SINEW DEVELOPERS PRIVATE LIMITED: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

SINEW DEVELOPERS PRIVATE LIMITED has 2 registrations on MahaRERA, including 45 NIRVANA HILLS -C1 WING and 45 NIRVAANA HILL - C2 WING. Its filings disclose 9 earlier MahaRERA projects: declares 5 of 9 past projects completed on time. Litigation is declared on 1 of its registrations.

2RERA registrations
9Past projects disclosed
on timeMedian delivery slip
1Registrations with litigation
Follow this developer. An email when SINEW DEVELOPERS PRIVATE LIMITED registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 2 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
45 NIRVAANA HILL - C2 WINGP52100008687KARVE ROAD, Pune, 41100412150%19 Aug 2017Registered
45 NIRVANA HILLS -C1 WINGP52100007586Pune (M Corp.), Pune, 411004--17 Aug 2017Registration lapsed

What this promoter declares as its own experience

SINEW DEVELOPERS PRIVATE LIMITED declares experience on 9 earlier projects. 9 of them carry a registration number we could match on MahaRERA, and all of them are registered under a different promoter name.

9 of these declarations can be compared with the dates those projects' own registrations hold. On 7, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on 2 of the 5 completions recorded here as on time: measured against the original deadline the register itself holds, those were finished after it.

Declared projectRegistered toStatus
KUL TULIPKUMAR BUILDERS MUMBAI REALTY PVT LTDCompleted
KUL Utsav Phase I -Building FKumar BuildersCompleted
KUL Utsav Phase I -Building GKumar BuildersCompleted
Kul Utsav Ph 1 C buildingKumar BuildersCompleted
Kul Utsav Ph I E BuildingKumar BuildersCompleted
Kul Utsav Phase I - Building DKumar BuildersCompleted
Shantiniketan Phase II A3Kumar Builders ConsortiumCompleted
Shantiniketan Phase II A4Kumar Builders ConsortiumCompleted
KUL COURTKumar Builders Mumbai Realty Pvt LtdCompleted

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
KUL Utsav Phase I -Building F
P52100009849
23 Dec 201930 Jul 2020+7 months
KUL COURT
P51800009338
30 Dec 201911 Jan 2024+48 months
Shantiniketan Phase II A4
P52100006736
9 Mar 202026 Nov 2019On time
Shantiniketan Phase II A3
P52100005467
9 Mar 202026 Nov 2019On time
Kul Utsav Ph 1 C building
P52100007155
26 Oct 20203 Sep 2018On time
Kul Utsav Phase I - Building D
P52100007160
30 Oct 20206 Apr 2018On time
Kul Utsav Ph I E Building
P52100007157
14 Nov 20206 Apr 2018On time
KUL TULIP
P51900011786
12 Dec 202021 Aug 2023+32 months
KUL Utsav Phase I -Building G
P52100003489
30 Jun 202319 Jul 2023+1 months

Frequently asked questions

How do I verify SINEW DEVELOPERS PRIVATE LIMITED as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with SINEW DEVELOPERS PRIVATE LIMITED?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make SINEW DEVELOPERS PRIVATE LIMITED unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.