Home / Browse projects / Bengaluru Urban, Karnataka / Sattva Songbird

Registration approved No litigation declared Residential/Group Housing project

Sattva Songbird

By Sattva Resi Private Limited

RG-KA-03728 · RERA PRM/KA/RERA/1251/446/PR/060924/007008 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
May 2029Possession promisedno revision filed
2 of 18Construction stages donefurthest along: Upto Plinth Level, 93%
675 of 1,379Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 175 documents Report an error

Sattva Songbird is a Residential/Group Housing project by Sattva Resi Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/060924/007008 on 6 Sep 2024. Possession is promised by 6 May 2029. 704 of the 1,379 units on this registration are recorded sold or booked, and 2 of 18 construction stages are filed complete.

At a glance

Project

  • NameSattva Songbird
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560049
  • Pincode560049
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/060924/007008
  • ReraGenie IDRG-KA-03728

Builder

  • NameSattva Resi Private Limited
  • Entity typeCompany
  • CINU45309KA2022PTC160813
  • GSTIN29ABICS4269F1ZX
  • Authorized SignatoryMr.P.K.Mishra
  • CeoMr.P.K.Mishra
  • DirectorsShivam Agarwal, P.K.Mishra
  • Project HeadPrakash S
  • Other registrations11 more →
  • Declared earlier projects17 →

Key dates

this monthRegisteredSep 2024PromisedMay 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on6 Sep 2024
  • Promised completion6 May 2029
  • Revised completionNone
  • Buildings5 building records
  • Documents filed175 files

Current status

51%704 of 1,379 units booked
6.3%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1---4710471
Tower 2---4830483
Tower 3---1890189
Tower 4---1780178
Row Houses---58058

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 18 construction stages are filed complete. The stage furthest along is Upto Plinth Level, at 93%.

Building: 41% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level93%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)80%
Retaining wall (All types)90%
RCC or MS Framed structure45%
Masonry Construction45%
Plastering inside , outside & Ceiling36%
Joinery: Doors, Windows, Ventilators etc13%
Basic work of Water supply, Sanitary and Electrification45%
Dadoing, Skirting, Flooring, Tiles work (All types)8%
Railing and Grill fixing24%
Electrification, Water supply and Sanitary Finishing0%
Painting3%
Fire prevention and fire fighting fitting and fixture with network18%
Weather Proof work(tile,concrete)16%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings23%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes22%
Sewage and Drainage SystemYes50%
Water conservation/rain water harvesting/recharge of ground waterYes33%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes18%
Solid waste management and disposalYes50%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes55%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes13%
Parks & Tree plantingYes10%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes30%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes33%
GymNoNot applicable
ParksYes10%
Power BackupNoNot applicable
Piped GasYes0%
Water and SanitationYes22%
Air ConditioningNoNot applicable
StaircasesYes50%
LiftsYes0%
Corridor/LobbiesYes50%
Fire escapesYes40%
Common entrance and exit for the building/common portico/foyer/verandahYes50%
BasementYes46%
TerraceYes0%
Outer WallYes45%
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area48,460 sq m
Named landowners3
LandownerVillageDistrict
DARSHITA BUILD-TECH PRIVATE LIMITED--
DARSHITA BUILD-TECH PRIVATE LIMITED--
DARSHITA BUILD-TECH PRIVATE LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 602.46 cr
Cost incurredRs 38.09 cr
Spent of the estimate6.32%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 584.34 crRs 35.99 cr
On-site expenditure-Site OverheadRs 18.12 crRs 2.10 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV Narasimhan
EngineerBELLAD DINESH KUMAR
Chartered AccountantM O J & ASSOCIATES

