RG-KA-34401 · RERA PRM/KA/RERA/1251/310/PR/090925/008077 · Last updated on RERA Karnataka portal: 14 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2028Possession promisedno revision filed
16 of 16Construction stages doneevery applicable stage filed complete
16 of 16Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 123 documents Report an error

Trilok Premium Apartments is a Residential/Group Housing project by NARESH KUMAR H in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/090925/008077 on 9 Sep 2025. Possession is promised by 30 Aug 2028. 0 of the 16 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.

At a glance

Project

  • NameTrilok Premium Apartments
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560098
  • Pincode560098
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/090925/008077
  • ReraGenie IDRG-KA-34401

Builder

  • NameNARESH KUMAR H
  • Entity typeProprietorship
  • GSTIN29ABGPJ5503L1ZH
  • Authorized SignatoryNARESH KUMAR H
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2025PromisedAug 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Sep 2025
  • Promised completion30 Aug 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed123 files

Current status

0%0 of 16 units booked
96.2%Of the estimated cost spent so far

Figures as on 14 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Trilok Premium Apartments---16016

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 16 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes100%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,314 sq m
Named landowners2
LandownerVillageDistrict
NARESH KUMAR H--
NARESH KUMAR H--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 6.72 cr
Cost incurredRs 6.47 cr
Spent of the estimate96.23%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 6.00 crRs 6.00 cr
On-site expenditure-Salaries of workersRs 72.35 lakhRs 12.00 lakh
Payment of charges-Rs 35.00 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAditya G Kashyap
EngineerS Lakshmikantha
Chartered AccountantJagadeesh Anant Hebbar

