ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Rural, Karnataka / WHITESTONE TWINKLES

Registration approved No litigation declared Residential/Group Housing project

WHITESTONE TWINKLES

By WHITESTONE PROJECTS

RG-KA-11858 · RERA PRM/KA/RERA/1250/304/PR/020926/008901 · Last updated on RERA Karnataka portal: 29 Aug 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 115 documents Report an error

WHITESTONE TWINKLES is a Residential/Group Housing project by WHITESTONE PROJECTS in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/020926/008901 on 2 Sep 2026. Possession is promised by 31 Dec 2029.

At a glance

Project

  • NameWHITESTONE TWINKLES
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
    • 560049
  • Pincode560049
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/304/PR/020926/008901
  • ReraGenie IDRG-KA-11858

Builder

  • NameWHITESTONE PROJECTS
  • Entity typePartnership Firm
  • GSTIN29AABFW1285C1Z8
  • Authorized SignatorySATISH BOGOLLU
  • Other registrations3 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredSep 2026PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on2 Sep 2026
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed115 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WHITESTONE TWINKLES---74074

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 29 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 29 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesYes-
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,070 sq m
Named landowners1
LandownerVillageDistrict
JAYAKUMAR.H.M--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 22.05 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 20.98 cr-
Administrative CostsRs 72.00 lakh-
On-site expenditure-Consultants FeesRs 35.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectB V NARENDRANATH REDDY
EngineerM V V SATYANARAYANA MURTHY
Chartered AccountantCHITTRA GIRI PRASAD

