Home / Browse projects / Bengaluru Urban, Karnataka / ADARSH GREENS PHASE 1
ADARSH GREENS PHASE 1
By ADARSH HAVEN PRIVATE LIMITED
RG-KA-86636 · RERA PRM/KA/RERA/1251/309/PR/201001/003607 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- 12 complaints at RERA Karnataka
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
Saved.
ADARSH GREENS PHASE 1 is a Residential/Group Housing project by ADARSH HAVEN PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/201001/003607 on 1 Oct 2020. Possession is promised by 31 Oct 2026. The completion date has moved by 24 months from the original filing. 669 of the 669 units on this registration are recorded sold or booked, and 15 of 18 construction stages are filed complete. 12 complaints are on record with the regulator.
At a glance
Project
- NameADARSH GREENS PHASE 1
- TypeResidential/Group Housing
- Location
- Bengaluru North
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/309/PR/201001/003607
- ReraGenie IDRG-KA-86636
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on1 Oct 2020
- Promised completion31 Oct 2026
- Revised completionRevised to 31 Oct 2026 (originally 31 Oct 2024)
- Buildings3 building records
- Documents filed114 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Block A | - | - | - | 193 | 0 | 193 |
| Block G | - | - | - | 309 | 0 | 309 |
| Block H | - | - | - | 167 | 0 | 167 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 18 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 99%.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Retaining wall (All types) | 100% |
| Plinth level Beam | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 99% |
| RCC or MS Framed structure | 100% |
| Masonry construction: Bricks, Concrete blocks etc | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 99% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | 100% |
| Weather Proof work(tile,concrete) | 95% |
| Painting | 100% |
| Elevation work | 100% |
| Internal and External work including landscapes as per santioned drawings | 100% |
Progress on shared amenities41
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Internal Roads & Footpaths | Yes | 100% |
| Sewage and Drainage System | Yes | 100% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | 98% |
| Solid waste management and disposal | Yes | 95% |
| Water conservation | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | 98% |
| Emergency Evacuation services | Yes | 0% |
| Storm water drains | Yes | 100% |
| Use of renewable energy | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | Yes | 98% |
| Community Hall | Yes | 100% |
| Outdoor Sports facility | Yes | 100% |
| Indoor Sports facility | Yes | 100% |
| Swimming Pool | Yes | 98% |
| Gym | Yes | 100% |
| Parks | Yes | 100% |
| Power Backup | Yes | 100% |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | 100% |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | 100% |
| Fire escapes | Yes | 100% |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | 100% |
| Basement | Yes | 100% |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 99% |
| Open parking areas and common storage spaces | Yes | 99% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 99% |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| ADARSH HAVEN PRIVATE LIMITED | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 226.42 cr | Rs 202.00 cr |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | Rs 150.00 cr | - |
| Approval cost | Rs 20.64 cr | - |
| On-site expenditure-Site Overhead | Rs 16.98 cr | Rs 1.74 cr |
| On-site expenditure-Salaries of workers | Rs 11.30 cr | Rs 38.05 cr |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 6.79 cr | Rs 4.54 cr |
| On-site expenditure-Consultants Fees | Rs 6.37 cr | Rs 10.45 lakh |
| RERA Fee | Rs 2.67 lakh | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shymala Bharadwaj |
| Engineer | Chetana Engineering Consultants Pvt. Ltd |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterothers
No reason recorded in the filing
Complaints filed with RERA Karnataka12
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 00817/2025 | - | ADARSH HAVEN PRIVATE LIMITED | 11/06/2025 |
| 00839/2025 | - | ADARSH HAVEN PRIVATE LIMITED | 12/06/2025 |
| 00957/2025 | - | ADARSH HAVEN PRIVATE LIMITED | 22/07/2025 |
| 01460/2025 | - | ADARSH HAVEN PRIVATE LIMITED | 08/12/2025 |
| 01508/2025 | - | ADARSH HAVEN PRIVATE LIMITED | 22/12/2025 |
| 00333/2026 | - | ADARSH HAVEN PRIVATE LIMITED | 02/04/2026 |
| 00337/2026 | - | ADARSH HAVEN PRIVATE LIMITED | 04/04/2026 |
| 00343/2026 | - | ADARSH HAVEN PRIVATE LIMITED | 06/04/2026 |
| 00432/2026 | - | ADARSH HAVEN PRIVATE LIMITED | 22/04/2026 |
| 00506/2026 | - | ADARSH HAVEN PRIVATE LIMITED | 11/05/2026 |
| 00575/2026 | - | ADARSH HAVEN PRIVATE LIMITED | 25/05/2026 |
| 00596/2026 | - | ADARSH HAVEN PRIVATE LIMITED | 26/05/2026 |
Documents filed114
