Arkade Developers Ltd: RERA track record
CIN U45200MH1986PLC039813 · GSTIN 27AAACA3578Q1Z4 · Company · attribution by exact filing name, entity resolution in progress
Arkade Developers Ltd has 2 registrations on MahaRERA, including Arkade Pearl 4 and Arkade Evoke. Its filings disclose 16 earlier MahaRERA projects: declares 16 of 16 past projects completed on time. Litigation is declared on 1 of its registrations.
Projects by this developer
Showing all 2 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Arkade EvokePR1180002502642 | Borivali, Mumbai Suburban, 400104 | 145 | 7% | 9 Mar 2026 | Registered |
| Arkade Pearl 4P51800079922 | Vile Parle (East), Mumbai Suburban, 400057 | 16 | 31% | 1 Apr 2025 | Registered |
What this promoter declares as its own experience
Arkade Developers Ltd declares experience on 16 earlier projects. 14 of them carry a registration number we could match on MahaRERA, and all of them are registered under a different promoter name.
14 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds. A completion date is also recorded against 3 registrations MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.
| Declared project | Registered to | Status |
|---|---|---|
| ARKADE AURA | ARKADE DEVELOPERS PRIVATE LIMITED | Completed |
| ARKADE CROWN | Arkade Developers Private Limited | Completed |
| ARKADE EARTH - EBONY | Arkade Developers Private Limited | Completed |
| ARKADE EARTH - FERN | Arkade Developers Private Limited | Completed |
| ARKADE EARTH - GARDENIA | Arkade Developers Private Limited | Completed |
| ARKADE EARTH - HAZEL | Arkade Developers Private Limited | Completed |
| ARKADE EARTH- BLUEBELL | Arkade Developers Private Limited | Registration lapsed |
| ARKADE EARTH-ASPEN | Arkade Developers Private Limited | Registration lapsed |
| ARKADE EARTH-CARNATION | Arkade Developers Private Limited | Registration lapsed |
| ARKADE EARTH-DAFFODIL | Arkade Developers Private Limited | Completed |
| Arkade Aspire | Arkade Developers Private Limited | Completed |
| Arkade Serene | Arkade Developers Private Limited | Completed |
| DARSHAN | Arkade Developers Private Limited | Completed |
| Arkade Prime | M/s. Arkade Developers Pvt Ltd. | Completed |
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| ARKADE EARTH-DAFFODIL P51800004440 | 31 Dec 2022 | 20 Feb 2020 | On time |
| ARKADE EARTH - EBONY P51800008953 | 31 Dec 2022 | 20 Feb 2020 | On time |
| ARKADE EARTH - FERN P51800004750 | 31 Dec 2022 | 20 Feb 2020 | On time |
| ARKADE EARTH - GARDENIA P51800010074 | 31 Dec 2022 | 20 Feb 2020 | On time |
| ARKADE EARTH - HAZEL P51800022666 | 31 Dec 2022 | 4 Apr 2022 | On time |
| Darshan | 30 Jun 2023 | 7 Nov 2022 | On time |
| DARSHAN P51800027271 | 30 Jun 2023 | 7 Nov 2022 | On time |
| ARKADE EARTH-ASPEN P51800006579 | 31 Dec 2023 | 12 Apr 2021 | On time |
| ARKADE EARTH- BLUEBELL P51800011586 | 31 Dec 2023 | 12 Apr 2021 | On time |
| ARKADE EARTH-CARNATION P51800014422 | 31 Dec 2023 | 12 Apr 2021 | On time |
| Arkade Serene P51800029961 | 30 Jun 2024 | 8 Feb 2023 | On time |
| Arkade Aspire | 31 Dec 2025 | 31 Jul 2024 | On time |
Frequently asked questions
How do I verify Arkade Developers Ltd as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45200MH1986PLC039813 and GSTIN 27AAACA3578Q1Z4 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Arkade Developers Ltd?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make Arkade Developers Ltd unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.