Home / Browse projects / Bengaluru Urban, Karnataka / ABHEE SILICONSHINE

Registration approved No litigation declared Residential/Group Housing project

ABHEE SILICONSHINE

By ABHEE VENTURES PRIVATE LIMITED

RG-KA-48643 · RERA TOR/PRM/KA/RERA/1251/446/PR/230914/004587 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Aug 2026Possession promisedmoved 12 months from the original
14 of 17Construction stages donefurthest along: Painting, 95%
206 of 462Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 90 documents Report an error

ABHEE SILICONSHINE is a Residential/Group Housing project by ABHEE VENTURES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as TOR/PRM/KA/RERA/1251/446/PR/230914/004587 on 14 Sep 2023. Possession is promised by 31 Aug 2026. The completion date has moved by 12 months from the original filing. 256 of the 462 units on this registration are recorded sold or booked, and 14 of 17 construction stages are filed complete.

At a glance

Project

  • NameABHEE SILICONSHINE
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.TOR/PRM/KA/RERA/1251/446/PR/230914/004587
  • ReraGenie IDRG-KA-48643

Builder

  • NameABHEE VENTURES PRIVATE LIMITED
  • Entity typeCompany
  • CINU45203KA2021PTC153091
  • Authorized SignatoryR NAGARAJ REDDY
  • OthersPavanasutha
  • Other registrations8 more →
  • Declared earlier projects5 →

Key dates

this monthRegisteredSep 2023First promiseAug 2025Revised toAug 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Sep 2023
  • Promised completion31 Aug 2026
  • Revised completionRevised to 31 Aug 2026 (originally 31 Aug 2025)
  • Buildings4 building records
  • Documents filed90 files

Current status

55%256 of 462 units booked
76.2%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING 1---2120212
BUILDING 2---1000100
BUILDING 3---45045
BUILDING 4---1050105

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 17 construction stages are filed complete. The stage furthest along is Painting, at 95%.

Building: 99% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing90%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Painting95%
Elevation work100%
Internal and External work including landscapes as per santioned drawings90%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes100%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes85%
Street LightingYes75%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes0%
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes90%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes50%
Club HouseYes75%
Community HallYes100%
Outdoor Sports facilityYes50%
Indoor Sports facilityYes50%
Swimming PoolYes90%
GymYes50%
ParksYes70%
Power BackupYes70%
GasNoNot applicable
Water and SanitationYes90%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes80%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,295 sq m
Named landowners1
LandownerVillageDistrict
BASAVAREDDY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 177.55 cr
Cost incurredRs 135.29 cr
Spent of the estimate76.2%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 132.88 crRs 109.51 cr
Payment of taxesRs 25.72 crRs 14.64 cr
On-site expenditure-Consultants FeesRs 6.65 crRs 4.44 cr
On-site expenditure-Site OverheadRs 5.72 crRs 2.29 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 4.29 crRs 2.86 cr
On-site expenditure-Salaries of workersRs 2.31 crRs 1.54 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBV NARENDRANATH REDDY
EngineerMadamanchi Surendranadh

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/446/PR/251017/004587Aug 2025 → Aug 2026

Reason as filed by the promoterApplied for modification

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed90

As listed on the registration, under the names the promoter filed them with; the newest 80 of 90 are shown. The files themselves are available at source: search the registration number TOR/PRM/KA/RERA/1251/446/PR/230914/004587 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form- 4 Silicon Shine Q2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: silicon shine form 5 final.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6, FY 26-27-SILICON SHINE.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Abhee Silicon Shine Form 4 Q1.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: silicon shine form 5 final.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: SS 1 FORM 6 Engineer Certificate.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Silicon Shine Q4 2025-26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate_compressed.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.PDF15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate-SS.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate-Silicon shine.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate-Silicon shine.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 KPTCL- BESCOM15 Jan 2026
Explanation & Documents on PenaltyFile: Penalty Reply_compressed.pdf21 Aug 2025
Form BFile: Form -B Aft & Dec.pdf21 Aug 2025
Plan Copy , CC & Building Licence CopyFile: Plan.pdf21 Aug 2025
Form Ex-6File: Form Ex-6.pdf21 Aug 2025
Signed Copy of Sold and Unsold Units ListFile: Sold & Unsold Units List.pdf21 Aug 2025
CertificateFile: CERTIFICATE OF INCORPORATION.PDF-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Stilt Plan Licence.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Elevation Plan.pdf-
List Of AllotteesFile: List of Allottees.pdf-
List Of ComplaintsFile: No Complaints.pdf-
Consent LetterFile: Consent.pdf-
List Of Pending LitigationsFile: No Litigations.pdf-
Chartered Accountant CertificateFile: Form 1 CA.pdf-
Notarized AffidavitFile: Affidavit.pdf-
Engineer CertificateFile: FORM 3 SILICON.pdf-
Architect CertificateFile: Form-2 Architect.pdf-
Structural Engineer Certificate for stability of structureFile: Satbility Certificate.pdf-
Modification of Plan DetailsFile: Plan.pdf-
Modification of Plan DetailsFile: Site Plan.pdf-
Modification of Plan DetailsFile: CC Commencement.pdf-
Modification of Plan DetailsFile: Upload Later.pdf-
Modification of Plan DetailsFile: Sold & Unsold Units.pdf-
Modification of Plan DetailsFile: Sold & Unsold Units.pdf-
Document 1File: Water NOC.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Form Ex1.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form Ex5.pdf-
CA Certificate for Funds UtilizationFile: Form Ex3.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form Ex2.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form Ex-6.pdf-
CA Certificate for Funds required for Project CompletionFile: Form Ex4.pdf-
AffidavitFile: Affidavit Form Ex7_compressed.pdf-
Latest Encumbrance CertificateFile: EC 34-6_merged_compressed.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold & Unsold Units List.pdf-
Document 1File: ilovepdf_merged_compressed.pdf-
CC (1)-
Approved Plan-
Upload Later-
Proforma Sale Agreement-
Up Loadlater-
Plan-
Plan-
Upload Later-
Abhee Silicon Shine Brochre-
Up Loadlater-
EC (2)-
Affidavit-
JD Cum Affidavit-
Katha-
JDA Silicon-
GPA-
Conversion-
Up Loadlater-
Up Loadlater-
Up Loadlater-
Unnamed document-
Plan-
Plan-
Plan-
Conversion-
Balance Sheet 2021 - 2022File: Balance sheet.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
ABHEE KINGS COURT-OngoingJun 2026Not delivered

How this compares with Bengaluru Urban

55%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ABHEE SILICONSHINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmABHEE SILICONSHINEOther 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 39 registered projects within 2 km.

Builder: ABHEE VENTURES PRIVATE LIMITED

ABHEE VENTURES PRIVATE LIMITED has 9 registrations on RERA Karnataka, including ABHEE SRISHTI LAYOUT and ABHEE SERENITY SPRINGS. Its filings declare 5 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ABHEE SILICONSHINE is delayed beyond 31 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ABHEE SILICONSHINE?

The registered promoter entity is ABHEE VENTURES PRIVATE LIMITED, a company as per the filing. Its CIN U45203KA2021PTC153091 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ABHEE SILICONSHINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ABHEE SILICONSHINE?

The professionals named in the filing: Architect: BV NARENDRANATH REDDY; Engineer: Madamanchi Surendranadh. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ABHEE SILICONSHINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ABHEE SILICONSHINE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ABHEE SILICONSHINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.