ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Vista Svara

Registration approved No litigation declared Residential/Group Housing project

Vista Svara

By Vista Spaces Sun (Lalbagh) Private Limited

RG-KA-00329 · RERA PRM/KA/RERA/1251/310/PR/130722/005068 · Last updated on RERA Karnataka portal: 10 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Oct 2026Possession promisedno revision filed
5 of 18Construction stages donefurthest along: Masonry construction: Bricks, 99%
20 of 36Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 148 documents Report an error

Vista Svara is a Residential/Group Housing project by Vista Spaces Sun (Lalbagh) Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/130722/005068 on 13 Jul 2022. Possession is promised by 30 Oct 2026. 16 of the 36 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete.

At a glance

Project

  • NameVista Svara
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560027
  • Pincode560027
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/130722/005068
  • ReraGenie IDRG-KA-00329

Builder

  • NameVista Spaces Sun (Lalbagh) Private Limited
  • Entity typeCompany
  • CINU45500KA2018PTC111585
  • GSTIN29AAGCV3499P1Z7
  • Authorized SignatoryRaghuveer Veeramachaneni
  • ExecutiveRaghuveer Veeramachaneni
  • DirectorsRaghuveer Veeramachaneni, Praveen Kumar
  • Project HeadABHINAY G B

Key dates

this monthRegisteredJul 2022PromisedOct 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 Jul 2022
  • Promised completion30 Oct 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed148 files

Current status

44%16 of 36 units booked
3.9%Of the estimated cost spent so far

Figures as on 10 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1---32032

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 10 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 18 construction stages are filed complete. The stage furthest along is Masonry construction: Bricks, at 99%.

Building: 76% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)Not applicable
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc99%
Plastering inside , outside & Ceiling95%
Joinery: Doors, Windows, Ventilators etc60%
Basic work of Water supply, Sanitary and Electrification55%
Dadoing, Skirting, Flooring, Tiles work (All types)90%
Railing and Grill fixing95%
Electrification, Water supply and Sanitary Finishing55%
Wardrobe, Showcase, Kitchen cabinet, Puja work0%
Fire prevention and fire fighting fitting and fixture with network65%
Weather Proof work(tile,concrete)90%
Painting30%
Elevation work70%
Internal and External work including landscapes as per santioned drawings65%

Progress on shared amenities41

As on 10 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Internal Roads & FootpathsYes5%
Sewage and Drainage SystemYes20%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservationYes15%
Energy managementYes0%
Fire protection and fire safety requirementsYes50%
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes15%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes0%
ParksNoNot applicable
Power BackupYes0%
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes85%
LiftsYes80%
Staircases and Lift lobbies, corridor,lobbies, corridorYes80%
Fire escapesYes0%
Common entrance and exit for the building / common portico/foyer/verandahYes20%
BasementNoNot applicable
TerraceYes80%
Outer WallYes97%
Open parking areas and common storage spacesYes12%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes12%

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,930 sq m
Named landowners3
LandownerVillageDistrict
Mr.B Nirgunarthy--
Dr.B Sagunarthy--
Mr.B Shivarathy--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 27.44 cr
Cost incurredRs 1.07 cr
Spent of the estimate3.9%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 27.44 crRs 1.05 cr
On-site expenditure-Site Overhead-Rs 1.59 lakh
Payment of taxes-Rs 17,700
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)-Rs 562

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVenkataramanan Associates
EngineerM S NAGENDRA PRASAD
Chartered AccountantVINAY THYAGARAJ