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed115

As listed on the registration, under the names the promoter filed them with; the newest 80 of 115 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/020926/008901 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
clarification for annual auditFile: clarification for annual audit.pdf29 Aug 2026
and 70 accounts detailsFile: 100 and 70 accounts detaisl.pdf29 Aug 2026
clarification Affidavit of loan detailsFile: Affidavit for sale and operation.pdf29 Aug 2026
ICAI cert self attesedFile: ICAI cert self attesed.pdf29 Aug 2026
ITR balance sheet - p and l 2023-24File: ITR balance sheet - p and l 2023-24.pdf29 Aug 2026
ITR balance sheet and P and L 22-23File: ITR balance sheet and P and L 22-23.pdf29 Aug 2026
ITR-balance sheetand profir and loss account 2024-25File: ITR-balance sheetand profir and loss account 2024-25.pdf29 Aug 2026
source of fund whitestoneFile: Source of Fund.pdf29 Aug 2026
account detailsFile: 30 account details.pdf29 Aug 2026
Form Reg-1-Chartered Accountant CertificateFile: Form Reg-1-Chartered Accountant Certificate.pdf29 Aug 2026
Sale Deed TwinkleFile: Sale Deed Twinkle.pdf29 Aug 2026
Form-B affidavit whitestoneFile: Form-B affidavit whitestone.pdf29 Aug 2026
SINGLE LAYOUT PLANFile: SINGLE LAYOUT PLAN 1.pdf29 Aug 2026
Single site plan order copyFile: Single site plan order copy.pdf29 Aug 2026
CCFile: cc.pdf29 Aug 2026
ADLR sketchFile: ADLR sketch.pdf29 Aug 2026
SECTIONAL BUILDING PLANTWINKLESFile: SECTIONAL BUILDING PLANTWINKLES.pdf29 Aug 2026
KSPCB NOC clarificationFile: KSPCB NOC clarification.pdf29 Aug 2026
clarification of noc under KTCP actFile: clarification of noc under KTCP act.pdf29 Aug 2026
Project Amenities DetailsFile: Project Amenities Details.pdf29 Aug 2026
Brochures Clarification White stoneFile: Brochures Clarification White stone.pdf29 Aug 2026
project common area detailsFile: project common area details.pdf29 Aug 2026
AAI NOCFile: AAI NOC.pdf29 Aug 2026
BESCOM NOCFile: BESCOM NOC.pdf29 Aug 2026
BSNL NOCFile: BSNL NOC.pdf29 Aug 2026
Fire NOCFile: Fire NOC.pdf29 Aug 2026
PCB NOCFile: PCB NOC.pdf29 Aug 2026
WATER NOCFile: WATER NOC.pdf29 Aug 2026
SpecificationFile: Specification.pdf29 Aug 2026
FIRE NOC Affidavit cum DeclarationFile: FIRE NOC Affidavit cum Declaration.pdf29 Aug 2026
Location details of the ProjectFile: Location details of the Project.pdf29 Aug 2026
STRUCTURAL STABILITY CERTIFICATEFile: STRUCTURAL STABILITY CERTIFICATE.pdf29 Aug 2026
AOS as per RERAFile: AOS as per RERA.pdf29 Aug 2026
Allotment LetterFile: Allotment Letter whitestone.pdf29 Aug 2026
Section 3-1 affidavitFile: Section 3-1 affidavit whitestone.pdf29 Aug 2026
FIRE NOC Affidavit cum DeclarationFile: FIRE NOC Affidavit cum Declaration.pdf29 Aug 2026
Estimation CertFile: Estimation.pdf29 Aug 2026
STP NEWFile: STP NEW.pdf29 Aug 2026
Land cost details with Guidance value certFile: Land cost details with Guidance value cert.pdf29 Aug 2026
Clarification of Main source of water whitestoneFile: Clarification of Main source of water whitestone.pdf29 Aug 2026
AAI NOCFile: AAI NOC.pdf29 Aug 2026
BESCOM NOCFile: BESCOM NOC.pdf29 Aug 2026
BSNL NOCFile: BSNL NOC.pdf29 Aug 2026
Fire NOCFile: Fire NOC.pdf29 Aug 2026
FIRE NOC Affidavit cum DeclarationFile: FIRE NOC Affidavit cum Declaration.pdf29 Aug 2026
PCB NOCFile: PCB NOC.pdf29 Aug 2026
WATER NOCFile: WATER NOC.pdf29 Aug 2026
CDP MAPFile: CDP MAPTWINKLES.pdf29 Aug 2026
village MapFile: village Map.pdf29 Aug 2026
clarification of loan detailsFile: clarification of loan details.pdf29 Aug 2026
EC till dateFile: EC till date.pdf29 Aug 2026
Legal OpinionFile: Legal Opinion.pdf29 Aug 2026
Eng Licence with self atttestedFile: Eng Licence with self atttested.pdf29 Aug 2026
STRUCTURAL STABILITY CERTIFICATEFile: STRUCTURAL STABILITY CERTIFICATE revised.pdf29 Aug 2026
STPFile: STP revised.pdf29 Aug 2026
RTC, survey 45/3-
Mutation, survey 45/3-
Encumbrance Certificate, survey 45/3-
Conversion/Alienation Order, survey 45/3-
Sale/Title/Gift Deed, survey 45/3-
JDA, survey 45/3-
Khatha, survey 45/3-
Registration CertificateFile: FIRM REGISTRATION CERTIFICATE (1).pdf-
GST CertificateFile: WSP-GST Registration-new.pdf-
Partnership DeedFile: PARTNERSHIP DEED.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form Reg-1-Chartered Accountant Certificate.pdf-
Certificate issued by Architect Form 2File: ARCHITECT’S CERTIFICATE - Twinkles.pdf-
Certificate issued by Engineer Form 3File: Form -6 Eng Cert.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit (Non-Litigation).pdf-
Balance Sheet 2024 - 2025File: Whitestone-Financials(AY 2025-26) (1)-TWINKLES NEW.pdf-
Balance Sheet 2023 - 2024File: Whitestone-Financials(AY 2024-25).pdf-
Balance Sheet 2022 - 2023File: Whitestone-Financials(AY 2023-24).pdf-
Audited Profit and Loss Statement 2024 - 2025File: Whitestone-Financials(AY 2025-26) (1)-TWINKLES NEW.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Whitestone-Financials(AY 2024-25).pdf-
Audited Profit and Loss Statement 2022 - 2023File: Whitestone-Financials(AY 2023-24).pdf-

How this compares with Bengaluru Rural

20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep WHITESTONE TWINKLES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmWHITESTONE TWINKLESOther 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 21 registered projects within 2 km.

Builder: WHITESTONE PROJECTS

WHITESTONE PROJECTS has 4 registrations on RERA Karnataka, including WHITESTONE TWINKLES and WHITESTONE MILANO. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if WHITESTONE TWINKLES is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of WHITESTONE TWINKLES?

The registered promoter entity is WHITESTONE PROJECTS, a partnership firm as per the filing. Its GSTIN 29AABFW1285C1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in WHITESTONE TWINKLES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at WHITESTONE TWINKLES?

The professionals named in the filing: Architect: B V NARENDRANATH REDDY; Engineer: M V V SATYANARAYANA MURTHY; Chartered Accountant: CHITTRA GIRI PRASAD. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in WHITESTONE TWINKLES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About WHITESTONE TWINKLES. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save WHITESTONE TWINKLES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.