Home / Browse projects / Gandhinagar, Gujarat / TULSI BUNGLOW

Valid until 30 Jan 2027 Residential/Group Housing project

TULSI BUNGLOW

By TULSI DEVELOPERS

RG-GJ-48254 · RERA PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA12819/290124/300926 · Last updated on GujRERA portal: 6 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jan 2027Possession promisedno revision filed
75 of 90Construction stages doneacross 10 buildings; furthest along: Slabs of Super Structure, 67%
11 of 36Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

TULSI BUNGLOW is a Residential/Group Housing project by TULSI DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA12819/290124/300926 on 29 Jan 2024. Possession is promised by 30 Jan 2027. 25 of the 36 units on this registration are recorded sold or booked, and 75 of 90 construction stages are filed complete.

At a glance

Project

  • NameTULSI BUNGLOW
  • TypeResidential/Group Housing
  • Location
    • survey no. 1041 + 1042 + 1043
    • FP - 231
    • NEW PANCHWATI AREA
    • KALOL
    • GANDHINAGAR - 382721
    • KALOL
    • Kalol (G)
    • Gandhinagar
    • 382721
  • Pincode382721
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA12819/290124/300926
  • ReraGenie IDRG-GJ-48254

Builder

  • NameTULSI DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →
  • Past their filed date1

Key dates

this monthRegisteredJan 2024PromisedJan 2027

Key facts

Registration and timeline

  • StatusValid until 30 Jan 2027
  • Registered on29 Jan 2024
  • Promised completion30 Jan 2027
  • Revised completionNone
  • Buildings10 building records
  • Documents filed41 files

Current status

69%25 of 36 units booked
57.4%Of the estimated cost spent so far

Figures as on 6 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A (1)---101
B (2)---101
A (5)---101
A (4)---101
A (3)---909
A (6)---101
B (3)---606
B (4)---606
A (2)---909
B (1)---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building10

As on 6 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

75 of 90 construction stages are filed complete across 10 buildings. The stage furthest along is Slabs of Super Structure, at 67%.

A (1)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B (2)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A (5)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A (4)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A (3)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A (6)80%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure67%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B (3)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B (4)78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor67%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats67%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing67%
A (2)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B (1)89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 6 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes80%
Water supplyYes80%
Sewerage (chamber, lines, septic tank, STP)Yes80%
Storm water drainsYes80%
Landscaping and tree plantingNoNot applicable
Street lightingYes80%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityNoNot applicable
Letter boxNoNot applicable
Compound wallYes80%
Plinth protectionYes80%
Water tankYes80%
Other requirementsYes80%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,493 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 9.58 cr
Cost incurredRs 5.50 cr
Spent of the estimate57.42%
BuildingWingEstimatedIncurred
A (2)NARs 2.43 crRs 1.39 cr
A (3)NARs 2.43 crRs 1.39 cr
B (3)NARs 1.59 crRs 91.04 lakh
B (4)NARs 1.59 crRs 91.04 lakh
A (5)NARs 27.77 lakhRs 15.94 lakh
A (1)NARs 27.75 lakhRs 15.94 lakh
A (6)NARs 25.39 lakhRs 14.58 lakh
A (4)NARs 25.39 lakhRs 14.58 lakh
B (1)NARs 24.52 lakhRs 14.08 lakh
B (2)NARs 24.52 lakhRs 14.08 lakh

Certifying professionals and partners1

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerSANGHAVI BIPIN JAYANTILAL

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA12819/290124/300926 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)6 Oct 2024
Engineer's certificate annexure6 Oct 2024
RERA registration certificate29 Jan 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

69%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep TULSI BUNGLOW on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KALOL1,600+ in Gandhinagar

2 kmTULSI BUNGLOWOther 65Dot size: filed unitsN

Filed coordinates, straight-line distance. 65 registered projects within 2 km.

Builder: TULSI DEVELOPERS

TULSI DEVELOPERS has 2 registrations on GujRERA, including DWARKESH BUNGLOWS and TULSI BUNGLOW. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if TULSI BUNGLOW is delayed beyond 30 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of TULSI BUNGLOW?

The registered promoter entity is TULSI DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in TULSI BUNGLOW?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at TULSI BUNGLOW?

The professionals named in the filing: Engineer: SANGHAVI BIPIN JAYANTILAL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TULSI BUNGLOW?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TULSI BUNGLOW. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TULSI BUNGLOW to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.