Home / Browse projects / Chikkaballapura, Karnataka / UNNATI
UNNATI
RG-KA-00188 · RERA PRM/KA/RERA/1251/446/PR/190924/007045 · Last updated on RERA Karnataka portal: 16 Oct 2026
Source: official RERA Karnataka filing
Red flags
- Litigation declared, 1 case
- 1 complaint at RERA Karnataka
Clear
- Completion date never moved
- Separate project account declared
Saved.
UNNATI is a Plotted Development project by HC UNNATI FARMS LLP in Chikkaballapura, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/190924/007045 on 19 Sep 2024. Possession is promised by 1 Jan 2029. 1 complaint is on record with the regulator.
At a glance
Project
- NameUNNATI
- TypePlotted Development
- Location
- Gudibanda
- Chikkaballapura
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/446/PR/190924/007045
- ReraGenie IDRG-KA-00188
Builder
- NameHC UNNATI FARMS LLP
- Entity typePartnership Firm
- LLPINAAW-3783
- GSTIN29AANFH8277P1Z6
- Authorized SignatoryJayanthi Ashok Kumar
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on19 Sep 2024
- Promised completion1 Jan 2029
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed209 files
Current status
Figures as on 16 Oct 2026, this project's latest RERA Karnataka filing.
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership13
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| HC Unnati Farms LLP | - | - |
| HC Unnati Farms LLP | - | - |
| HC Unnati Farms LLP | - | - |
| HC Unnati Farms LLP | - | - |
| HC Unnati Farms LLP | - | - |
| HC Unnati Farms LLP | - | - |
| HC Unnati Farms LLP | - | - |
| HC Unnati Farms LLP | - | - |
| Hosachiguru Farms LLP | - | - |
| Hosachiguru Farms LLP | - | - |
| Hosachiguru Farms LLP | - | - |
| Hosachiguru Farms LLP | - | - |
| HOSACHIGURU FARMS LLP | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 44.21 cr | Rs 3.83 cr |
| Legal and Documentation | Rs 7.50 cr | Rs 13.00 lakh |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 5.00 cr | - |
| On-site expenditure-Consultants Fees | Rs 62.50 lakh | - |
| On-site expenditure-Salaries of workers | Rs 54.35 lakh | Rs 6.00 lakh |
| On-site expenditure-Site Overhead | Rs 53.51 lakh | Rs 2.75 lakh |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | SHIBASISH MAJUMDER |
| Chartered Accountant | Yashvant M Nijagal |
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 146 | CIVIL JUDGE AND JMFC GUDIBANDE | - |
Complaints filed with RERA Karnataka1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 00722/2025 | - | HC UNNATI FARMS LLP | 12/05/2025 |
Documents filed209
As listed on the registration, under the names the promoter filed them with; the newest 80 of 209 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/190924/007045 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form_-4_Chartered_Accountant_Unnati_Q2_FY_2026-27_15102026_signed.pdf | 16 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: 21-15102024-CE-HC UNNATI.pdf | 16 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 16 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 16 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 16 Oct 2026 |
