Home / Browse projects / Bengaluru Urban, Karnataka / VIKYATH SIGNATURE

Registration approved No litigation declared Residential/Group Housing project

VIKYATH SIGNATURE

By VIKYATH PROPERTIES PVT LTD

RG-KA-42258 · RERA PRM/KA/RERA/1251/446/PR/060324/006674 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2030Possession promisedno revision filed
7 of 18Construction stages donefurthest along: Plastering inside, 90%
189 of 315Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 180 documents Report an error

VIKYATH SIGNATURE is a Residential/Group Housing project by VIKYATH PROPERTIES PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/060324/006674 on 6 Mar 2024. Possession is promised by 31 Dec 2030. 126 of the 315 units on this registration are recorded sold or booked, and 7 of 18 construction stages are filed complete.

At a glance

Project

  • NameVIKYATH SIGNATURE
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560049
  • Pincode560049
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/060324/006674
  • ReraGenie IDRG-KA-42258

Builder

  • NameVIKYATH PROPERTIES PVT LTD
  • Entity typeCompany
  • CINU70109KA2020PTC140050
  • GSTIN29AAHCV6810H1Z2
  • Authorized SignatoryDODLA SRIKANTH
  • Managing DirectorDODLA SRIKANTH
  • DirectorsREKHA VULUVA, V KIRAN KUMAR, NALLABOTHU DHAMODHAR, DODLA SRIKANTH
  • Project HeadDODLA SRIKANTH
  • Other registrations1 more →

Key dates

this monthRegisteredMar 2024PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on6 Mar 2024
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings2 building records
  • Documents filed180 files

Current status

40%126 of 315 units booked
82.1%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER--A---1400140
TOWER-B---1750175

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 18 construction stages are filed complete. The stage furthest along is Plastering inside, at 90%.

Building: 60% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling90%
Joinery: Doors, Windows, Ventilators etc90%
Basic work of Water supply, Sanitary and Electrification75%
Dadoing, Skirting, Flooring, Tiles work (All types)65%
Railing and Grill fixing25%
Electrification, Water supply and Sanitary Finishing35%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes60%
Sewage and Drainage SystemYes50%
Water conservation/rain water harvesting/recharge of ground waterYes60%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes35%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes35%
Storm water drainsYes45%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes50%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes35%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes30%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes60%
Air ConditioningNoNot applicable
StaircasesYes85%
LiftsYes85%
Corridor/LobbiesYes85%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes100%
TerraceYes50%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes60%
Common storage spacesYes0%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,746 sq m
Named landowners2
LandownerVillageDistrict
VIKYATH PROPERTIES PRIVATE LIMITED--
Muddamma--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 91.70 cr
Cost incurredRs 75.29 cr
Spent of the estimate82.11%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 72.10 crRs 72.10 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 13.60 crRs 1.39 cr
Payment of taxesRs 2.50 crRs 2.08 lakh
On-site expenditure-Consultants FeesRs 1.10 crRs 78.27 lakh
On-site expenditure-Salaries of workersRs 1.00 crRs 1.00 cr
On-site expenditure-Site OverheadRs 90.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 20.00 lakh-
Payment of PremiumsRs 10.00 lakh-
Payment of feesRs 7.50 lakh-
Payment of chargesRs 7.50 lakh-
Payment of cessRs 5.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRUDHVI R
EngineerBALAJI K N
Chartered AccountantVenkataramana P

