Home / Browse projects / Bengaluru Urban, Karnataka / ABHEE SILICONSHINE

Registration transferred Residential/Group Housing project

ABHEE SILICONSHINE

By ABHEE DEVELOPERS

RG-KA-93301 · RERA PRM/KA/RERA/1251/446/PR/211215/004587 · Last updated on RERA Karnataka portal: 6 Dec 2021

Source: official RERA Karnataka filing

Red flags

  • Registration transferred

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2025Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 108 documents Report an error

ABHEE SILICONSHINE is a Residential/Group Housing project by ABHEE DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/211215/004587 on 15 Dec 2021. Possession is promised by 31 Aug 2025.

At a glance

Project

  • NameABHEE SILICONSHINE
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/211215/004587
  • ReraGenie IDRG-KA-93301

Builder

  • NameABHEE DEVELOPERS
  • Entity typePartnership Firm
  • Authorized SignatoryR NAGARAJA REDDY
  • DirectorR NAGARAJA REDDY
  • Other registrations4 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredDec 2021PromisedAug 2025

Key facts

Registration and timeline

  • StatusRegistration transferred
  • Registered on15 Dec 2021
  • Promised completion31 Aug 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed108 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ABHEE SILICON SHINE---2760276

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 6 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 6 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,295 sq m
Named landowners1
LandownerVillageDistrict
BASAVA REDDY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 72.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectB V Narendranath Reddy
EngineerVeeraiah