As listed on the registration, under the names the promoter filed them with; the newest 80 of 114 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/201001/003607 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA_.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Greens PH 1.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Greens PH 1.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 Fire and Safety | 15 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Greens PH 1 CA_.pdf | 1 Oct 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Arch.pdf | 1 Oct 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Eng - 1 - 13.pdf | 1 Oct 2026 |
| Q1 2026-27 Water supply and sewage board | 1 Oct 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 1 Oct 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 1 Oct 2026 |
| Q1 2026-27 KPTCL- BESCOM | 1 Oct 2026 |
| Q1 2026-27 Fire and Safety | 1 Oct 2026 |
| Q1 2026-27 Airport Authority of India | 1 Oct 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Greens PH 1 CA_.pdf | 28 Sep 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Arch.pdf | 28 Sep 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Eng - 1 - 13.pdf | 28 Sep 2026 |
| Q4 2025-26 Water supply and sewage board | 28 Sep 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 28 Sep 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 28 Sep 2026 |
| Q4 2025-26 KPTCL- BESCOM | 28 Sep 2026 |
| Q4 2025-26 Fire and Safety | 28 Sep 2026 |
| Q4 2025-26 Airport Authority of India | 28 Sep 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Greens PH 1 _merged.pdf | 31 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Greens PH 1.pdf | 31 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Eng Greens PH 1.pdf | 31 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 31 Jan 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 31 Jan 2026 |
| Q3 2025-26 KSPCB- MOEF (Above 50 Acres) | 31 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 31 Jan 2026 |
| Q3 2025-26 Fire and Safety | 31 Jan 2026 |
| Q3 2025-26 Airport Authority of India | 31 Jan 2026 |
| EC -Greens 1File: EC -Greens 1.pdf | 18 Dec 2024 |
| Engg pending work G1File: Engg pending work G1.pdf | 18 Dec 2024 |
| Engg status of work G1File: Engg status of work G1.pdf | 18 Dec 2024 |
| TYPICAL FLOOR PLAN- BLOCK A(Wing A & B)File: 37 floor plans compressed-1-4.pdf | 11 Sep 2020 |
| TYPICAL FLOOR PLAN-BLOCK G (Wing A, B & C) & H(Wing A &B)File: 37 floor plans compressed-5-6.pdf | 11 Sep 2020 |
| AREA STATEMENT DEMARKED IN THE DEVELOPMENT PLANFile: Greens-Phasing drawing.pdf | 11 Sep 2020 |
| CertificateFile: AHPL COI.pdf | - |
| Project Details | - |
| Architect Certificate for Work Completion Schedule till DateFile: Arch status of work.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Engg status of work G1.pdf | - |
| CA Certificate for Funds UtilizationFile: 1 CA certificate - fund utilized-Greens Phase 1.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Arch pending work.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Engg pending work G1.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: 2 CA certificate - funds required Greens Phase 1.pdf | - |
| AffidavitFile: FORM EX 7.pdf | - |
| Latest Encumbrance CertificateFile: Supporting document.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| Document 1File: EC-SyNos(3 & 9)-01-11-2023to20-03-2024.pdf | - |
| Document 2File: Greens -EC-01-03-2024 TO 13-06-2024.pdf | - |
| 9 Gasthikempanahalli Building licence Copy (1) | - |
| 10 Approved building plan-compressed | - |
| 11 GREENS -DP APPROVED SCANED COPY | - |
| 18-Proforma Sale Deed | - |
| 12-Porforma Sale Agreement | - |
| 13 SALE DEED AND RTC_compressed Final | - |
| 14 Approved Building sectional ele | - |
| 10 DP APPROVED | - |
| 16 Adarsh Greens phase 1 allotment letter | - |
| 19 FINAL ADARSH GREENS SPECs | - |
| 8 EC | - |
| 23 Section Notarized Affidavit | - |
| 22 Affidavit | - |
| 24 kHATHA | - |
| 29 Fire NOC | - |
| 25 Any other document gasti | - |
| 27 CONVERSION CERTIFICATE_compressed | - |
| Unnamed document | - |
| Unnamed document | - |
| 52 Relinquishment Deed | - |
| 2 | - |
| 30 AAI NOC | - |
| 31 Bescom NOC | - |
| 32 BWSSB NOC | - |
| 33 KSPCB CFE | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep ADARSH GREENS PHASE 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 46 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: ADARSH HAVEN PRIVATE LIMITED
ADARSH HAVEN PRIVATE LIMITED has 2 registrations on RERA Karnataka, including ADARSH GREENS PHASE 1 and ADARSH GREENS PHASE 2. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if ADARSH GREENS PHASE 1 is delayed beyond 31 Oct 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of ADARSH GREENS PHASE 1?
The registered promoter entity is ADARSH HAVEN PRIVATE LIMITED. Its CIN U45202KA2009PTC051266 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in ADARSH GREENS PHASE 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ADARSH GREENS PHASE 1?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at ADARSH GREENS PHASE 1?
The professionals named in the filing: Architect: Shymala Bharadwaj; Engineer: Chetana Engineering Consultants Pvt. Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ADARSH GREENS PHASE 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.