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed180

As listed on the registration, under the names the promoter filed them with; the newest 80 of 180 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/060324/006674 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: form 4 q2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 q2.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: VIKYATH SIGNATURE.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5, Architect.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Q4 2025-26 Fire and Safety14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 VIKYATH SIGNATURE -Q3 .pdf21 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5, Architect (Q3) 08JAN2026(DEC2025).pdf21 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Vikyath Signature - Form 6 Engineer's Certificate 08-01-2026.pdf21 Jan 2026
Q3 2025-26 Water supply and sewage board21 Jan 2026
Q3 2025-26 KPTCL- BESCOM21 Jan 2026
Q3 2025-26 Fire and Safety21 Jan 2026
profit and loss account and balance sheet, 2022-23 with CA UDINFile: 22-23 P&L Account and Balance Sheet schedules.pdf21 Feb 2024
sources of fundsFile: Source of Funds As per CA certificate.pdf21 Feb 2024
bank account affidavitFile: Bank Affidavit For Rera.pdf21 Feb 2024
conversion order issued by the deputy commissioner for sno 26/2File: 3 5 12 conversion oder.pdf21 Feb 2024
old tittle deed land owner of sno 26/2 (1)File: old tittle deed .pdf21 Feb 2024
old tittle deed land owner of sno 26/2 (2)File: 152-2008.pdf21 Feb 2024
old tittle deed land owner of sno 26/2 (3)File: 91-96-97.pdf21 Feb 2024
old tittle deed land owner of sno 26/2 (4)File: 2-2001-02.pdf21 Feb 2024
tittle deed of muddamma Sy No 26-2File: tittle deed of muddamma Sy No 26-2_compressed.pdf21 Feb 2024
Single plot layout.File: Single Layout plan Non availability.pdf21 Feb 2024
Single plot layout Order.File: Single Layout plan Non availability.pdf21 Feb 2024
relinquishment deed (Road widening area)File: Rera Notice Reply.pdf21 Feb 2024
KSPCB CFEFile: kspcb noc.pdf21 Feb 2024
Building LicenseFile: Rera Notice Reply.pdf21 Feb 2024
Rera Notice ReplyFile: Rera Notice Reply.pdf21 Feb 2024
Comply of Query letterFile: Comply of Query letter.pdf21 Feb 2024
B A D PLAN WORK ORDERFile: MS VIKYATH PROPERTIES PVT LTD KURUDUSONNENAHALLI VILLAGE WORK ORDER.pdf21 Feb 2024
Revised Project EstimationFile: Project Estimation.pdf21 Feb 2024
Vikyath signature form 1File: Vikyath signature form 1.pdf21 Feb 2024
Auditors report 2021File: auditors report 2021.pdf3 Feb 2024
20_21 balance sheet & profit and loss accountFile: 20_21 balance sheet & profit and loss account.pdf3 Feb 2024
Directors report 20_21File: directors report 20_21.pdf3 Feb 2024
Finacials and auditor report 21_22File: Finacials and auditor report 21_22.pdf3 Feb 2024
21_22 balance sheet & profit and loss accountFile: 21-22 balance sheet & profit and loss account.pdf3 Feb 2024
Audit report 21_22File: Audit report 21_22.pdf3 Feb 2024
BALANCESHEET 21_22File: BALANCESHEET 21_22.pdf3 Feb 2024
directors report 21_22File: directors report 21_22.pdf3 Feb 2024
ITR 21_22File: ITR 21_22.pdf3 Feb 2024
PROFIT and LOSS 21_22File: PROFIT and LOSS 21_22.pdf3 Feb 2024
Auditor report 22_23File: Auditor report 22_23.pdf3 Feb 2024
Balancesheet 22_23File: Balancesheet 22_23.pdf3 Feb 2024
Financials and Auditor report 22_23File: Financials and Auditor report 22_23.pdf3 Feb 2024
Financials of Pvt ltd 22_23File: Financials of Pvt ltd 22_23.pdf3 Feb 2024
Auditor report 22_23File: Auditor report 22_23.pdf3 Feb 2024
Balancesheet 22_23File: Balancesheet 22_23.pdf3 Feb 2024
Directors Report 22_23File: Directors Report 22_23.pdf3 Feb 2024
ITR 22_23File: ITR 22_23.pdf3 Feb 2024
Profit and loss 22_23File: Profit and loss 22_23.pdf3 Feb 2024
ElevationFile: Elevation.pdf3 Feb 2024
FLOOR PLANFile: FLOOR PLAN.pdf3 Feb 2024
Ground floor planFile: Ground floor plan.pdf3 Feb 2024
PLANFile: PLAN.pdf3 Feb 2024
Terrace floor planFile: Terrace floor plan.pdf3 Feb 2024
TYPICAL FLOOR PLANFile: TYPICAL FLOOR PLAN.pdf3 Feb 2024
26_1 ECFile: 26_1 EC.pdf3 Feb 2024
26_2 ECFile: 26_2 EC.pdf3 Feb 2024
26_2 23_24 RTC and MRFile: 26_2 23_24 RTC and MR.pdf3 Feb 2024
Amenities VikyathFile: Amenities Vikyath.pdf3 Feb 2024
BESCOM NOC and Payment ReceiptFile: BESCOM NOC and Payment Receipt.pdf3 Feb 2024
BWSSB NOCFile: BWSSB NOC.pdf3 Feb 2024
CARPET AREAFile: CARPET AREA.pdf3 Feb 2024
Estimation VikyathFile: Estimation Vikyath.pdf3 Feb 2024
FORM_1 CA CERTIFICATEFile: FORM_1 CA CERTIFICATE.pdf3 Feb 2024
katha extract copy Sy No 26_1File: katha extract copy Sy No 26_1.pdf3 Feb 2024
Katha extract copy Sy No 26_2File: Katha extract copy Sy No 26_2.pdf3 Feb 2024
KSPCB NOCFile: KSPCB NOC.pdf3 Feb 2024

How this compares with Bengaluru Urban

40%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep VIKYATH SIGNATURE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmVIKYATH SIGNATUREOther 54Dot size: filed unitsN

Filed coordinates, straight-line distance. 54 registered projects within 2 km.

Builder: VIKYATH PROPERTIES PVT LTD

VIKYATH PROPERTIES PVT LTD has 2 registrations on RERA Karnataka, including VIKYATH SIGNATURE and VIKYATH ELEGANT. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if VIKYATH SIGNATURE is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of VIKYATH SIGNATURE?

The registered promoter entity is VIKYATH PROPERTIES PVT LTD, a company as per the filing. Its CIN U70109KA2020PTC140050 and GSTIN 29AAHCV6810H1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in VIKYATH SIGNATURE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VIKYATH SIGNATURE?

The professionals named in the filing: Architect: PRUDHVI R; Engineer: BALAJI K N; Chartered Accountant: Venkataramana P. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIKYATH SIGNATURE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIKYATH SIGNATURE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIKYATH SIGNATURE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.