| Q2 2026-27 Preventive Order (Injunction / Interim Order / Final Order / Stay OrderFile: OS 146-2022.pdf | 16 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4_Chartered Accountant_Unnati_Q1_FY 2026-27_signed.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: 25-14072026-CE-HC UNNATI (1).pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q1 2026-27 Preventive Order (Injunction / Interim Order / Final Order / Stay OrderFile: 146-2022 Order sheet.pdf | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Q4 CA CERTIFICATE.pdf | 10 Jul 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q4 CE CERTIFICATE 2025-26.pdf | 10 Jul 2026 |
| Q4 2025-26 Water supply and sewage board | 10 Jul 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 10 Jul 2026 |
| Q4 2025-26 KPTCL- BESCOM | 10 Jul 2026 |
| Q4 2025-26 Preventive Order (Injunction / Interim Order / Final Order / Stay OrderFile: 146-2022 Order sheet.pdf | 10 Jul 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate Q3 20-01-2026.pdf | 20 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q3 Charted Engineer 20-01-2026.pdf | 20 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 20 Jan 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 20 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 20 Jan 2026 |
| Q3 2025-26 Preventive Order (Injunction / Interim Order / Final Order / Stay OrderFile: 146-2022 Order sheet.pdf | 20 Jan 2026 |
| Reply Letter clarificationFile: Reply Letter.pdf | 16 Sep 2024 |
| Source of Fund LetterFile: Source of Fund Letter.pdf | 16 Sep 2024 |
| Unnati ITR ACK AY 2022-23File: Unnati ITR ACK AY 2022-23.pdf | 16 Sep 2024 |
| Unnati ITR ACK AY 2023-24File: Unnati ITR ACK AY 2023-24.pdf | 16 Sep 2024 |
| Unnati ITR ACK AY 2024-25File: Unnati ITR ACK AY 2024-25.pdf | 16 Sep 2024 |
| CA Certificate HC unnathiFile: CA Certificate HC unnathi.pdf | 16 Sep 2024 |
| HC Unnati Farms LLP FS AY 2022- 2023File: HC Unnati Farms LLP FS AY 2022- 2023.pdf | 16 Sep 2024 |
| HC Unnati Farms LLP FS AY 2023- 2024File: HC Unnati Farms LLP FS AY 2023- 2024.pdf | 16 Sep 2024 |
| HC Unnati Farms LLP FS AY 2024- 2025File: HC Unnati Farms LLP FS AY 2024- 2025.pdf | 16 Sep 2024 |
| Ashok - Partner Financials Last 3 YearsFile: Ashok Financials Last 3 Years.pdf | 16 Sep 2024 |
| Srinath - Partner Financials Last 3 YearsFile: Srinath Financials Last 3 Years.pdf | 16 Sep 2024 |
| Reply Letter clarificationFile: Reply Letter.pdf | 16 Sep 2024 |
| Bank AffidavitFile: Bank Affidavit_Revised.pdf | 8 Jul 2024 |
| Financials for 2022-23 with udinFile: HC Unnati Farms LLP_ FY_2022-23_RERA Purpose.pdf | 8 Jul 2024 |
| Certificate of IncorporationFile: Certificate of Incorporation UNNATI.pdf | 8 Jul 2024 |
| EC FOR SURVEY NO 4File: EC FOR SURVEY NO 4.pdf | 8 Jul 2024 |
| EC FOR SURVEY NO 5File: EC FOR SURVEY NO 5.pdf | 8 Jul 2024 |
| KSPCB NOCFile: KSPCB NOC UNNATI PROJECT.pdf | 8 Jul 2024 |
| FORM B AFFIDAVITFile: Form B Affidavit.pdf | 8 Jul 2024 |
| OS 37-2022File: Order Sheet OS 37-2022.pdf | 8 Jul 2024 |
| OS 165-2020File: Order Sheet OS 165-2020.pdf | 8 Jul 2024 |
| OS 224 -2021File: Order Sheet OS 224-2021.pdf | 8 Jul 2024 |
| OS 225-2021File: Order Sheet OS 225-2021.pdf | 8 Jul 2024 |
| OS 226-2021File: Order sheet OS 226-2021.pdf | 8 Jul 2024 |
| OS 227-2021File: Order Sheet OS 227-2021.pdf | 8 Jul 2024 |
| OS 223-2021File: Order Sheet-OS 223-2021.pdf | 8 Jul 2024 |
| OS 21-2009File: Final Decree OS 21-2009.pdf | 8 Jul 2024 |
| CONVERSION ORDER 5/3File: Conversion Copy of Sy No 5-3.pdf | 8 Jul 2024 |
| SALE DEEDFile: Doc No 1238-2021-22 From Venkatesh To HFLLP Saledeed.pdf | 8 Jul 2024 |
