Registration approved No litigation declared Residential/Group Housing project

ADARSH GREENS PHASE 2

By ADARSH HAVEN PRIVATE LIMITED

RG-KA-64240 · RERA PRM/KA/RERA/1251/472/PR/210409/004117 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 26 complaints at RERA Karnataka
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
May 2027Possession promisedmoved 24 months from the original
0 of 19Construction stages donefurthest along: Earth work and other leveling..., 98%
0 of 1,042Units unsoldnot recorded sold or booked
26Complaints at RERA Karnatakaon this registration
Jump to the 148 documents Report an error

ADARSH GREENS PHASE 2 is a Residential/Group Housing project by ADARSH HAVEN PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/210409/004117 on 9 Apr 2021. Possession is promised by 31 May 2027. The completion date has moved by 24 months from the original filing. 1,042 of the 1,042 units on this registration are recorded sold or booked, and 0 of 19 construction stages are filed complete. 26 complaints are on record with the regulator.

At a glance

Project

  • NameADARSH GREENS PHASE 2
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/472/PR/210409/004117
  • ReraGenie IDRG-KA-64240

Builder

  • NameADARSH HAVEN PRIVATE LIMITED
  • Entity typeCompany
  • CINU45202KA2009PTC051266
  • Authorized SignatoryB M Jayeshankar
  • OthersBalaraj B L
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredApr 2021First promiseMay 2025Revised toMay 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Apr 2021
  • Promised completion31 May 2027
  • Revised completionRevised to 31 May 2027 (originally 31 May 2025)
  • Buildings2 building records
  • Documents filed148 files

Current status

100%1042 of 1,042 units booked
64.5%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---3730373
Block B---6690669

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 19 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 98%.

Building: 69% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work98%
Foundation footing work98%
Retaining wall (All types)95%
Plinth level Beam0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)95%
RCC or MS Framed structure95%
Masonry construction: Bricks, Concrete blocks etc95%
Plastering inside , outside & Ceiling95%
Joinery: Doors, Windows, Ventilators etc80%
Basic work of Water supply, Sanitary and Electrification50%
Dadoing, Skirting, Flooring, Tiles work (All types)85%
Railing and Grill fixing75%
Electrification, Water supply and Sanitary Finishing70%
Wardrobe, Showcase, Kitchen cabinet, Puja work0%
Fire prevention and fire fighting fitting and fixture with network30%
Weather Proof work(tile,concrete)75%
Painting80%
Elevation work50%
Internal and External work including landscapes as per santioned drawings40%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes50%
Internal Roads & FootpathsYes50%
Sewage and Drainage SystemYes50%
Parks & Tree plantingYes0%
Street LightingYes30%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes60%
Solid waste management and disposalYes60%
Water conservationYes50%
Energy managementYes0%
Fire protection and fire safety requirementsYes50%
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes45%
Emergency Evacuation servicesYes0%
Storm water drainsYes80%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes80%
ElectricityYes45%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes85%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes60%
Swimming PoolYes40%
GymYes70%
ParksYes0%
Power BackupYes0%
GasYes0%
Water and SanitationYes50%
Air Conditioning And incerntionNoNot applicable
StaircasesYes50%
LiftsYes50%
Staircases and Lift lobbies, corridor,lobbies, corridorYes40%
Fire escapesYes40%
Common entrance and exit for the building / common portico/foyer/verandahYes50%
BasementYes55%
TerraceYes80%
Outer WallYes0%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area33,077 sq m
Named landowners1
LandownerVillageDistrict
ADARSH HAVEN PRIVATE LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 545.41 cr
Cost incurredRs 351.93 cr
Spent of the estimate64.53%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 352.50 crRs 321.50 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 150.00 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 22.91 crRs 8.12 lakh
On-site expenditure-Salaries of workersRs 14.10 crRs 25.03 cr
On-site expenditure-Site OverheadRs 5.35 crRs 5.13 cr
On-site expenditure-Consultants FeesRs 50.75 lakhRs 19.03 lakh
RERA FEERs 3.31 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShymala Bharadwaj
EngineerChetana Engineering Consultants Pvt. Ltd

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/472/PR/250627/004117May 2025 → May 2026

Reason as filed by the promoterFinancial crunch

ExtensionMay 2026 → May 2027

No reason recorded in the filing

Complaints filed with RERA Karnataka26

Case no.ComplainantRespondentFiled
01462/2025-ADARSH HAVEN PRIVATE LIMITED10/12/2025
00560/2026-ADARSH HAVEN PRIVATE LIMITED19/05/2026
00565/2026-ADARSH HAVEN PRIVATE LIMITED20/05/2026
00571/2026-ADARSH HAVEN PRIVATE LIMITED21/05/2026
00593/2026-ADARSH HAVEN PRIVATE LIMITED26/05/2026
00609/2026-ADARSH HAVEN PRIVATE LIMITED27/05/2026
00696/2026-ADARSH HAVEN PRIVATE LIMITED15/06/2026
00708/2026-ADARSH HAVEN PRIVATE LIMITED19/06/2026
00785/2026-ADARSH HAVEN PRIVATE LIMITED06/07/2026
00791/2026-ADARSH HAVEN PRIVATE LIMITED06/07/2026
00802/2026-ADARSH HAVEN PRIVATE LIMITED08/07/2026
00811/2026-ADARSH HAVEN PRIVATE LIMITED14/07/2026
00814/2026-ADARSH HAVEN PRIVATE LIMITED14/07/2026
00928/2026-ADARSH HAVEN PRIVATE LIMITED03/08/2026
00929/2026-ADARSH HAVEN PRIVATE LIMITED03/08/2026
00945/2026-ADARSH HAVEN PRIVATE LIMITED04/08/2026
00946/2026-ADARSH HAVEN PRIVATE LIMITED04/08/2026
00963/2026-ADARSH HAVEN PRIVATE LIMITED05/08/2026
01020/2026-ADARSH HAVEN PRIVATE LIMITED18/08/2026
01040/2026-ADARSH HAVEN PRIVATE LIMITED24/08/2026
01048/2026-ADARSH HAVEN PRIVATE LIMITED24/08/2026
01065/2026-ADARSH HAVEN PRIVATE LIMITED27/08/2026
01066/2026-ADARSH HAVEN PRIVATE LIMITED27/08/2026
01124/2026-ADARSH HAVEN PRIVATE LIMITED15/09/2026
01260/2026-ADARSH HAVEN PRIVATE LIMITED22/10/2026
01306/2026-ADARSH HAVEN PRIVATE LIMITED06/11/2026

