Home / Browse projects / Gandhinagar, Gujarat / VRUNDAVAN ANANTAM

Valid until 30 Apr 2027 Residential/Group Housing project

VRUNDAVAN ANANTAM

By SHREE RADHE ENTERPRISE

RG-GJ-09754 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA13142/160324/311226 · Last updated on GujRERA portal: 8 Oct 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
22 of 36Construction stages doneacross 4 buildings; furthest along: External plumbing and external plaster, 95%
3 of 11Units unsoldnot recorded sold or booked
Jump to the 33 documents Report an error

VRUNDAVAN ANANTAM is a Residential/Group Housing project by SHREE RADHE ENTERPRISE in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA13142/160324/311226 on 16 Mar 2024. Possession is promised by 30 Apr 2027. 8 of the 11 units on this registration are recorded sold or booked, and 22 of 36 construction stages are filed complete.

At a glance

Project

  • NameVRUNDAVAN ANANTAM
  • TypeResidential/Group Housing
  • Location
    • Raysan
    • Gandhinagar
    • Raysan
    • Gandhinagar
    • 382421
  • Pincode382421
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA13142/160324/311226
  • ReraGenie IDRG-GJ-09754

Builder

  • NameSHREE RADHE ENTERPRISE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMar 2024PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on16 Mar 2024
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings4 building records
  • Documents filed33 files

Current status

73%8 of 11 units booked
139.7%Of the estimated cost spent so far

Figures as on 8 Oct 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B---202
A---303
D---303
C---303

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 8 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

B88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
A88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
D89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats35%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
C89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats35%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%

Progress on shared amenities19

As on 8 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes80%
Water supplyYes30%
Sewerage (chamber, lines, septic tank, STP)Yes70%
Storm water drainsYes80%
Landscaping and tree plantingYes0%
Street lightingYes60%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes30%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,000 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 6.52 cr
Cost incurredRs 9.11 cr
Spent of the estimate139.66%
BuildingWingEstimatedIncurred
CNARs 1.80 crRs 2.51 cr
DNARs 1.80 crRs 2.51 cr
ANARs 1.75 crRs 2.44 cr
BNARs 1.17 crRs 1.63 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhaumikkumar Chandravadanbhai Donga
EngineerKALGI RAJESHKUMAR TRIVEDI

Documents filed33

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA13142/160324/311226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)8 Oct 2025
Architect's certificate (Form 1)7 Oct 2025
Engineer's certificate (Form 2)7 Oct 2025
Engineer's certificate annexure7 Oct 2025
Site photograph, B7 Oct 2025
Site photograph, A7 Oct 2025
Site photograph, D7 Oct 2025
Site photograph, C7 Oct 2025
RERA registration certificate16 Mar 2024
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

73%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep VRUNDAVAN ANANTAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Raysan1,600+ in Gandhinagar

2 kmVRUNDAVAN ANANTAMOther 141Dot size: filed unitsN

Filed coordinates, straight-line distance. 141 registered projects within 2 km.

Builder: SHREE RADHE ENTERPRISE

SHREE RADHE ENTERPRISE has 1 registration on GujRERA, including VRUNDAVAN ANANTAM. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if VRUNDAVAN ANANTAM is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of VRUNDAVAN ANANTAM?

The registered promoter entity is SHREE RADHE ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in VRUNDAVAN ANANTAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VRUNDAVAN ANANTAM?

The professionals named in the filing: Architect: Bhaumikkumar Chandravadanbhai Donga; Engineer: KALGI RAJESHKUMAR TRIVEDI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VRUNDAVAN ANANTAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VRUNDAVAN ANANTAM. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VRUNDAVAN ANANTAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.