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed175

As listed on the registration, under the names the promoter filed them with; the newest 80 of 175 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/060924/007008 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA Certificate Song bird.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 - Songbird.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 - Songbird 1.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Labour and Education Department15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Song Bird Q1 form 4.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Sattva Songbird Form 5 POC.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Sattva Songbird Form 6 POC.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Labour and Education Department15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Sattva Song Bird Q4 FY 25-26.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 - Songbird - POC.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Songbird -POC.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Q4 2025-26 Fire and Safety14 Apr 2026
Q4 2025-26 Labour and Education Department14 Apr 2026
Q4 2025-26 Airport Authority of India14 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Sattva Song Bird Q3 FY 25-26.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Song Bird Form 5.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Song Bird - Form 6 Engg.pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Q3 2025-26 Fire and Safety14 Jan 2026
Q3 2025-26 Labour and Education Department14 Jan 2026
Q3 2025-26 Airport Authority of India14 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department14 Jan 2026
SHEET NO 1 OF 14 SITEPLANFile: 1 SHEET NO 1 OF 14 SITEPLAN.pdf20 Aug 2024
SHEET NO 02 OF 14 LOWER BASEMENT PLANFile: 2 SHEET NO 02 OF 14 LOWER BASEMENT PLAN.pdf20 Aug 2024
SHEET NO 03 OF 14 UPPER BASEMENT FLOOR PLANFile: 3 SHEET NO 03 OF 14 UPPER BASEMENT FLOOR PLAN.pdf20 Aug 2024
SHEET NO 04 OF 14 GROUND FLOOR PLANFile: 4 SHEET NO 04 OF 14 GROUND FLOOR PLAN.pdf20 Aug 2024
SHEET NO 05 OF 14 TOWER 1&2 FIRST FLOOR(2ND TO18TH)(20TH TO 27 &29TH )File: 5 SHEET NO 05 OF 14 TOWER 1&2 FIRST FLOOR(2ND TO18TH)(20TH TO 27 &29TH ).pdf20 Aug 2024
SHEET NO 06 OF 14 TOWER 1&2 TYPICAL 19TH&29TH&30TH FLOOR PLANFile: 6 SHEET NO 06 OF 14 TOWER 1&2 TYPICAL 19TH&29TH&30TH FLOOR PLAN.pdf20 Aug 2024
SHEET NO 07 OF 14 TOWER 1&2 TERRACE &AMENITY 2 FLOOR PLANS,ROW HOUSE,SECTION,ELEVATIONFile: 7 SHEET NO 07 OF 14 TOWER 1&2 TERRACE &AMENITY 2 FLOOR PLANS,ROW HOUSE,SECTION,ELEVATION.p20 Aug 2024
SHEET NO 08 OF 14 TOWER 1 & 2 ELEVATIONFile: 8 SHEET NO 08 OF 14 TOWER 1 & 2 ELEVATION.pdf20 Aug 2024
SHEET NO 09 OF 14 TOWER 1&2 SECTIONFile: 9 SHEET NO 09 OF 14 TOWER 1&2 SECTION.pdf20 Aug 2024
SHEET NO 10 OF 14 TOWER 3&4 FIRST FLOOR(2ND TO 18TH)(20TH TO 27TH) AND 19TH AND28TH FLOOR PLANSFile: 10 SHEET NO 10 OF 14 TOWER 3&4 FIRST FLOOR(2ND TO 18TH)(20TH TO 27TH) AND 19TH AND28TH FLO20 Aug 2024
SHEET NO 11 OF 14 TOWER 1&2 30TH&31ST&TERRACE FLOOR PLANFile: 11 SHEET NO 11 OF 14 TOWER 1&2 30TH&31ST&TERRACE FLOOR PLAN.pdf20 Aug 2024
SHEET NO 12 OF 14 TOWER 3&4 ELEVATION PLANFile: 12 SHEET NO 12 OF 14 TOWER 3&4 ELEVATION PLAN.pdf20 Aug 2024
SHEET NO 13 OF 14 TOWER 3&4 SECTION PLANFile: 13 SHEET NO 13 OF 14 TOWER 3&4 SECTION PLAN.pdf20 Aug 2024
SHEET NO 14 OF 14 AMENITY 01 FLOOR PLANS&SECTION&ELEVATIONFile: 14 SHEET NO 14 OF 14 AMENITY 01 FLOOR PLANS&SECTION&ELEVATION.pdf20 Aug 2024
Clarification on Building License from local authorityFile: 15 Clarification on Building License from local authority.pdf20 Aug 2024
Form-2 Architect CertificateFile: 16 Form-2 Architect Certificate.pdf20 Aug 2024
Architect LicenseFile: 17 Architect License.pdf20 Aug 2024
KSPCB NOC Declaration and Fee paid receiptFile: 18 KSPCB NOC Declaration and Fee paid receipt.pdf20 Aug 2024
RTC Sy No 16-1File: 19 RTC Sy No 16-1.pdf20 Aug 2024
RTC Sy No 16-2File: 20 RTC Sy No 16-2.pdf20 Aug 2024
RTC Sy No 89File: 21 RTC Sy No 89.pdf20 Aug 2024
Mother Conversion OrderFile: 22 Mother Conversion Order.pdf20 Aug 2024
Self-attested Songbird-E-khathaFile: 23 Self-attested Songbird-E-khatha.pdf20 Aug 2024
Building Plan LicenseFile: 24 Building Plan License.pdf20 Aug 2024
RTC, survey 16/1-
Mutation, survey 16/1-
Encumbrance Certificate, survey 16/1-
Conversion/Alienation Order, survey 16/1-
Sale/Title/Gift Deed, survey 16/1-
JDA, survey 16/1-
Khatha, survey 16/1-
RTC, survey 16/2-
Mutation, survey 16/2-
Encumbrance Certificate, survey 16/2-
Conversion/Alienation Order, survey 16/2-
Sale/Title/Gift Deed, survey 16/2-

How this compares with Bengaluru Urban

51%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Sattva Songbird on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSattva SongbirdOther 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 36 registered projects within 2 km.

Builder: Sattva Resi Private Limited

Sattva Resi Private Limited has 12 registrations on RERA Karnataka, including Sattva Vasanta Cove and Sattva Vasanta Skye. Its filings declare 17 earlier projects, 4 of them declared completed. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Sattva Songbird is delayed beyond 6 May 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Sattva Songbird?

The registered promoter entity is Sattva Resi Private Limited, a company as per the filing. Its CIN U45309KA2022PTC160813 and GSTIN 29ABICS4269F1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Sattva Songbird?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Sattva Songbird?

The professionals named in the filing: Architect: V Narasimhan; Engineer: BELLAD DINESH KUMAR; Chartered Accountant: M O J & ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sattva Songbird?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sattva Songbird. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sattva Songbird to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.