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed148

As listed on the registration, under the names the promoter filed them with; the newest 80 of 148 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/130722/005068 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - CA Certificate.pdf10 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect certificate.pdf10 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf10 Oct 2026
Q2 2026-27 Water supply and sewage board10 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)10 Oct 2026
Q2 2026-27 KPTCL- BESCOM10 Oct 2026
Q2 2026-27 Fire and Safety10 Oct 2026
Q2 2026-27 Airport Authority of India10 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department10 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4-CA certificate June 26.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect certificate (1).pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate (2).pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate March 26.pdf20 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect certificate.pdf20 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf20 Apr 2026
Q4 2025-26 Water supply and sewage board20 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)20 Apr 2026
Q4 2025-26 KPTCL- BESCOM20 Apr 2026
Q4 2025-26 Fire and Safety20 Apr 2026
Q4 2025-26 Airport Authority of India20 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department20 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - Vista Svara -Dec 2025.pdf19 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect certificate.pdf19 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf19 Jan 2026
Q3 2025-26 Water supply and sewage board19 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)19 Jan 2026
Q3 2025-26 KPTCL- BESCOM19 Jan 2026
Q3 2025-26 Fire and Safety19 Jan 2026
Q3 2025-26 Airport Authority of India19 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department19 Jan 2026
No Litigation AffidavitFile: Affidavit for Non-Litigation Details_Signed.pdf29 Jun 2022
GPAFile: GPA OF LALBAGH PROJECT.pdf29 Jun 2022
INDEX OF LANDFile: Annx 2 Index of Lands.pdf13 Jun 2022
Declaration of non-availability of MR and RTCFile: Annx 3 Declaration Conversion Letter MR and RTC.pdf13 Jun 2022
SPA from NirgunarathyFile: Annx 4 SPA from B Nirgunarthy.pdf13 Jun 2022
SPA from SugunarathyFile: Annx 4 SPA from Sagunarthy.pdf13 Jun 2022
Joint AffidavitFile: Joint Affidavit - Promoter and Landowner - Company - Apartment.pdf13 Jun 2022
EXTRACT OF MASTER PLANFile: Annx 6 RMP site Chamrajpet.pdf13 Jun 2022
LOCATION AND DEMARCATION PLANFile: Annx 7 lalbagh Location map.pdf13 Jun 2022
Bescom NOCFile: Annx 8 Bescom NOC.pdf13 Jun 2022
Bwwsb NOCFile: Annx 9 BWSSB NOC.pdf13 Jun 2022
Bwwsb receiptFile: Annx 9 BWSSB receipts.pdf13 Jun 2022
Site PlanFile: Lalbagh Site Plan.pdf13 Jun 2022
building plan 1File: Lalbagh Building Plan 1.pdf13 Jun 2022
Building Plan 2File: Lalbagh Building Plan 2.pdf13 Jun 2022
Proforma Agreement for SaleFile: PROFORMA AGREEMENT FOR SALE.pdf13 Jun 2022
Registration CertificateFile: Lalbagh CIN.PDF-
Organization StructureFile: Lalbagh Organizational Structure.pdf-
Certificate issued by CA Form 1File: CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form 5 Architect certificate.pdf-
Certificate issued by Engineer Form 3File: Engineering Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit No Litigation.pdf-
Certificate from Chartered AccountFile: CA Certificate.pdf-
Balance Sheet 2020 - 2021File: BS FY 20 21.pdf-
Balance Sheet 2019 - 2020File: BS 2019 20.pdf-
Balance Sheet 2018 - 2019File: BS 2018 19.pdf-
Audited Profit and Loss Statement 2020 - 2021File: P L FY 20 21.pdf-
Audited Profit and Loss Statement 2019 - 2020File: P L 2019 20.pdf-
Audited Profit and Loss Statement 2018 - 2019File: P L 2018 19.pdf-
Director's Report 2020 - 2021File: Directors Report 20 21.pdf-
Director's Report 2019 - 2020File: Directors Report 2019 20.pdf-
Director's Report 2018 - 2019File: Directors Report 2018 19.pdf-
Cash Flow Statement 2020 - 2021File: CFS FY 20 21.pdf-
Cash Flow Statement 2019 - 2020File: C F 2019 20.pdf-
Auditor's Report 2020 - 2021File: Audit Report FY20 21.pdf-
Auditor's Report 2019 - 2020File: Audit Report FY 2019 20.pdf-
Auditor's Report 2018 - 2019File: Audit Report 2018 19.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR 2020 21.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR Ack 2019 20.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR FY2018 19.pdf-
Approval Letter-

How this compares with Bengaluru Urban

44%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Vista Svara on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmVista SvaraOther 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 15 registered projects within 2 km.

Builder: Vista Spaces Sun (Lalbagh) Private Limited

Vista Spaces Sun (Lalbagh) Private Limited has 1 registration on RERA Karnataka, including Vista Svara. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Vista Svara is delayed beyond 30 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Vista Svara?

The registered promoter entity is Vista Spaces Sun (Lalbagh) Private Limited, a company as per the filing. Its CIN U45500KA2018PTC111585 and GSTIN 29AAGCV3499P1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Vista Svara?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Vista Svara?

The professionals named in the filing: Architect: Venkataramanan Associates; Engineer: M S NAGENDRA PRASAD; Chartered Accountant: VINAY THYAGARAJ. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vista Svara?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vista Svara. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vista Svara to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.