-site expenditure-Consultants FeesRs 1.65 crRs 1.46 cr
Payment of taxesRs 98,335-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATUL AGGARWAL
EngineerChetana Engineering Consultants Pvt. Ltd

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionNov 2021 → not stated

No reason recorded in the filing

EX/PRM/KA/RERA/1251/310/PR/221121/002367not stated → Aug 2023

Reason as filed by the promoterothers

ExtensionAug 2023 → Mar 2027

No reason recorded in the filing

Complaints filed with RERA Karnataka14

Case no.ComplainantRespondentFiled
00561/2023-Akarsh Residence Pvt Ltd26/04/2023
00397/2025-Akarsh Residence Pvt Ltd07/03/2025
00398/2025-Akarsh Residence Pvt Ltd07/03/2025
00200/2026-Akarsh Residence Pvt Ltd05/03/2026
00201/2026-Akarsh Residence Pvt Ltd05/03/2026
00235/2026-Akarsh Residence Pvt Ltd10/03/2026
00269/2026-Akarsh Residence Pvt Ltd17/03/2026
00400/2026-Akarsh Residence Pvt Ltd16/04/2026
00410/2026-Akarsh Residence Pvt Ltd17/04/2026
00425/2026-Akarsh Residence Pvt Ltd21/04/2026
00476/2026-Akarsh Residence Pvt Ltd06/05/2026
00686/2026-Akarsh Residence Pvt Ltd10/06/2026
00764/2026-Akarsh Residence Pvt Ltd29/06/2026
01109/2026-Akarsh Residence Pvt Ltd08/09/2026

Documents filed119

As listed on the registration, under the names the promoter filed them with; the newest 80 of 119 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/171207/002367 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Mayberry Ph-1_.pdf15 Oct 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Mayberry.pdf15 Oct 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Mayberry PH 1.pdf15 Oct 2026
Q1 2026-27 Water supply and sewage board15 Oct 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q1 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Fire and Safety15 Oct 2026
Q1 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Mayberry Ph-1_.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Mayberry.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Mayberry PH 1.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
CertificateFile: AKRPL-Certificate ofIncorporation.pdf-
Project Details-
Already registered project ongoing detailsFile: Project Onging Details.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Site Plan & Floor Plan.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Section & Eleveation.pdf-
List Of AllotteesFile: List Of Allottes.pdf-
List Of ComplaintsFile: List of Complaints & Litigation.pdf-
Consent LetterFile: Suporting document.pdf-
List Of Pending LitigationsFile: List of Complaints & Litigation.pdf-
Chartered Accountant CertificateFile: CA Mayberry.pdf-
Notarized AffidavitFile: Mayberry Affidavit_.pdf-
Engineer CertificateFile: Eng Mayberry.pdf-
Architect CertificateFile: Arch Mayberry.pdf-
Structural Engineer Certificate for stability of structureFile: Stability Certificate.pdf-
Modification of Plan DetailsFile: 10-Building plan-Mayberry.pdf-
Modification of Plan DetailsFile: MAYBERRY MODIFIED PLAN.pdf-
Modification of Plan DetailsFile: CC 14-10-2019.pdf-
Modification of Plan DetailsFile: MAYBERRY MODIFIED LICENSE 151225.pdf-
Modification of Plan DetailsFile: List of Sold Unsold.pdf-
Modification of Plan DetailsFile: List of Sold Unsold Modified.pdf-
Document 1File: BESCOM.pdf-
Document 2File: KSPCB.pdf-
Document 3File: SEIAA.pdf-
Document 4File: Fire.pdf-
Document 5File: Airport.pdf-
Signed ConsentFile: 01 Signed Consent_.pdf-
Signed ConsentFile: 02 Signed Consent.pdf-
Signed ConsentFile: 03 Signed Consent.pdf-
Signed ConsentFile: 04 Signed Consent_.pdf-
Signed ConsentFile: 05 Signed Consent.pdf-
Signed ConsentFile: 06 Signed Consent.pdf-
Signed ConsentFile: 07 Signed Consent_.pdf-
Signed ConsentFile: 08 Signed Consent.pdf-
Signed ConsentFile: 09 Signed Consent.pdf-
Signed ConsentFile: 10 Signed Consent.pdf-
Signed ConsentFile: 11 Signed Consent_.pdf-
Section & EleveationFile: Section & Eleveation.pdf-
Site Plan & Floor PlanFile: Site Plan & Floor Plan.pdf-
Stability CertificateFile: Stability Certificate.pdf-
Mayberry AffidavitFile: Mayberry Affidavit.pdf-
Mayberry Reason For ModificatioFile: Mayberry Reason For Modificatio.pdf-
Commencement certificateFile: CC 14-10-2019.pdf-
Modified LicenseFile: MAYBERRY MODIFIED LICENSE 151225.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Arch certificate- Work completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Work completed Engg certificate.pdf-
CA Certificate for Funds UtilizationFile: 9 CA certificate - fund utilized-Mayberry.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Arch certificate- Pending work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Pending work Engg certificate.pdf-
CA Certificate for Funds required for Project CompletionFile: 8 CA certificate - funds required Mayberry.pdf-
AffidavitFile: Notarised Extn Affidavit-APR-Mayberry Ph-1.pdf-
Latest Encumbrance CertificateFile: Merged EC.pdf-
Consent letter from 2/3rd of AllotteesFile: Relevant docs.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold units details(EX).xlsx-
Document 1File: Notarised Form-B-APR-Mayberry Ph-1.pdf-
Document 2File: 04012017 Airport Mayberry.pdf-
Document 3File: 15022016 Mayberry Fire.pdf-
Document 4File: 25042017SEIAA MAYBERRY.pdf-
Document 5File: BESCOM (1).pdf-
Document 6File: KSPCB MAYBERRY 8112017.pdf-
Document 7File: Reasons for Delay.pdf-
Document 8File: 44 consents merged_compressed.pdf-
Document 9File: 10 consents.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Adarsh Palm Retreat- Phase 3, Part B-OngoingJul 2020Not delivered

How this compares with Bengaluru Urban

55%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 64 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Adarsh Palm Retreat Mayberry-Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAdarsh Palm Retreat MaybOther 33Dot size: filed unitsN

Filed coordinates, straight-line distance. 33 registered projects within 2 km.

Builder: Akarsh Residence Pvt Ltd

Akarsh Residence Pvt Ltd has 3 registrations on RERA Karnataka, including Adarsh Palm Retreat Mayberry-Phase 1 and Adarsh Palm Retreat -Phase 3 Part B. Its filings declare 1 earlier project, none of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Adarsh Palm Retreat Mayberry-Phase 1 is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Adarsh Palm Retreat Mayberry-Phase 1?

The registered promoter entity is Akarsh Residence Pvt Ltd, a company as per the filing. Its CIN U45201KA2009PTC051265 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Adarsh Palm Retreat Mayberry-Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Adarsh Palm Retreat Mayberry-Phase 1?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Adarsh Palm Retreat Mayberry-Phase 1?

The professionals named in the filing: Architect: ATUL AGGARWAL; Engineer: Chetana Engineering Consultants Pvt. Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Adarsh Palm Retreat Mayberry-Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Adarsh Palm Retreat Mayberry-Phase 1. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Adarsh Palm Retreat Mayberry-Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.