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed123

As listed on the registration, under the names the promoter filed them with; the newest 80 of 123 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/090925/008077 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA Certificate_signed.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect certficate - Q1 till Jun 26.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineers Certificate -Q1 till Jun 26.pdf14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA certificate Mar Q4.pdf12 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect certficate - Q4 till Mar 26.pdf12 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineers Certificate -Q4 till Mar 26.pdf12 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Signed Q3 RERA Certificate.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect certficate - Q3 till Dec 25.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineers Certificate -Q3 till dec 25.pdf13 Jan 2026
Area development planFile: Area development plan.pdf6 Sep 2025
CC AffidavitFile: CC Affidavit.pdf6 Sep 2025
KTCP NocFile: KTCP Noc.pdf6 Sep 2025
Sanction PlanFile: Sanction Plan.pdf6 Sep 2025
Single Plot layout plan & Single Plot Layout Plan OrderFile: Single Plot layout plan & Order.pdf6 Sep 2025
Survey SketchFile: Survey Sketch.pdf6 Sep 2025
Village MapFile: Village Map.pdf6 Sep 2025
Building LicenseFile: Building License.pdf6 Sep 2025
Land CostFile: Land Cost.pdf6 Sep 2025
29_14 and 29_15 B EkhataFile: 29_14 and 29_15 B Ekhata.PDF13 Aug 2025
2914 RTCFile: 2914 RTC.pdf13 Aug 2025
2915B RTCFile: 2915B RTC.pdf13 Aug 2025
Allotment LetterFile: Allotment Letter.pdf13 Aug 2025
Point 1 & 2File: Point 1 & 2.pdf13 Aug 2025
Estimation by EngineereFile: Point 2 Para 2 Estimation by Engineere.pdf13 Aug 2025
Apartments PlanFile: Point 3 Trilok Premium Apartments Plan.pdf13 Aug 2025
Survey sketchFile: Point 4 29_14 and 29_15b sketch.pdf13 Aug 2025
Point 7 Village MapFile: Point 7 Village Map.pdf13 Aug 2025
STP ClarificationFile: STP Clarification.pdf13 Aug 2025
BESCOMFile: BESCOM.pdf13 Aug 2025
BWSSBFile: BWSSB.pdf13 Aug 2025
Land cost Calculatio sheetFile: Land cost Calculatio sheet.pdf13 Aug 2025
Common area calculationFile: Common area calculation.pdf13 Aug 2025
survey sketchFile: 29 survey sketch.pdf24 Jun 2025
29.14 ECFile: 2914 EC.pdf24 Jun 2025
29.14 MRFile: 2914 MR.pdf24 Jun 2025
29.14 RTCFile: 2914 RTC.pdf24 Jun 2025
29.15B ConversionFile: 2915B Conversion.pdf24 Jun 2025
29.15B ECFile: 2915B EC.pdf24 Jun 2025
29.15B MRFile: 2915B MR.pdf24 Jun 2025
29.15B RTCFile: 2915B RTC.pdf24 Jun 2025
Allotment LetterFile: Allotment Letter.pdf24 Jun 2025
AmenitiesFile: Amenities Letter.pdf24 Jun 2025
Bank Account AffidavitFile: Bank Account Affidavit.pdf24 Jun 2025
Bank StatementFile: Bank Account Statement.pdf24 Jun 2025
Building LicenseFile: Building License.pdf24 Jun 2025
ITR with Balance Sheet, P&L, Schedule 21-22File: CA 21-22.pdf24 Jun 2025
ITR with Balance Sheet, P&L, Schedule 22-23File: CA 22-23.pdf24 Jun 2025
ITR with Balance Sheet, P&L, Schedule 23-24File: CA 23-24.pdf24 Jun 2025
Commencement CertificateFile: CC Affidavit.pdf24 Jun 2025
Cost of projectFile: Certificate of Cost of Project.pdf24 Jun 2025
Date of Completion AffidavitFile: Date of Completion Affidavit.pdf24 Jun 2025
Engineere LicenseFile: Engineer License.pdf24 Jun 2025
Engineere EstimationFile: Engineere Estimation.pdf24 Jun 2025
KTCPFile: KPTCL letter.pdf24 Jun 2025
Rera Acknowledgement AffidavitFile: Rera Acknowledgement Affidavit.pdf24 Jun 2025
Guideline ValueFile: SR Value.pdf24 Jun 2025
Sanction plan. Section drawingFile: Trilok Premium Apartments Plan.pdf24 Jun 2025
Village MapFile: Village Map.pdf24 Jun 2025
RTC, survey 29/14-
Mutation, survey 29/14-
Encumbrance Certificate, survey 29/14-
Conversion/Alienation Order, survey 29/14-
Sale/Title/Gift Deed, survey 29/14-
Khatha, survey 29/14-
RTC, survey 29/15B-
Mutation, survey 29/15B-
Encumbrance Certificate, survey 29/15B-
Conversion/Alienation Order, survey 29/15B-
Sale/Title/Gift Deed, survey 29/15B-
Khatha, survey 29/15B-
Registration CertificateFile: M Square Properties GST CERTIFICATE.pdf-
GST CertificateFile: M Square Properties GST CERTIFICATE.pdf-
Certificate issued by CA Form 1File: CA Certificate.pdf-
Certificate issued by Architect Form 2File: Architect.pdf-
Certificate issued by Engineer Form 3File: Engineers Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: No Litigation.pdf-
Balance Sheet 2023 - 2024File: Balance 23.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Trilok Villas And Apartments29/1 kenchenehalli village rr nagarCompleted-No date filed

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Trilok Premium Apartments on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmTrilok Premium ApartmentOther 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 17 registered projects within 2 km.

Builder: NARESH KUMAR H

NARESH KUMAR H has 2 registrations on RERA Karnataka, including Trilok Premium Apartments and Trilok Villas and Apartments. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Trilok Premium Apartments is delayed beyond 30 Aug 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Trilok Premium Apartments?

The registered promoter entity is NARESH KUMAR H, a proprietorship as per the filing. Its GSTIN 29ABGPJ5503L1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Trilok Premium Apartments?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Trilok Premium Apartments?

The professionals named in the filing: Architect: Aditya G Kashyap; Engineer: S Lakshmikantha; Chartered Accountant: Jagadeesh Anant Hebbar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Trilok Premium Apartments?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Trilok Premium Apartments. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Trilok Premium Apartments to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.