UNNATHI ASSOCIATES: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
UNNATHI ASSOCIATES has 14 registrations in this build, including RAUNAK HEIGHTS and RAUNAK DELIGHT. Its filings disclose 2 earlier MahaRERA projects: 2 of 2 past projects completed on time. Litigation is declared on 7 of its registrations.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| RAUNAK HEIGHTS | Thane, Maharashtra | - | - | Completed |
| RAUNAK DELIGHT | Thane, Maharashtra | - | - | Completed |
| RAUNAK BLISS PHASE A | Thane, Maharashtra | - | - | Completed |
| RAUNAK BLISS PHASE A - A3 | Thane, Maharashtra | 242 | 98% | Completed |
| RAUNAK BLISS - B1 | Thane, Maharashtra | - | - | Registered |
| RAUNAK BLISS - B2 | Thane, Maharashtra | - | - | Registered |
| RAUNAK 108 | Thane, Maharashtra | 760 | 73% | Registered |
| RAUNAK BLISS B1 | Thane, Maharashtra | 273 | 67% | Registered |
| RAUNAK BLISS B2 | Thane, Maharashtra | 273 | 75% | Registered |
| RAUNAK BLISS B3 | Thane, Maharashtra | 273 | 99% | Registered |
| RAUNAK BLISS A4 | Thane, Maharashtra | 273 | 76% | Registered |
| Raunak Bliss B4 | Thane, Maharashtra | 273 | 100% | Registered |
| Raunak Bliss B5 | Thane, Maharashtra | 273 | 80% | Registered |
| Raunak Bliss B6 | Thane, Maharashtra | 273 | 64% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| UNNATHI GREENS PHASE VII | 31 Mar 2012 | 30 Mar 2012 | On time |
| RAUNAK HEIGHTS BUILDING H1 | 31 Dec 2015 | 9 Nov 2015 | On time |
Frequently asked questions
How do I verify UNNATHI ASSOCIATES as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with UNNATHI ASSOCIATES?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make UNNATHI ASSOCIATES unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.