ReraGenieLog inGet a buyer report

Home / Browse projects / Chikkaballapura, Karnataka / AKSHADHAA ASSISTED LIVING

Registration approved No litigation declared Mixed Development project

AKSHADHAA ASSISTED LIVING

By AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP

RG-KA-85594 · RERA PRM/KA/RERA/1254/464/PR/260224/006652 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Feb 2029Possession promisedno revision filed
1 of 17Construction stages donefurthest along: Earth work and other leveling..., 80%
22 of 119Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 124 documents Report an error

AKSHADHAA ASSISTED LIVING is a Mixed Development project by AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP in Chikkaballapura, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1254/464/PR/260224/006652 on 26 Feb 2024. Possession is promised by 14 Feb 2029. 97 of the 119 units on this registration are recorded sold or booked, and 1 of 17 construction stages are filed complete.

At a glance

Project

  • NameAKSHADHAA ASSISTED LIVING
  • TypeMixed Development
  • Location
    • Gudibanda
    • Chikkaballapura
    • 562104
  • Pincode562104
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1254/464/PR/260224/006652
  • ReraGenie IDRG-KA-85594

Builder

  • NameAKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP
  • Entity typePartnership Firm
  • LLPINABA-7274
  • GSTIN29ABYFA3343F1Z4
  • Authorized SignatoryMr. ANIRBAN DUTTA

Key dates

this monthRegisteredFeb 2024PromisedFeb 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on26 Feb 2024
  • Promised completion14 Feb 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed124 files

Current status

82%97 of 119 units booked
65.1%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARENTS HOUSING BLOCK---65065
SPECIAL NEEDS INDIVIDUAL (SNI) ACCOMMODATION BLOCK---54054

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 80%.

Building: 57% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work80%
Foundation footing work80%
Upto Plinth Level75%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)60%
Retaining wall (All types)100%
RCC or MS Framed structure60%
Masonry Construction55%
Plastering inside , outside & Ceiling55%
Joinery: Doors, Windows, Ventilators etc50%
Basic work of Water supply, Sanitary and Electrification50%
Dadoing, Skirting, Flooring, Tiles work (All types)50%
Railing and Grill fixing60%
Electrification, Water supply and Sanitary Finishing50%
Painting50%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)50%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work30%
Internal and External work including landscapes as per sanctioned drawings10%

Progress on shared amenities41

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes60%
Sewage and Drainage SystemYes60%
Water conservation/rain water harvesting/recharge of ground waterYes15%
Energy managementYes10%
Fire protection and fire safety requirementsYes20%
Solid waste management and disposalYes5%
Emergency Evacuation servicesYes10%
Internal Roads & FootpathsYes35%
Electricity supply transformer and substationYes75%
Storm water drainsYes20%
Use of renewable energyYes15%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes50%
Street LightingYes10%
ElectricityYes80%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes10%
Club HouseNoNot applicable
Community HallYes25%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes20%
ParksYes20%
Power BackupYes50%
Piped GasYes10%
Water and SanitationYes50%
Air ConditioningNoNot applicable
SNI Learning Center FacilityYes0%
StaircasesYes50%
LiftsYes50%
Corridor/LobbiesYes45%
Fire escapesYes25%
Common entrance and exit for the building/common portico/foyer/verandahYes35%
BasementNoNot applicable
TerraceYes50%
Outer WallNoNot applicable
Open parking areasYes40%
Provision for lodging of management staff and security staffYes10%
Water conservation and renewable energyYes15%
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area19,627 sq m
Named landowners3
LandownerVillageDistrict
AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP--
AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP--
AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 38.83 cr
Cost incurredRs 25.29 cr
Spent of the estimate65.14%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 37.43 crRs 24.28 cr
On-site expenditure-Site OverheadRs 1.40 crRs 1.02 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSrimathi J Adiga
EngineerVishnu Kumar
Chartered AccountantMahaveer Jain

