Red flags

  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Mar 2020Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 56 documents Report an error

Venugram Vajra is a Residential/Group Housing project by Venugram Infraventures Pvt Ltd in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/180313/002394 on 13 Mar 2018. Possession is promised by 30 Mar 2020. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameVenugram Vajra
  • TypeResidential/Group Housing
  • Location
    • Belagavi
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1249/447/PR/180313/002394
  • ReraGenie IDRG-KA-00130

Builder

  • NameVenugram Infraventures Pvt Ltd
  • Entity typeCompany
  • CINU70102KA2011PTC056502
  • Authorized SignatorySubodh A Tembe, CMD
  • DirectorsHarshad S. Kalghatgi, Bhagwan A Walvekar, Dnyanesh K.Ginde, Sanjiv R Doddanavar, Ajit V Lokur, Vijay M Muchandikar
  • Other registrations1 more →

Key dates

this monthRegisteredMar 2018First promiseMar 2019Revised toMar 2020

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 Mar 2018
  • Promised completion30 Mar 2020
  • Revised completionRevised to 30 Mar 2020 (originally 30 Mar 2019)
  • Buildings1 building record
  • Documents filed56 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VENUGRAM VAJRA---16016

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area428 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 1.01 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAbheet V. Devel
EngineerSagar Huddar

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2019 → Dec 2020

No reason recorded in the filing

EX/PRM/KA/RERA/1249/447/PR/200218/002394Dec 2020 → Mar 2020

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed56

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/180313/002394 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Company Regn Certificate.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate for work done Godsewadi.jpg-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate for Completed work ( Project Extension) Vajra.pdf-
CA Certificate for Funds UtilizationFile: C A Cert Funds Utilised Vajra_compressed.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate for pending work Godsewadi.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate for Pending work ( Project Extension) Vajra.pdf-
CA Certificate for Funds required for Project CompletionFile: C A Cert Funds Required Vajra_compressed (1).pdf-
AffidavitFile: FORM B Godsewadi Project Extn.pdf-
Latest Encumbrance CertificateFile: Nil Encumbrance Godsewadi.pdf-
Consent letter from 2/3rd of AllotteesFile: Consent Letter from allottes Vajra.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails Godsewadi.xlsx-
Document 1File: Notarised Affidavit Vajra.pdf-
Document 2File: Affidavit for Project Extn VAJRA.pdf-
Document 3File: Modified Plan acknowledgement VAJRA.pdf-
Document 4File: Revised Estimate Godsewadi merged (1).pdf-
Document 5File: UBI statement merged.pdf-
Document 6File: Building permission order copy & Modified plan acknowledgemnt.pdf-
Building Permission letter Godsewadi-
godsewadi colour-
Layout Plot ( Property Card)-
Draft of SALE-DEED Godsewadi RERA-
Draft of Agreement of Sale RERA-
combinepdf-ilovepdf-compressed-
godsewadi colour-
godsewadi colour-
Draft of Possession Certificate Godsewadi RERA-
SPECIFICATIONS RERA-
Nil Encumbrance 2001 to 2015-ilovepdf-compressed (1)-
CTS Extract Godsewadi (2 files merged)-
Fire NOC RERA-ilovepdf-compressed (1)-
NOC HESCOM-
All NOCS for RERA-
Layout Plot ( Property Card)-
godsewadi colour-
N A Layout (3 files merged)-ilovepdf-compressed-
Legal Opinion for RERA-
Balance Sheet 2016 - 2017File: Balance Sheet 2016-17.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet 2015-16.pdf-
Balance Sheet 2014 - 2015File: Bal Sheet 2015 RERA.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit & Loss 2016-17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Profit & Loss 2015-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Profit & Loss 2014-15.pdf-
Director's Report 2016 - 2017File: Directors Report 2016-17 For RERA.pdf-
Director's Report 2015 - 2016File: Directors Report 2015-16 for RERA.pdf-
Director's Report 2014 - 2015File: Directors Report 2015.pdf-
Cash Flow Statement 2016 - 2017File: Cash Flow Statement 2016-17.pdf-
Cash Flow Statement 2015 - 2016File: Cash Floww Statement 2015-16.pdf-
Auditor's Report 2016 - 2017File: 7th Annual Report 2016-17_0001 (20 files merged)-ilovepdf-compressed.pdf-
Auditor's Report 2015 - 2016File: Tax Audit Report 2015-16 for RERA.pdf-
Auditor's Report 2014 - 2015File: Tax Audit Report_0001 (11 files merged)-ilovepdf-compressed.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: IT Return acknowledgment 2016-2017.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: IT Tax return Acknowlegment 2015-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: IT Tax return Acknowlegment 2014-15.pdf-
FORM B for RERA-
Advertisement Copy 1File: ADVT Copy Godsewadi.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1249_447_PR_180313_002394 Godsewadi.xlsx-

How this compares with Belagavi

24%of Belagavi projects moved their completion datethis one moved by 12 months
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep Venugram Vajra on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

Builder: Venugram Infraventures Pvt Ltd

Venugram Infraventures Pvt Ltd has 2 registrations on RERA Karnataka, including Venugram Vajra and VENUGRAM EMERALD. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if Venugram Vajra is delayed beyond 30 Mar 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Venugram Vajra?

The registered promoter entity is Venugram Infraventures Pvt Ltd, a company as per the filing. Its CIN U70102KA2011PTC056502 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Venugram Vajra?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Venugram Vajra?

The professionals named in the filing: Architect: Abheet V. Devel; Engineer: Sagar Huddar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Venugram Vajra?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Venugram Vajra. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Venugram Vajra to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.