Home / Browse projects / Bengaluru Urban, Karnataka / UMIYA PRISM

Registration approved No litigation declared Residential/Group Housing project

UMIYA PRISM

By UMIYA BUILDTEK

RG-KA-19196 · RERA PRM/KA/RERA/1251/309/PR/180426/008593 · Last updated on RERA Karnataka portal: 10 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2029Possession promisedno revision filed
0 of 17Construction stages donefurthest along: Earth work and other leveling..., 75%
8 of 9Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 91 documents Report an error

UMIYA PRISM is a Residential/Group Housing project by UMIYA BUILDTEK in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180426/008593 on 18 Apr 2026. Possession is promised by 31 Mar 2029. 1 of the 9 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete.

At a glance

Project

  • NameUMIYA PRISM
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 560001
  • Pincode560001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/180426/008593
  • ReraGenie IDRG-KA-19196

Builder

  • NameUMIYA BUILDTEK
  • Entity typePartnership Firm
  • GSTIN29AAIFU7757L1Z7
  • Authorized SignatoryANIRUDDHA MEHTA

Key dates

this monthRegisteredApr 2026PromisedMar 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Apr 2026
  • Promised completion31 Mar 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed91 files

Current status

11%1 of 9 units booked
6.3%Of the estimated cost spent so far

Figures as on 10 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
UMIYA PRISM---909

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 10 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 75%.

Building: 6% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work75%
Foundation footing work35%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)Not applicable
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja work0%
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 10 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes0%
TerraceYes0%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,765 sq m
Named landowners1
LandownerVillageDistrict
UMIYA BUILDTEK--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 24.34 cr
Cost incurredRs 1.54 cr
Spent of the estimate6.34%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 24.34 crRs 1.54 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANICKAVEL G K
EngineerHANUMANT GYANAPPA NAIKAR
Chartered AccountantASHAR A D

