ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / 63 Degree East - Tower F

Registration approved No litigation declared Residential/Group Housing project

63 Degree East - Tower F

By APG Intelli Homes Private Limited

RG-KA-32788 · RERA PRM/KA/RERA/1251/446/PR/240122/004655 · Last updated on RERA Karnataka portal: 30 Sep 2025

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jul 2025Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 124 documents Report an error

63 Degree East - Tower F is a Residential/Group Housing project by APG Intelli Homes Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/240122/004655 on 24 Jan 2022. Possession is promised by 31 Jul 2025.

At a glance

Project

  • Name63 Degree East - Tower F
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560035
  • Pincode560035
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/240122/004655
  • ReraGenie IDRG-KA-32788

Builder

  • NameAPG Intelli Homes Private Limited
  • Entity typeCompany
  • CINU70100KA2014PTC077189
  • GSTIN29AANCA0060C1Z1
  • Authorized SignatoryAkshay Kishore Dewani
  • CeoAkshay Kishore Dewani
  • DirectorsAkshay Kishore Dewani, Sachin Vora
  • Project HeadAkshay Kishore Dewani
  • Other registrations6 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2022PromisedJul 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on24 Jan 2022
  • Promised completion31 Jul 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed124 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
63 Degree East - Tower F---88088

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 30 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 30 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesYes-
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyYes-
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesYes-
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,198 sq m
Named landowners5
LandownerVillageDistrict
APG Intelli Homes Private Limited--
APG Intelli Homes Private Limited--
APG Intelli Homes Private Limited--
APG Intelli Homes Private Limited--
APG Intelli Homes Private Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 75.87 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 49.33 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 23.27 cr-
Approval CostRs 1.93 cr-
On-site expenditure-Consultants FeesRs 1.34 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANOJ LADHAD
EngineerNeminath P Parigond, Cratis Designers Pvt Ltd
Chartered AccountantY S Shetty & Company

