VIVANTA REALTY: RERA track record
GSTIN 27AAJFV6269P1Z4 · Partnership · attribution by exact filing name, entity resolution in progress
VIVANTA REALTY has 10 registrations on MahaRERA, including VIVANTA LIFE VIPUL PHASE 1 and VIVANTA LIFE VISHAKHA PHASE I. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 3 past projects completed on time.
Projects by this developer
Showing all 10 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| YASHADA EARTHSONGP52100079396 | RAVET, Pune, 412101 | 599 | 34% | 3 Mar 2025 | Registered |
| YASHADA WINDSONGP52100050915 | RAVET, Pune, 412101 | 407 | 99% | 15 May 2023 | Registered |
| VANTAGE TWENTY ONEP52100022932 | PK CHOWK PIMPALE SOUDAGER, Pune, 411027 | 379 | 98% | 5 Nov 2019 | Registered |
| vipul commercialPC1260002501573 | BORHADEWADI, Pune, 412105 | 40 | 5% | 25 Nov 2025 | Registered |
| VIVANTA LIFE VEDIKA PHASE 1P52100019022 | PK CHOWK, NR PK INTERNATIONAL SCHOOL, Pune, 411027 | - | - | 28 Dec 2018 | Completed |
| VIVANTA LIFE VERONIKAP52100002206 | Pimpale Saudagar, Pune, 411027 | - | - | 31 Jul 2017 | Completed |
| VIVANTA LIFE VIPUL PHASE 1P52100001347 | Pimpri Chinchawad (M Corp.), Pune, 412105 | - | - | 27 Jul 2017 | Completed |
| VIVANTA LIFE VISHAKHA PHASE IP52100004348 | 411015 | - | - | 9 Aug 2017 | Completed |
| VIVANTA LIFE VISHAKHA PHASE IIP52100002690 | 411045 | - | - | 2 Aug 2017 | Completed |
| Vivanta Life Vishakha Phase IIIP52100015199 | KAMAL PARK, 411045 | - | - | 7 Feb 2018 | Completed |
What this promoter declares as its own experience
VIVANTA REALTY declares experience on 5 earlier projects. 2 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
2 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| VIVANTA LIFE VIBHA | 31 Mar 2016 | 31 Mar 2016 | On time |
| VIVANTA LIFE VISHAKHA PHASE 1 | 30 Apr 2019 | 27 Nov 2017 | On time |
| VIVANTA LIFE VIPUL PHASE 1 | 31 Oct 2022 | 7 Dec 2018 | On time |
| YASHADA WINDSONG P52100050915 | 31 Dec 2026 | Not completed yet | Ongoing |
| VANTAGE TWENTY ONE P52100022932 | 1 Oct 2027 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify VIVANTA REALTY as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAJFV6269P1Z4 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with VIVANTA REALTY?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.