ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / YASH PARISAR

Valid until 31 May 2022 Residential/Group Housing project

YASH PARISAR

By Riddhi Developer

RG-GJ-51289 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02539/EX1/200921 · Last updated on GujRERA portal: 31 May 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • Separate project account declared
May 2022Possession promisedmoved 11 months from the original
24 of 24Construction stages doneacross 3 buildings; every applicable stage filed complete
3 of 80Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

YASH PARISAR is a Residential/Group Housing project by Riddhi Developer in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02539/EX1/200921 on 3 May 2018. Possession is promised by 31 May 2022. The completion date has moved by 11 months from the original filing. 77 of the 80 units on this registration are recorded sold or booked, and 24 of 24 construction stages are filed complete.

At a glance

Project

  • NameYASH PARISAR
  • TypeResidential/Group Housing
  • Location
    • Survey No. 408
    • OP No.11
    • FP No.11
    • TPS No. 18
    • Kudasan
    • Gandhinagar
    • Kudasan
    • Gandhinagar
    • 382421
  • Pincode382421
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02539/EX1/200921
  • ReraGenie IDRG-GJ-51289

Builder

  • NameRiddhi Developer
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2018First promiseJun 2021Revised toMay 2022

Key facts

Registration and timeline

  • StatusValid until 31 May 2022
  • Registered on3 May 2018
  • Promised completion31 May 2022
  • Revised completionRevised to 31 May 2022 (originally 30 Jun 2021)
  • Buildings3 building records
  • Documents filed40 files

Current status

96%77 of 80 units booked
100.0%Of the estimated cost spent so far

Figures as on 31 May 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---26026
BLOCK B---26026
BLOCK C---28028

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 31 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 24 construction stages are filed complete across 3 buildings.

BLOCK A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 31 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,788 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 16.01 cr
Cost incurredRs 16.01 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
BLOCK ANARs 5.34 crRs 5.34 cr
BLOCK BNARs 5.34 crRs 5.34 cr
BLOCK CNARs 5.34 crRs 5.34 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPragna Machhar
EngineerVasant Soni

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02539/EX1/200921Applied Jun 2021; approved Sep 2021

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02539/EX1/200921 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)31 May 2022
Architect's certificate (Form 1)28 May 2022
Engineer's certificate (Form 2)28 May 2022
Engineer's certificate annexure28 May 2022
Site photograph, BLOCK A28 May 2022
Site photograph, BLOCK B28 May 2022
Site photograph, BLOCK C28 May 2022
RERA registration certificate3 May 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

96%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 11 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep YASH PARISAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kudasan1,600+ in Gandhinagar

2 kmYASH PARISAROther 277Dot size: filed unitsN

Filed coordinates, straight-line distance. 277 registered projects within 2 km.

Builder: Riddhi Developer

Riddhi Developer has 1 registration on GujRERA, including YASH PARISAR. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if YASH PARISAR is delayed beyond 31 May 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of YASH PARISAR?

The registered promoter entity is Riddhi Developer, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in YASH PARISAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at YASH PARISAR?

The professionals named in the filing: Architect: Pragna Machhar; Engineer: Vasant Soni. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in YASH PARISAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About YASH PARISAR. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save YASH PARISAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.