| MR 5/3File: MR No T7 of Sy No 5-3.pdf | 8 Jul 2024 |
| WATER NOCFile: Water - Gram Panchyath NOC (1).pdf | 8 Jul 2024 |
| RTC 5/3File: RTC of Sy No 5-3 Hosachiguru Farms LLP Autorized Rep by Pavithra B C.pdf | 8 Jul 2024 |
| SECTION 3 AFFIDAVITFile: Notarized Affidavit for 3(1) Violation (1)_revised.pdf | 8 Jul 2024 |
| VILLAGE MAPFile: Village Map - Gaddam Naganadinne.pdf | 8 Jul 2024 |
| GPAFile: GDB-4-00002-2024-25 Hosachiguru Farms LLP & others to HC Unnati Farms LLP (GPA).pdf | 8 Jul 2024 |
| JDAFile: GDB-1-00044-2024-25 from Hosachiguru Farms LLP to HC Unnati Farms LLP Joint Development Ag | 8 Jul 2024 |
| legal opinionFile: Legal Opinion-Unnati_compressed (1).pdf | 8 Jul 2024 |
| Engineer certificateFile: Form 3 -RERA (1).pdf | 8 Jul 2024 |
| Engineer licenceFile: Chartered Engineer Certificate.jpg | 8 Jul 2024 |
| project specificationsFile: Unnathi Project Specification.pdf | 8 Jul 2024 |
| financial statements for 2021-22 with udinFile: HC Unnati Farms LLP FS FY 2021- 2022.pdf | 8 Jul 2024 |
| BESCOM NocFile: BESCOM NOC (1).pdf | 8 Jul 2024 |
| Technical ApprovalFile: Unnati Layout -Technical Approved Copy (4).pdf | 8 Jul 2024 |
| MRFile: MR.pdf | 8 Jul 2024 |
| Conversion OrdersFile: Conversion orders.pdf | 8 Jul 2024 |
| Relinquishment DeedFile: Reliquish Deed Unnati.pdf | 8 Jul 2024 |
| AgreementsFile: HC Unnati-Agreements.pdf | 8 Jul 2024 |
| Latest RTCFile: RTC Sy No.pdf | 8 Jul 2024 |
| RTC, survey 4/1 | - |
| Mutation, survey 4/1 | - |
| Encumbrance Certificate, survey 4/1 | - |
| Conversion/Alienation Order, survey 4/1 | - |
| Sale/Title/Gift Deed, survey 4/1 | - |
| Khatha, survey 4/1 | - |
| RTC, survey 4/2 | - |
| Mutation, survey 4/2 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Chikkaballapura
Computed across the 170+ Chikkaballapura projects on ReraGenie, from their own filings.
Keep UNNATI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chikkaballapura170+ in Chikkaballapura
AKSHADHAA ASSISTED LIVING
AKSHADHAA ASSISTED LIVING ESTABLISHMENT LL
RETREAT 76
M/s Truenest Builders
BELMONT CONDOMINIUM
CITRUS INFRASTRUCTURE PRIVATE LIMITED
OVER THE RAINBOW PHASE 1
TOTAL ENVIRONMENT PROJECTS (INDIA) PRIVATE
CONSTRUCTION OF AHP UNITS UNDER PKGB SEP-2019
MUNICIPAL COMMISSIONER
onstruction of 18 DUS-PKGB in Chintamani CMC
City Municipal Council Chintamani
See every Chikkaballapura project, with the district possession charts
Builder: HC UNNATI FARMS LLP
HC UNNATI FARMS LLP has 1 registration on RERA Karnataka, including UNNATI. Its filings disclose no earlier RERA Karnataka projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Chikkaballapura district page.
Frequently asked questions
What are my rights if UNNATI is delayed beyond 1 Jan 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of UNNATI?
The registered promoter entity is HC UNNATI FARMS LLP, a partnership firm as per the filing. Its LLPIN AAW-3783 and GSTIN 29AANFH8277P1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in UNNATI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against UNNATI?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at UNNATI?
The professionals named in the filing: Engineer: SHIBASISH MAJUMDER; Chartered Accountant: Yashvant M Nijagal. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in UNNATI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback