Registration approved No litigation declared Residential/Group Housing project

ADARSH LAKEFRONT RESIDENTIAL PHASE 2

By M/s Alekhya Property Developments Pvt Ltd

RG-KA-15774 · RERA PRM/KA/RERA/1251/446/PR/200323/003382 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 39 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Mar 2027Possession promisedmoved 39 months from the original
10 of 13Construction stages donefurthest along: Electrification, 99%
110 of 418Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 183 documents Report an error

ADARSH LAKEFRONT RESIDENTIAL PHASE 2 is a Residential/Group Housing project by M/s Alekhya Property Developments Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/200323/003382 on 23 Mar 2020. Possession is promised by 31 Mar 2027. The completion date has moved by 39 months from the original filing. 308 of the 418 units on this registration are recorded sold or booked, and 10 of 13 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameADARSH LAKEFRONT RESIDENTIAL PHASE 2
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/200323/003382
  • ReraGenie IDRG-KA-15774

Builder

  • NameM/s Alekhya Property Developments Pvt Ltd
  • Entity typeCompany
  • CINU45200KA2011PTC059904
  • Authorized SignatoryB M Karunesh
  • OthersK.B Shivamurthy, L.Shashikumar

Key dates

this monthRegisteredMar 2020First promiseDec 2023Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 Mar 2020
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2023)
  • Buildings9 building records
  • Documents filed183 files

Current status

74%308 of 418 units booked
98.5%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---40040
B---40040
C---40040
D---40040
E---40040
F---40040
G---40040
H---40040
J---98098

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 13 construction stages are filed complete. The stage furthest along is Electrification, at 99%.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing workNot applicable
Retaining wall (All types)Not applicable
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing99%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)Not applicable
Painting99%
Elevation work100%
Internal and External work including landscapes as per santioned drawings98%

Progress on shared amenities41

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes50%
Internal Roads & FootpathsYes40%
Sewage and Drainage SystemYes50%
Parks & Tree plantingYes30%
Street LightingYes20%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes50%
Solid waste management and disposalYes50%
Water conservationNoNot applicable
Energy managementYes0%
Fire protection and fire safety requirementsYes70%
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes40%
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes45%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes40%
ElectricityYes50%
Smart Home AutomationYes0%
CCTV SurveillanceYes0%
Club HouseYes50%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
GasYes0%
Water and SanitationYes0%
Air Conditioning And incerntionYes0%
StaircasesYes70%
LiftsYes50%
Staircases and Lift lobbies, corridor,lobbies, corridorYes50%
Fire escapesYes60%
Common entrance and exit for the building / common portico/foyer/verandahYes45%
BasementYes40%
TerraceYes50%
Outer WallYes0%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area30,493 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 316.44 cr
Cost incurredRs 311.84 cr
Spent of the estimate98.55%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 316.44 crRs 213.94 cr
On-site expenditure-Salaries of workers-Rs 16.44 cr
On-site expenditure-Consultants Fees-Rs 35.60 lakh
On-site expenditure-Site Overhead-Rs 4.28 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)-Rs 2.46 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)-Rs 74.36 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShymala Bharadwaj
EngineerChetana Engineering Consultants Pvt. Ltd

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2023 → not stated

No reason recorded in the filing

EX/PRM/KA/RERA/1251/446/PR/250129/003382not stated → Sep 2025

Reason as filed by the promoterothers

ExtensionSep 2025 → Mar 2027

No reason recorded in the filing

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
CMP/220702/0009714-M/s Alekhya Property Developments Pvt Ltd02/07/2022