Documents filed148

As listed on the registration, under the names the promoter filed them with; the newest 80 of 148 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/210409/004117 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA_.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Greens PH 2.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Greens PH 2.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Greens PH 2 _.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Greens PH 2.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Greens PH 2.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: GREENS PH 2.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Greens PH 2.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Greens PH 2.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Greens PH 2 _merged.pdf31 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Greens PH 2.pdf31 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Eng Greens PH 2.pdf31 Jan 2026
Q3 2025-26 Water supply and sewage board31 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)31 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)31 Jan 2026
Q3 2025-26 KPTCL- BESCOM31 Jan 2026
Q3 2025-26 Fire and Safety31 Jan 2026
Q3 2025-26 Airport Authority of India31 Jan 2026
Encumbrance certificate till March 2021File: 1 Encumbrance certificate till march 2021.pdf3 Apr 2021
Clarification of Phased Development detailsFile: 2PHASE-I & II numbering-Development Details.pdf3 Apr 2021
Commencement certificate/ Technical sanction letterFile: 3cc.pdf3 Apr 2021
Bank pass book copy - Letter from BankFile: 2 Bank Passbook copy.pdf25 Mar 2021
EC Transaction in favour of Adarsh Haven Private LimitedFile: 3 EC reflecting adarsh havens pvt ltd.pdf25 Mar 2021
Form-B on Stamp paperFile: 4 Form-B (Declaration)- Greens Phase-II (23.3.2021.pdf25 Mar 2021
Plan Licence letterFile: 6 plan licence letter.pdf25 Mar 2021
Affidavit under section 3(1) of the RERA Act uploaded on non-Judicial paperFile: 8 Affidavit- Greens Phase-II (23.3.2021.pdf25 Mar 2021
Sanction plan - Part 1File: 7 Sanctioned plans.pdf25 Mar 2021
Sanction plan - Part 2File: 7 Sanctioned plans-1-3_compressed.pdf25 Mar 2021
Sanction plan - Part 3File: 7 Sanctioned plans-4-6_compressed.pdf25 Mar 2021
CertificateFile: AHPL COI.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Work as on Date ARCH.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Greens PH 2 Work as on Date ENG.pdf-
CA Certificate for Funds UtilizationFile: 18 CA certificate - Fund Utilized Greens Phase 2.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Work Pending ARCH.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Greens PH 2 Work Pending ENG.pdf-
CA Certificate for Funds required for Project CompletionFile: 19 CA certificate - Funds Required Greens Phase 2.pdf-
AffidavitFile: Supporting Document Nottarised Affidavit.pdf-
Latest Encumbrance CertificateFile: Supporting Document EC.pdf-
Consent letter from 2/3rd of AllotteesFile: Supporting Document Consent Letter.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: Affidavit.pdf-
Document 2File: Affidavit.pdf-
Document 3File: Affidavit.pdf-
Document 4File: Form B.pdf-
Document 5File: 8 EC.pdf-
Document 6File: Greens PH 2 1.pdf-
Document 7File: Greens PH 2 2.pdf-
Document 8File: Greens PH 2 3.pdf-
Document 9File: Greens PH 2 4.pdf-
Document 10File: Greens PH 2 5.pdf-
Document 11File: Greens PH 2 6.pdf-
Document 12File: Greens PH 2 7.pdf-
Document 13File: Greens PH 2 8.pdf-
Document 14File: Greens PH 2 9.pdf-
Document 15File: Greens PH 2 10.pdf-
Document 16File: Greens PH 2 11.pdf-
Document 17File: Greens PH 2 12.pdf-
Document 18File: Greens PH 2 13.pdf-
Document 19File: Greens PH 2 14.pdf-
Document 20File: Greens PH 2 15.pdf-
Document 21File: Greens PH 2 16.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Adarsh Greens Phase 1-OngoingOct 2024Not delivered

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 24 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ADARSH GREENS PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: ADARSH HAVEN PRIVATE LIMITED

ADARSH HAVEN PRIVATE LIMITED has 2 registrations on RERA Karnataka, including ADARSH GREENS PHASE 1 and ADARSH GREENS PHASE 2. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ADARSH GREENS PHASE 2 is delayed beyond 31 May 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ADARSH GREENS PHASE 2?

The registered promoter entity is ADARSH HAVEN PRIVATE LIMITED, a company as per the filing. Its CIN U45202KA2009PTC051266 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ADARSH GREENS PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ADARSH GREENS PHASE 2?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at ADARSH GREENS PHASE 2?

The professionals named in the filing: Architect: Shymala Bharadwaj; Engineer: Chetana Engineering Consultants Pvt. Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ADARSH GREENS PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADARSH GREENS PHASE 2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADARSH GREENS PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.