NAHAR BUILDERS LIMITED: RERA track record
CIN U45202MH2011PLC221752 · GSTIN 27AADCN8065A1ZL · Company · attribution by exact filing name, entity resolution in progress
NAHAR BUILDERS LIMITED has 1 registration in this build, including NAHAR'S CHANDI VALLEY - PHASE I. Its filings disclose 8 earlier MahaRERA projects: 5 of 7 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| NAHAR'S CHANDI VALLEY - PHASE I | Mumbai Suburban, Maharashtra | 308 | 25% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| R-12,10 LAUREL-LILAC | 30 Jun 2013 | 28 Feb 2014 | +8 months |
| R-18 White Lily and Water Lily | 31 Dec 2014 | 7 Jul 2016 | +18 months |
| R-20 Nahar Business Center | 23 Jan 2015 | 23 Jan 2015 | On time |
| R-12/7 and 8 Barberny-Bryony | 12 Aug 2015 | 31 Dec 2014 | On time |
| R 12 /11, YVONNE | 12 Aug 2015 | 31 Dec 2014 | On time |
| OLIVIA P51800003168 | 25 Dec 2022 | 25 Dec 2022 | On time |
| Winterberry Tower and Plaza P51800047208 | 31 Mar 2026 | Not completed yet | Ongoing |
| AMARYLLIS TOWERS AND PLAZA P51800028801 | 30 Jun 2026 | 29 Apr 2025 | On time |
Frequently asked questions
How do I verify NAHAR BUILDERS LIMITED as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45202MH2011PLC221752 and GSTIN 27AADCN8065A1ZL on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with NAHAR BUILDERS LIMITED?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.