LAXMI LEELA BUILDCON LLP: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

LAXMI LEELA BUILDCON LLP has 1 registration in this build, including LAXMI MADHUVAN. Its filings disclose 5 earlier MahaRERA projects: 1 of 3 past projects completed on time.

1Registrations in this build
5Past projects disclosed
+17 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
LAXMI MADHUVANMumbai Suburban, Maharashtra--Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Laxmi Heights
31 Dec 201828 Jul 2023+55 months
Laxmi Callista
30 Sep 201928 Feb 2021+17 months
LUXURY CHSL LTD
P51800050568
30 Jun 2025Not completed yetOngoing
LAXMI SHRUSHTI - WING B
P51800030965
31 Aug 202521 Feb 2025On time
LAXMI MADHUVAN
P51800078958
31 May 2027Not completed yetOngoing

Frequently asked questions

How do I verify LAXMI LEELA BUILDCON LLP as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with LAXMI LEELA BUILDCON LLP?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.