Documents filed183

As listed on the registration, under the names the promoter filed them with; the newest 80 of 183 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/200323/003382 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Adarsh Lakefront Q2_.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: ALF PH 2.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: ALF PH 2.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: 7 LAKEFRONT Phase 2_.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: ALF 2.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: ALF 2.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: ALF 2_merged.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: ALF PH 2.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: ALF PH 2.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA ALF PH 2_merged.pdf31 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: ALF PH 2.pdf31 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Eng ALF PH 2.pdf31 Jan 2026
Q3 2025-26 Water supply and sewage board31 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)31 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)31 Jan 2026
Q3 2025-26 KPTCL- BESCOM31 Jan 2026
Q3 2025-26 Fire and Safety31 Jan 2026
Q3 2025-26 Airport Authority of India31 Jan 2026
Lake Front CC 23-05-2016File: Lake Front CC 23-05-2016.pdf18 Dec 2024
LAKEFRONT - Building Section - Approval copyFile: 14- LAKEFRONT - Building Section - Approval copy (1)_compressed.pdf18 Dec 2024
LAKEFRONT PHASE 2 BPFile: 10-LAKEFRONT PHASE 2 BP.pdf18 Dec 2024
Point No 1: JDA/ GPA copyFile: JDA AND GPA TO FINAL UPLOAD.pdf11 Mar 2020
Point No 2: Cost of LandFile: Point No 2.pdf11 Mar 2020
Point No 3: Sanctioned plan with DemarkationFile: Modified Sanction plan with demarcation.pdf11 Mar 2020
Area and fee discrepancyFile: Area and Fee Discrepancy.pdf4 Mar 2020
Bank Passbook and account nameFile: Bank pass book and account no.pdf4 Mar 2020
EC from date 01.11.2019 till 02.03.2020File: Common EC 01.11.2019 to 02.03.2020 _ Lakefront.pdf4 Mar 2020
JDA/GPAFile: 20 JDA,GPA,Exchange, Sharing.pdf4 Mar 2020
Cost of landFile: Cost of land.pdf4 Mar 2020
Plan Licence letterFile: Plan Licence letter full copy.pdf4 Mar 2020
Site palnFile: 01 Site plan.pdf4 Mar 2020
Basement 2 floor planFile: 02 Basement 2 floor.pdf4 Mar 2020
Basement 1 floor planFile: 03 Basement 1 floor.pdf4 Mar 2020
Ground Floor planFile: 04 Ground floor.pdf4 Mar 2020
Typical 1 floor planFile: 05 T1 floor plans.pdf4 Mar 2020
Typical 2 floor planFile: 06 T2 floor plans.pdf4 Mar 2020
Typical floor planFile: 07 Typical floors.pdf4 Mar 2020
Terrace planFile: 08 Terrace plan.pdf4 Mar 2020
Commercial planFile: 09 Commercial plans.pdf4 Mar 2020
Elevation sectionFile: 10 Elevation section.pdf4 Mar 2020
Project Details-
Already registered project ongoing detailsFile: List of On going Project.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Modified Plan License.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Supporting Document Elevation.pdf-
List Of AllotteesFile: List of Allottes.pdf-
List Of ComplaintsFile: List of Complaints.pdf-
Consent LetterFile: Supporting Document Consent Letter.pdf-
List Of Pending LitigationsFile: List of Pending Litigation.pdf-
Chartered Accountant CertificateFile: CA Certificate.pdf-
Notarized AffidavitFile: Supporting Document Nottarised Affidavit.pdf-
Engineer CertificateFile: Eng.pdf-
Architect CertificateFile: Arch.pdf-
Structural Engineer Certificate for stability of structureFile: Stability Certificate.pdf-
Modification of Plan DetailsFile: 10-LAKEFRONT PHASE 2 BP_compressed (2).pdf-
Modification of Plan DetailsFile: Lakefront ph 2 Modification Drawing merged.pdf-
Modification of Plan DetailsFile: 9- CC.pdf-
Modification of Plan DetailsFile: 9- CC.pdf-
Modification of Plan DetailsFile: Sold Unsold Details.pdf-
Modification of Plan DetailsFile: Sold Unsold Details.pdf-
Document 1File: 31 BESCOM NOC Lakefront 2020 01 08.pdf-
Document 2File: 32 BWSSB NOC.pdf-
Document 3File: 33 KSPCB.pdf-

How this compares with Bengaluru Urban

74%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 39 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ADARSH LAKEFRONT RESIDENTIAL PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: M/s Alekhya Property Developments Pvt Ltd

M/s Alekhya Property Developments Pvt Ltd has 1 registration on RERA Karnataka, including ADARSH LAKEFRONT RESIDENTIAL PHASE 2. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ADARSH LAKEFRONT RESIDENTIAL PHASE 2 is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ADARSH LAKEFRONT RESIDENTIAL PHASE 2?

The registered promoter entity is M/s Alekhya Property Developments Pvt Ltd, a company as per the filing. Its CIN U45200KA2011PTC059904 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ADARSH LAKEFRONT RESIDENTIAL PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ADARSH LAKEFRONT RESIDENTIAL PHASE 2?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at ADARSH LAKEFRONT RESIDENTIAL PHASE 2?

The professionals named in the filing: Architect: Shymala Bharadwaj; Engineer: Chetana Engineering Consultants Pvt. Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ADARSH LAKEFRONT RESIDENTIAL PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADARSH LAKEFRONT RESIDENTIAL PHASE 2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADARSH LAKEFRONT RESIDENTIAL PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.