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed108

As listed on the registration, under the names the promoter filed them with; the newest 80 of 108 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/211215/004587 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Draft Sale Deed as per Rera ClauseFile: Draft- Sale Deed.pdf6 Dec 2021
Confirmation Deed of Chinnamma Wife of Ramaswamy and others in favour of Basava ReddyFile: 3-Deed of Confirmation 4279-2020-21.pdf2 Dec 2021
Release deed of Ramaswamy in fvaour of Basava ReddyFile: 4-Release Deed 4278-2020-21.pdf2 Dec 2021
Sale Deed in the name name of Basava Reddy Sy No 34/4File: 5-Sale Deed Doc No 4271-2020-21.pdf2 Dec 2021
Rlease Deed of Sisters Lakshmamma and others in favour of Basava Reddy & othersFile: 6-Release Deed Doc No 4258-2020-21.pdf2 Dec 2021
Sale AgreementFile: 7-Sale Agr 9030-2017-18.pdf2 Dec 2021
GPAFile: 8-GPA 592-2017-18.pdf2 Dec 2021
release DeedFile: 9-BNS-1-08572-2016-17.pdf2 Dec 2021
Confirmation Deed in favour of BasavareddyFile: 10-Deed of Confirmation 4273 20-21.pdf2 Dec 2021
sale DeedFile: 11-Doc No 19244-2020-21.pdf2 Dec 2021
Sale DeedFile: 12-Doc No 19243-2020-21.pdf2 Dec 2021
Sale DeedFile: 13-Doc No 19238-2020-21.pdf2 Dec 2021
WillFile: 14-Doc No 280-1992-93.pdf2 Dec 2021
Partition DeedFile: 15-Partition Deed dated 30-10-1992.pdf2 Dec 2021
Sale DeedFile: 16-Doc no 6258-1973-74.pdf2 Dec 2021
Sale DeedFile: 17-Doc No 3771-1972-73.pdf2 Dec 2021
Sale deedFile: 17-Doc No 3771-1972-73.pdf2 Dec 2021
Sale DeedFile: 19-Doc No 1191-1968-69.pdf2 Dec 2021
Partitio DeedFile: 20-Doc No 2241-1959-60.pdf2 Dec 2021
Parition DeedFile: 21-Doc No 4299-1963-64.pdf2 Dec 2021
Sale DeedFile: 22-Doc No 1621-1963-64.pdf2 Dec 2021
Sale DeedFile: 23-Doc No 1251-1951-52.pdf2 Dec 2021
Sale DeedFile: 24-Doc No 6597-1948-49.pdf2 Dec 2021
Sale DeedFile: 25-Doc No 2550-1948-49.pdf2 Dec 2021
Sale DeedFile: 26-Doc No 5370-1945-46.pdf2 Dec 2021
Sale DeedFile: 27-Doc No 3709-1945-46.pdf2 Dec 2021
Sale deedFile: 28-Doc No 888-1940-41.pdf2 Dec 2021
family tree of venkataramanapaFile: Family tree of Venkataramanappa.pdf2 Dec 2021
Joint Affidavit from land owner and developer regarding discloser of non mortgageFile: Affidavit cum declaration by land lord and developer for non mortgage also.pdf2 Dec 2021
broucherFile: Brochure not yet done waiting for RERA approval.pdf2 Dec 2021
project specificationFile: project specification_1.pdf2 Dec 2021
project specification as in Registered JDA also uplodedFile: Specification of as per JDA Registered Page No 63.pdf2 Dec 2021
legal reportFile: Legal Report.pdf2 Dec 2021
Draft ATSFile: Sale Agreement.pdf2 Dec 2021
construction AgreementFile: Construction Agreement.pdf2 Dec 2021
Draft Sale DeedFile: Draft- Sale Deed.pdf2 Dec 2021
1) KathaFile: Katha.pdf19 Nov 2021
2) saledeed sy no 34/5 ( old sy no. 34/2A)File: sale deed 1.pdf19 Nov 2021
3) saledeed syno 34/6 ( old no. 34/2A)File: Saledeed 2.pdf19 Nov 2021
4) Release Deed 34/7File: Release Deed.pdf19 Nov 2021
5) All these sy no are phodied from old sy no 34/2AFile: Sy no phodi.pdf19 Nov 2021
6) Guidance valueFile: Guidance Value.pdf19 Nov 2021
1. BANK STATEMENTFile: Bank statement.pdf28 Oct 2021
2. RTCFile: RTC.pdf28 Oct 2021
3. MRFile: MRcopy.pdf28 Oct 2021
4. MUTATIONFile: Mutation copy 1.pdf28 Oct 2021
5. CORRECTION ORDER SY NOFile: Conversionorder.pdf28 Oct 2021
6. CONVERSION ORDERFile: Conversionorder.pdf28 Oct 2021
7. SALEDEEDFile: Absolute saledeed 1.pdf28 Oct 2021
8. SALEDEEDFile: Absolute sale deed 2.pdf28 Oct 2021
9. SALEDEEDFile: Absolute sale deed 3.pdf28 Oct 2021
10. SALEDEEDFile: Absolute saledeed 4.pdf28 Oct 2021
11. ECFile: EC.pdf28 Oct 2021
12. KSPCBFile: KSPCB 1.pdf28 Oct 2021
13. SEIAAFile: SEIAA.pdf28 Oct 2021
14. Notarized affidavitFile: Affidavit.pdf28 Oct 2021
15. FIREFORCEFile: FIRE FORCE.pdf28 Oct 2021
16. BESCOMFile: BESCOM.pdf28 Oct 2021
17. SEIAAFile: SEIAA.pdf28 Oct 2021
1. FIRM DETAILSFile: firm details.pdf4 Oct 2021
2. PROJECT LAYOUT SITE PLANSFile: Approved Plans.pdf4 Oct 2021
4. PROJECT SPECIFICATIONFile: Specification.pdf4 Oct 2021
5. JD & DECLARATION AND FORM B AND AFFIDAVITFile: JD Declaration.pdf4 Oct 2021
6. SEIAA AcknowledgementFile: SEIAA.pdf4 Oct 2021
7. BESCOM AND WATER NOCFile: Bescom Water NOc.pdf4 Oct 2021
8. STP DRAWINGFile: STP DRAWING.pdf4 Oct 2021
9. SALEDEEDFile: Saledeed.pdf4 Oct 2021
Reply of Notice for ABHEE SILICONSHINE Ack Number : ACK/KA/RERA/1251/446/PR/210908/005231File: combinepdf.pdf19 Sep 2021
CertificateFile: ABHEE DEVELOPERS REGISTRATION CERTIFICATE.jpg-
CC (1)-
Plan-
Approved Plan-
Up Loadlater-
Plan-
Plan-
Up Loadlater-
Up Loadlater-
combinepdf-
Up Loadlater-
Up Loadlater-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
PRM/KA/RERA/1251/310/PR/210319/004024-OngoingMar 2023Not delivered

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ABHEE SILICONSHINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmABHEE SILICONSHINEOther 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 39 registered projects within 2 km.

Builder: ABHEE DEVELOPERS

ABHEE Developers has 5 registrations on RERA Karnataka, including ABHEE LOTUS and ABHEE NANDIKA. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ABHEE SILICONSHINE is delayed beyond 31 Aug 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ABHEE SILICONSHINE?

The registered promoter entity is ABHEE DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ABHEE SILICONSHINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ABHEE SILICONSHINE?

The professionals named in the filing: Architect: B V Narendranath Reddy; Engineer: Veeraiah. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ABHEE SILICONSHINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ABHEE SILICONSHINE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ABHEE SILICONSHINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.