ROMELL REAL ESTATE PRIVATE LIMITED has 15 registrations on MahaRERA, including TRIMURTI CHSL PHASE I - UPTO 15TH FLOOR and TRIMURTI CHSL PHASE II - 16TH TO 18TH FLOOR. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 5 past projects completed on time.
Projects by this developer
Showing all 15 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Romell EspalierP51800079081 | Vile Parle East, Mumbai Suburban, 400057 | 133 | 0% | 3 Feb 2025 | Registered |
| Romell ArianaPR1180002400010 | Borivali(West), Mumbai Suburban, 400103 | 110 | 6% | 20 Sep 2024 | Registered |
| ROMELL ALLUREP51800023445 | BORIVALI EAST, Mumbai Suburban, 400066 | - | - | 16 Dec 2019 | Completed |
| ROMELL CORNERSTONEP51800032709 | EKSAR VILLAGE, Mumbai Suburban, 400103 | - | - | 24 Jan 2022 | Completed |
| ROMELL DIVA PHASE II - 17TH TO 20TH FOORP51800014389 | Borivali, Mumbai Suburban, 400064 | - | - | 29 Nov 2017 | Completed |
| ROMELL DIVA PHASE III - 21ST TO 23RD FLOORP51800014484 | Borivali, Mumbai Suburban, 400064 | - | - | 4 Dec 2017 | Completed |
| ROMELL EMPRESS C WING PHASE I - UPTO 13TH FLOORP51800018513 | I C COLONY, BORIVALI WEST, Mumbai Suburban, 400103 | - | - | 12 Nov 2018 | Completed |
| ROMELL EMPRESS C WING PHASE II - 14TH TO 17TH FLOORP51800021923 | BORIVALI WEST, Mumbai Suburban, 400103 | - | - | 8 Aug 2019 | Completed |
| ROMELL EMPRESS C WING PHASE III - 18TH TO 22ND FLOORP51800025888 | BORIVALI WEST, Mumbai Suburban, 400102 | - | - | 27 Jul 2020 | Completed |
| ROMELL EUPHORIAP51800026583 | BORIVALI WEST, Mumbai Suburban, 400103 | - | - | 6 Oct 2020 | Completed |
| ROMELL RHYTHMP51800022142 | MALAD WEST, Mumbai Suburban, 400064 | - | - | 28 Aug 2019 | Completed |
| ROMELL SERENEP51800034025 | Borivali West, Mumbai Suburban, 400103 | - | - | 17 Mar 2022 | Completed |
| ROMELL VASANTHIP51800022238 | MULUND EAST, Mumbai Suburban, 400081 | - | - | 5 Sep 2019 | Completed |
| TRIMURTI CHSL PHASE I - UPTO 15TH FLOORP51800007589 | Kurla, Mumbai Suburban, 400081 | - | - | 17 Aug 2017 | Completed |
| TRIMURTI CHSL PHASE II - 16TH TO 18TH FLOORP51800008089 | Kurla, Mumbai Suburban, 400081 | - | - | 18 Aug 2017 | Completed |
What this promoter declares as its own experience
ROMELL REAL ESTATE PRIVATE LIMITED declares experience on 5 earlier projects. None of them carries a registration number we could match on MahaRERA, which is usual for work done before the register existed.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Romell Umiya Grandeur Phase I - Upto 19th Floor | 31 Dec 2014 | 19 Oct 2016 | +22 months |
| ROMELL DIVA PHASE I - UPTO 16TH FLOOR | 30 Jun 2015 | 29 Apr 2017 | +22 months |
| ROMELL EMPRESS C WING PHASE II - 14TH TO 17TH FLOOR | 30 Jun 2022 | 5 Mar 2020 | On time |
| ROMELL EMPRESS C WING PHASE I - UPTO 13TH FLOOR | 31 Dec 2022 | 4 May 2019 | On time |
| ROMELL DIVA PHASE II - 17TH TO 20TH FLOOR | 31 Dec 2024 | 26 Apr 2019 | On time |
Frequently asked questions
How do I verify ROMELL REAL ESTATE PRIVATE LIMITED as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with ROMELL REAL ESTATE PRIVATE LIMITED?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.