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed124

As listed on the registration, under the names the promoter filed them with; the newest 80 of 124 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1254/464/PR/260224/006652 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form - 4, CA rera QR - Akshada - Sep26 sd.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form -5 AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP 30-09-2026.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP 30-09-2026.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form - 4, CA rera QR - Akshada - Jun26 sd.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form5, Q1,2026-27,Akshadhaa Assisted Living Establishment LLP.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 AKSHADHAA ASSISTED LIVING EST LL 30-06-2026.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form - 4, CA rera QR - Akshada - Mar26 sd.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form5,Q4,2025-26 Akshadhaa Assisted Living.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP 31-03-2026.pdf14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form - 4, CA rera QR - Akshada - Dec25 signed.pdf16 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5,Q3,2025-26, Akshadhaa Assisted Living.pdf16 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 AKSHADHAA ASSISTED LIVING ESTABLISHMENT LL 31-12-2025.pdf16 Jan 2026
Financial Justification for Source of fundsFile: 1 Financial Justification for Source of funds.pdf6 Feb 2024
RTC Sy No 333-3File: 11 RTC Sy No 333-3.pdf6 Feb 2024
Form-B AffidavitFile: 2 Form-B Affidavit.pdf6 Feb 2024
Non-Litigation AffidavitFile: 3 Non-Litigation Affidavit.pdf6 Feb 2024
Sec 3(1) AffidavitFile: 4 Sec 3(1) Affidavit.pdf6 Feb 2024
STP Design signed by EngineerFile: 7 STP Design signed by Engineer.pdf6 Feb 2024
Estimation summary Signed by EngineerFile: 8 Estimation summary Signed by Engineer.pdf6 Feb 2024
AKSHADHAA Foundation Area StatementFile: 9 AKSHADHAA Foundation Area Statement.pdf6 Feb 2024
Guidance Value Self-attestedFile: 10 Guidance Value Self-attested.pdf6 Feb 2024
Development Plan 1File: 1 Development Plan 1.pdf6 Feb 2024
Development Plan 2File: 2 Development Plan 2.pdf6 Feb 2024
Approved Plan Page 2File: 3 Approved Plan Page 2.pdf6 Feb 2024
Approved Plan Page 3File: 4 Approved Plan Page 3.pdf6 Feb 2024
Approved Plan Page 4File: 5 Approved Plan Page 4.pdf6 Feb 2024
Approved Plan Page 5File: 6 Approved Plan Page 5.pdf6 Feb 2024
Approved Plan Page 6File: 7 Approved Plan Page 6.pdf6 Feb 2024
Approved Plan Page 7File: 8 Approved Plan Page 7.pdf6 Feb 2024
Approved Plan Page 8File: 9 Approved Plan Page 8.pdf6 Feb 2024
Approved Plan Page 9File: 10 Approved Plan Page 9.pdf6 Feb 2024
Approved Plan Page 10File: 11 Approved Plan Page 10.pdf6 Feb 2024
Approved Plan Page 11File: 12 Approved Plan Page 11.pdf6 Feb 2024
Approved Plan Page 12File: 13 Approved Plan Page 12.pdf6 Feb 2024
Approved Plan Page 13File: 14 Approved Plan Page 13.pdf6 Feb 2024
RTC, survey 333/1-
Mutation, survey 333/1-
Encumbrance Certificate, survey 333/1-
Conversion/Alienation Order, survey 333/1-
Sale/Title/Gift Deed, survey 333/1-
Khatha, survey 333/1-
RTC, survey 333/3-
Mutation, survey 333/3-
Encumbrance Certificate, survey 333/3-
Conversion/Alienation Order, survey 333/3-
Sale/Title/Gift Deed, survey 333/3-
Khatha, survey 333/3-
RTC, survey 333/4-
Mutation, survey 333/4-
Encumbrance Certificate, survey 333/4-
Conversion/Alienation Order, survey 333/4-
Sale/Title/Gift Deed, survey 333/4-
Khatha, survey 333/4-
Registration CertificateFile: Incorporation Certificate.PDF-
Partnership DeedFile: LLP Agreement.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form-1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form -2 AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP.pdf-
Certificate issued by Engineer Form 3File: Form-3,AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non-Litigiation Affidavit.pdf-
Certificate from Chartered AccountFile: Form-1 CA Certificate.pdf-
Balance Sheet 2022 - 2023File: Balancesheet 2022-23.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Profit and Loss.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR 2022-23.pdf-
Building License and Commencement Letter-
BESCOM NOC with fee paid receipt-

How this compares with Chikkaballapura

82%of this project is bookeddistrict median 86%
27%of Chikkaballapura projects moved their completion datethis one has not
1%of Chikkaballapura registrations are shown as withdrawn or revokedthis one is not

Computed across the 170+ Chikkaballapura projects on ReraGenie, from their own filings.

Keep AKSHADHAA ASSISTED LIVING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Chikkaballapura170+ in Chikkaballapura

Builder: AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP

AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP has 1 registration on RERA Karnataka, including AKSHADHAA ASSISTED LIVING. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Chikkaballapura district page.

Frequently asked questions

What are my rights if AKSHADHAA ASSISTED LIVING is delayed beyond 14 Feb 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of AKSHADHAA ASSISTED LIVING?

The registered promoter entity is AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP, a partnership firm as per the filing. Its LLPIN ABA-7274 and GSTIN 29ABYFA3343F1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in AKSHADHAA ASSISTED LIVING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AKSHADHAA ASSISTED LIVING?

The professionals named in the filing: Architect: Srimathi J Adiga; Engineer: Vishnu Kumar; Chartered Accountant: Mahaveer Jain. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AKSHADHAA ASSISTED LIVING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AKSHADHAA ASSISTED LIVING. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AKSHADHAA ASSISTED LIVING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.