MUMBAI HOUSING AND AREA DEVELOPMENT BOARD: RERA track record
Public Authority ยท attribution by exact filing name, entity resolution in progress
MUMBAI HOUSING AND AREA DEVELOPMENT BOARD has 21 registrations in this build, including Construction of 83 LIG Ts on Guest plot CTS no 43 Pt of Unnatagar, Village Pahadi goregaon and Construcion of 28 LIG tenement on Plot OB 8,Siddharth nagar ,Goregaon west,Mumbai. Its filings disclose 12 earlier MahaRERA projects: 3 of 11 past projects completed on time.
Projects in this build
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| R-10 MANKHURD EWS AND LIG | 24 Feb 2012 | 30 Jun 2016 | +52 months |
| CONSTRUCTION OF 282 TS LIG | 31 Mar 2013 | 17 Jun 2013 | +3 months |
| Bharat Mill P51900000032 | 31 Dec 2017 | 19 Dec 2018 | +12 months |
| TUNGWA POWAI | 31 Mar 2018 | 31 Mar 2018 | On time |
| Construction of 86 Tenements out of 430 MIG tenements of old Magathane village Borivali P51800000063 | 13 Dec 2018 | 30 Mar 2019 | +4 months |
| TUNGWA POWAI P51800000056 | 31 Mar 2019 | 25 Mar 2021 | +24 months |
| R-4 mankhurd P51800000034 | 31 Jul 2019 | 11 Feb 2022 | +30 months |
| Construction of 406 TR TS 442 EWS 258 MIG TS at Gavanpada Mulund east Mumbai P51800000024 | 31 Dec 2019 | 30 Mar 2019 | On time |
| Pratiksha Nagar Phase IV P51900000050 | 30 Oct 2020 | 1 Jul 2018 | On time |
| VIRAR PROJECT | 28 Feb 2023 | 31 May 2023 | +3 months |
| Construction of EWS,LIG,MIG-HIG T/s. on Open Plot-A and B S.NO 29P CTS NO50A Pahadi Goregaon Mumbai P51800053837 | 31 Dec 2024 | 18 Jun 2025 | +6 months |
| Const of 1041 TR Ts 69 shops 1950 EWS 224 MIG at Kannamwar nagar vikhroli east P51800000058 | 31 Mar 2026 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify MUMBAI HOUSING AND AREA DEVELOPMENT BOARD as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with MUMBAI HOUSING AND AREA DEVELOPMENT BOARD?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.