ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / AARADHYA EASTWIND

Completed No litigation declared Residential / Group Housing project

AARADHYA EASTWIND

By MICL DEVELOPERS LLP

RG-MH-02995 · RERA P51800020183 · Last updated on MahaRERA portal: 13 Jul 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

AARADHYA EASTWIND is a Residential / Group Housing project by MICL DEVELOPERS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800020183 on 29 Mar 2019. The registration is recorded completed; possession was promised by 30 Dec 2024.

At a glance

Project

  • NameAARADHYA EASTWIND
  • TypeResidential / Group Housing
  • Location
    • TAGORE NAGAR ROAD
    • HARIYALI VILLAGE VIKHROLI EAST
    • Kurla
    • Mumbai Suburban
    • 400083
  • Pincode400083
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800020183
  • ReraGenie IDRG-MH-02995

Builder

  • NameMICL DEVELOPERS LLP
  • Entity typeOthers
  • Named personsMAN INFRACONSTRUCTION LIMITED, SUKETU PRABODH SHAH

Key dates

this monthRegisteredMar 2019PromisedDec 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Mar 2019
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed96 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AARADHYA EASTWINDNA360000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

AARADHYA EASTWIND: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed180

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots180
Closed/Covered180

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,820 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI14023.68
Proposed, not sanctioned13,989 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchM G ROAD GHATKOPAR EAST MUMBAI

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectENCLOSURRE ARCHITECTS AND INTERIOR DESIGNERS
EngineerRAVINDRA YEVALE
Chartered AccountantSHAPARIA MEHTA AND ASSOCIATES
Chartered AccountantB P SANGHANI AND ASSOCIATES
PartnerRole in project
MICL DEVELOPERS LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Mar 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Mar 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Jul 2022

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY202223.pdf13 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 27062022.pdf13 Oct 2022
Disclosure of sold/ booked inventoryFile: Sold and Unsold 30092022.pdf8 Oct 2022
Status of ConveyanceFile: Aaradhya Eastwind Lease Deed.pdf7 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 11072022.pdf11 Jul 2022
Disclosure of sold/ booked inventoryFile: Sold And Unsold 07072022.pdf7 Jul 2022
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 06072022.pdf6 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full OC and BCC Dated 30062022.pdf2 Jul 2022
Certificates of CA (Form 3)File: FORM 3 27062022.pdf27 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf16 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf6 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 05042022.pdf6 Apr 2022
Disclosure of sold/ booked inventoryFile: Sold and Unsold 06042022.pdf6 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EASTWIND FORM 2 DEC21.pdf8 Mar 2022
Certificates of CA (Form 3)File: EASTWIND FORM 3 DEC21.pdf8 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 25022022.pdf25 Feb 2022
Disclosure of sold/ booked inventoryFile: Sold and Unsold 22012021.pdf22 Jan 2022
Details of encumbrancesFile: Declaration for no Encumbrances.pdf3 Dec 2021
Certificates of CA (Form 3)File: FORM 3 29102021.pdf30 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 27102021.pdf28 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 02102021.pdf7 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 06102021.pdf7 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A 06102021.pdf7 Oct 2021
Details of encumbrancesFile: CERSAI Sept 21.pdf5 Oct 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold 30092021.pdf5 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: Full CC.pdf27 Aug 2021
Declaration about Commencement CertificateFile: Format D Full CC.pdf27 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 17082021.pdf27 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 14082021.pdf27 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 14082021.pdf27 Aug 2021
Certificates of CA (Form 3)File: Form 3 30062021.pdf11 Aug 2021
Details of encumbrancesFile: CERSAI.pdf4 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold 30062021.pdf13 Jul 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold Rehab 30062021.pdf13 Jul 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Aaradhya Eastwind Society Registration.pdf22 Jun 2021
Proforma of Allotment letterFile: Draft AFS.pdf17 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: Declaration Format D and CC 16062021.pdf16 Jun 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory as on 31032021.pdf8 Jun 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 as on 31032021.pdf4 Jun 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 as on 31032021.pdf4 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2 A 03062021.pdf4 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2 A 03062021.pdf4 Jun 2021
Certificates of CA (Form 3)File: FORM 3 as on 31032021.pdf4 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 as on 31032021.pdf4 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: CC 11052021.pdf13 May 2021
Commencement Certificates / NA Order for plotted developmentFile: CC 11052021.pdf13 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 30062020.PDF27 Nov 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30092020.pdf27 Nov 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30092020.pdf27 Nov 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 30092020.pdf27 Nov 2020
Certificates of CA (Form 3)File: Form 3 30092020.pdf27 Nov 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 17092020.pdf17 Sep 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 17092020.pdf17 Sep 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A 17092020.pdf17 Sep 2020
Certificates of CA (Form 3)File: FORM 3 17092020.pdf17 Sep 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 06072020.pdf29 Jul 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 06072020.pdf29 Jul 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 06072020.pdf29 Jul 2020
Certificates of CA (Form 3)File: Form 3 31032020.pdf15 Jul 2020
Certificates of CA (Form 5)File: Form 5 31032020.pdf15 Jul 2020
Details of Restarting of Construction work post lockdownFile: LOCKDOWN DETAILS.pdf17 Jun 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 14022020.pdf26 Feb 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 25022020.pdf25 Feb 2020
Certificates of CA (Form 3)File: Form 3 31122019.pdf24 Feb 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 31122020.pdf18 Feb 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf2 Jan 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 25092019.pdf6 Dec 2019
Certificates of CA (Form 3)File: Form 3 30092019.pdf5 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf25 Nov 2019
Certificates of CA (Form 3)File: Form 3 30062019.pdf17 Sep 2019
Details of encumbrancesFile: ENCUMBRANCE - KOTAK 16042019.pdf13 Jun 2019
Certificates of CA (Form 5)File: Form 5 31032019.pdf7 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: CC 26042019.pdf30 Apr 2019
Layout approvalFile: AE IOA PAGE ONE AND TWO.pdf27 Mar 2019
Building plan approvalFile: AE IOA PAGE ONE AND TWO.pdf27 Mar 2019
Building plan approvalFile: AE IOA PAGE THREE AND FOUR.pdf27 Mar 2019
Building plan approvalFile: AE IOA PAGE FIVE.pdf27 Mar 2019
Building plan approvalFile: AE IOA PAGE SIX.pdf27 Mar 2019
Building plan approvalFile: AE IOA PAGE SEVEN.pdf27 Mar 2019
Building plan approvalFile: AE IOA PAGE EIGHT.pdf27 Mar 2019

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AARADHYA EASTWIND on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near HARIYALI VILLAGE VIKHROLI EAST6,700+ in Mumbai Suburban

2 kmAARADHYA EASTWINDCompleted 2Lapsed / revoked 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: MICL DEVELOPERS LLP

MICL DEVELOPERS LLP has 1 registration on MahaRERA, including AARADHYA EASTWIND. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if AARADHYA EASTWIND is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AARADHYA EASTWIND?

The registered promoter entity is MICL DEVELOPERS LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AARADHYA EASTWIND?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AARADHYA EASTWIND?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AARADHYA EASTWIND?

The professionals named in the filing: Architect: ENCLOSURRE ARCHITECTS AND INTERIOR DESIGNERS; Engineer: RAVINDRA YEVALE; Chartered Accountant: SHAPARIA MEHTA AND ASSOCIATES; Chartered Accountant: B P SANGHANI AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AARADHYA EASTWIND?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AARADHYA EASTWIND. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AARADHYA EASTWIND to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.