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed124

As listed on the registration, under the names the promoter filed them with; the newest 80 of 124 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/240122/004655 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Covering LetterFile: Covering Letter.pdf30 Sep 2025
Occupancy CertificateFile: 63 DEGREE EAST TOWER F - OCCUPANCY CERTIFICATE.pdf30 Sep 2025
PIC 1File: PIC 1.jpg30 Sep 2025
PIC 2File: PIC 2.jpg30 Sep 2025
PIC 3File: PIC 3.jpg30 Sep 2025
PIC 4File: PIC 4.jpg30 Sep 2025
PIC 5File: PIC 5.jpg30 Sep 2025
PIC 6File: PIC 6.jpg30 Sep 2025
Agreement to sell -Tower FFile: Agreement to Sell -Tower F.pdf20 Jan 2022
covering LetterFile: Covering Letter.pdf6 Jan 2022
Agreement to sellFile: Agreement to Sell -Tower F.pdf6 Jan 2022
Covering LatterFile: Covering Letter -Tower F.pdf22 Dec 2021
Unaudited Financial 2020-21File: Annexure 1-Unaudited Financial 2020-21.pdf22 Dec 2021
Notarized form-b in RERA prescribed formFile: Annexure 2-Form B.pdf22 Dec 2021
Notarized non litigation affidavitFile: Annexure 3-Non-Litigation Affidavit.pdf22 Dec 2021
Site plan with Demark DrawingFile: Annexure 4-Site Plan with Demark Drawing.pdf22 Dec 2021
Basement PlanFile: Annexure 5-Basement Plan.pdf22 Dec 2021
Ground Floor PlanFile: Annexure 6-Ground Floor Plan.pdf22 Dec 2021
Typical Floor Plan (GF 1st 2nd 3rd 7th and 11th)File: Annexure 7-Typical(GF 1st 2nd 3rd 7th and 11th) Floor Plan.pdf22 Dec 2021
Typical Floor Plan (4th 5th 6th 8th 9th 10th 12th 13th and 14th)File: Annexure 8-Typical (4th 5th 6th 8th 9th 10th 12th 13th and 14th)Floor plan.pdf22 Dec 2021
Section & Elevation PlanFile: Annexure 9-Section & Elevation.pdf22 Dec 2021
Relinquishment DeedFile: Annexure 10 - Relinquishment Deed.pdf22 Dec 2021
Common Area to alloteeFile: Annexure 11-Common Area to allotee.pdf22 Dec 2021
Engineer CertificateFile: Annexure 12-Engineer Certificate.pdf22 Dec 2021
Architect CertificateFile: Annexure 13-Architect Certificate.pdf22 Dec 2021
CA CertificateFile: Annexure 14-CA Certificate.pdf22 Dec 2021
Attached AOSFile: Annexure 15-Agreement to Sell.pdf22 Dec 2021
Provision for STPFile: Annexure 16-Provison for STP.pdf22 Dec 2021
Other Common Area AmentiesFile: Annexure 17-Other Common Area Amenties.pdf22 Dec 2021
RTC, survey 69/1-
Mutation, survey 69/1-
Encumbrance Certificate, survey 69/1-
Conversion/Alienation Order, survey 69/1-
Sale/Title/Gift Deed, survey 69/1-
Khatha, survey 69/1-
RTC, survey 69/2-
Mutation, survey 69/2-
Encumbrance Certificate, survey 69/2-
Conversion/Alienation Order, survey 69/2-
Sale/Title/Gift Deed, survey 69/2-
Khatha, survey 69/2-
RTC, survey 69/3-
Mutation, survey 69/3-
Encumbrance Certificate, survey 69/3-
Conversion/Alienation Order, survey 69/3-
Sale/Title/Gift Deed, survey 69/3-
Khatha, survey 69/3-
RTC, survey 69/4-
Mutation, survey 69/4-
Encumbrance Certificate, survey 69/4-
Conversion/Alienation Order, survey 69/4-
Sale/Title/Gift Deed, survey 69/4-
Khatha, survey 69/4-
RTC, survey 171-
Mutation, survey 171-
Encumbrance Certificate, survey 171-
Conversion/Alienation Order, survey 171-
Sale/Title/Gift Deed, survey 171-
Khatha, survey 171-
Registration CertificateFile: Annexure 1-COI.pdf-
Organization StructureFile: Annexure 11-Org Structure.pdf-
Certificate issued by CA Form 1File: Annexure 14-CA Certificate.pdf-
Certificate issued by Architect Form 2File: Annexure 13-Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Annexure 12-Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Annexure 35-69-3 RTC.pdf-
Certificate from Chartered Account-
Balance Sheet 2020 - 2021File: Not yet Audited.pdf-
Balance Sheet 2019 - 2020File: Annexure 49b-BS 19-20.pdf-
Balance Sheet 2018 - 2019File: Annexure 49a-BS 18-19.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Not yet Audited.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Annexure 50b-P&L 19-20.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Annexure 50a-P&L 18-19.pdf-
Director's Report 2020 - 2021File: Not yet Audited.pdf-
Director's Report 2019 - 2020File: Annexure 51b-DR 19-20.pdf-
Director's Report 2018 - 2019File: Annexure 51a-DR 18-19.pdf-
Cash Flow Statement 2020 - 2021File: Not yet Audited.pdf-
Cash Flow Statement 2019 - 2020File: Annexure 52b-CF 19-20.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep 63 Degree East - Tower F on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 km63 Degree East - Tower FOther 63Dot size: filed unitsN

Filed coordinates, straight-line distance. 63 registered projects within 2 km.

Builder: APG Intelli Homes Private Limited

APG Intelli Homes Private Limited has 7 registrations on RERA Karnataka, including 63 Degree East - Tower C & D and Leaves & Lives Phase 1. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if 63 Degree East - Tower F is delayed beyond 31 Jul 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of 63 Degree East - Tower F?

The registered promoter entity is APG Intelli Homes Private Limited, a company as per the filing. Its CIN U70100KA2014PTC077189 and GSTIN 29AANCA0060C1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in 63 Degree East - Tower F?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at 63 Degree East - Tower F?

The professionals named in the filing: Architect: MANOJ LADHAD; Engineer: Neminath P Parigond, Cratis Designers Pvt Ltd; Chartered Accountant: Y S Shetty & Company. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 63 Degree East - Tower F?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 63 Degree East - Tower F. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 63 Degree East - Tower F to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.