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed91

As listed on the registration, under the names the promoter filed them with; the newest 80 of 91 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180426/008593 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: form 4 CA CERTIFICATE_Q2 ( 2026-27 ).pdf10 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: From 5_Architect CERTIFICATE_Q2 ( 2026-27 ).pdf10 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer CERTIFICATE_Q2 ( 2026-27 ).pdf10 Oct 2026
Q2 2026-27 Water supply and sewage board10 Oct 2026
Q2 2026-27 KPTCL- BESCOM10 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4_CA Certificate_Q1_26-27.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate _Q1_26-27.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer Certificate_Q1_26-27.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
CA Form -01 ( with 3 bank accounts details ) & UDINFile: 1_FORM1_CA CERTIFICATE_Umiya Prism.pdf10 Apr 2026
Connected MR_ NA DeclarationFile: 2_MR_NA_Declearation_Umiya Prism.pdf10 Apr 2026
Conversion order issued by DC _ NA DeclarationFile: 3_Conversion Order_NA_Declearation_Umiya Prism.pdf10 Apr 2026
Advocate search report in the name of promoter firmFile: 10_Legal Opinion_Umiya Prism.pdf10 Apr 2026
Single Plot layout plan Approved _NA DeclarationFile: 4_Single Plot Plan & Order_NA_Declearation_Umiya Prism.pdf10 Apr 2026
Survey sketch __NA DeclarationFile: 5_Survey sketch_NA_Declearation_Umiya Prism.pdf10 Apr 2026
Approved Master plan BBMP_2015File: BBMP Master plan_2015.pdf10 Apr 2026
Demarcation of proposed land _Master PlanFile: 11_C T S vasanthnagar_Master Plan_Demarked.pdf10 Apr 2026
NOC under section 14 of the KTCP Act __NA DeclarationFile: 6_NOC under section 14_NA_Declearation_Umiya Prism.pdf10 Apr 2026
Affidivat _BESCOM NOC & BillFile: 8_Afffidivat_BESCOM NOC & Bill Reciept _Umiya Prism.pdf10 Apr 2026
Affidivat_BWSSB NOCFile: 9_Afffidivat_BWSSB NOC_Umiya Prism.pdf10 Apr 2026
structural stability certificate & structural engineer licence copyFile: 7_Structural stability certificate & Engineer License.pdf10 Apr 2026
KathaFile: 12_Katha & Tax Paid Recipet_BBMP_Umiya Prisim.pdf10 Apr 2026
Sale Deed BuildteckFile: 13_Sale Deed_Umiya Builteck.pdf10 Apr 2026
other refered Title document & MapsFile: 14_Title Document & map.pdf10 Apr 2026
Brief project estimation with licenced engineer signatureFile: Brief project estimation_umiya prism_Signed.pdf10 Apr 2026
Agreement of Sale_Perform_Umiya PrismFile: Agreement of Sale_Perform_Umiya Prism.pdf10 Apr 2026
Declaration_Amenities & Common Area_Umiya PrismFile: Declaration_Amenities & Common Area_Umiya Prism.pdf10 Apr 2026
BESCOM_Service Certificate_Umiya PrismFile: BESCOM_Service Certificate_Umiya Prism.pdf10 Apr 2026
Registration CertificateFile: Umiya Buildtek_Firm Reg Certificate.pdf-
GST CertificateFile: Umiya Buildtek_GST.pdf-
Partnership DeedFile: Umiya Buildtek_Partnership Deed_1.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: 1_FORM1_CA CERTIFICATE_Umiya Prism.pdf-
Certificate issued by Architect Form 2File: Form 2Architects certificateUmiya Prism.pdf-
Certificate issued by Engineer Form 3File: Form - 3_Engineer certificate_Umiya Prism.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation_Affidavit _Umiya Prism.pdf-
Balance Sheet 2024 - 2025File: Umiya Builteck_ITR_2024-25.pdf-
Balance Sheet 2023 - 2024File: Self Declaration tax return 2023-24.pdf-
Balance Sheet 2022 - 2023File: self Declaration tax return 2022-23.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Umiya Builteck_ITR_2024-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Self Declaration tax return 2023-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: self Declaration tax return 2022-23.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: Umiya Builteck_ITR_2024-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: Self Declaration tax return 2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: self Declaration tax return 2022-23.pdf-
Approval letter_Building Licence_Umiya-
Approved Building Plan_Umiya Prism-
Approved Building Plan_Umiya Prism-
Stability Certificate_Umiya Prisim-
Project Specifications_Umiya Prism-
Self Declaration Project Brochore-
Self Declaration Relinquishment Deed-
Perform Agreement of Sale_Umiya Prism-
Allotment Letter_Umiya Prism-
Form B_Affidavit cum Declaration_Umiya Prism-
Affidavit 3_1_Violation_Umiya Prism-
Self Declaration JDA-
Legal Opinion_Umiya Prism-
BSCOM_Existing Service Bill-
NOC_BWSSB-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Katha & Tax Paid Recipet_BBMP-
26172_2008_OS-
51_14_15_JDA-
9634_2017_18_Deed Canceled-

How this compares with Bengaluru Urban

11%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep UMIYA PRISM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmUMIYA PRISMOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: UMIYA BUILDTEK

UMIYA BUILDTEK has 1 registration on RERA Karnataka, including UMIYA PRISM. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if UMIYA PRISM is delayed beyond 31 Mar 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of UMIYA PRISM?

The registered promoter entity is UMIYA BUILDTEK, a partnership firm as per the filing. Its GSTIN 29AAIFU7757L1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in UMIYA PRISM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at UMIYA PRISM?

The professionals named in the filing: Architect: MANICKAVEL G K; Engineer: HANUMANT GYANAPPA NAIKAR; Chartered Accountant: ASHAR A D. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UMIYA PRISM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UMIYA PRISM. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UMIYA PRISM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.