HAVELI RESI CUM PLAZA
RG-GJ-54842 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA02948/190618 · Last updated on GujRERA portal: 9 Sep 2020
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
- Separate project account declared
Saved.
HAVELI RESI CUM PLAZA is a Mixed Development project by VRAJ ASSOCIATES in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA02948/190618 on 19 Jun 2018. Possession is promised by 25 Jun 2023. 228 of the 278 units on this registration are recorded sold or booked, and 114 of 117 construction stages are filed complete.
At a glance
Project
- NameHAVELI RESI CUM PLAZA
- TypeMixed Development
- Location
- OPP ROYAL VILL
- BH AIR FORCE STATION MAKARPURA
- Makarpura
- Vadodara
- 390014
- Pincode390014
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA02948/190618
- ReraGenie IDRG-GJ-54842
Builder
- NameVRAJ ASSOCIATES
- Entity typePARTNERSHIP FIRM
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 25 Jun 2023
- Registered on19 Jun 2018
- Promised completion25 Jun 2023
- Revised completionNone
- Buildings13 building records
- Documents filed50 files
Current status
Figures as on 9 Sep 2020, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER F | - | - | - | 20 | 0 | 20 |
| TOWER G | - | - | - | 20 | 0 | 20 |
| TOWER H | - | - | - | 20 | 0 | 20 |
| TOWER I | - | - | - | 20 | 0 | 20 |
| TOWER J | - | - | - | 20 | 0 | 20 |
| TOWER K | - | - | - | 14 | 12 | 26 |
| TOWER L | - | - | - | 14 | 12 | 26 |
| TOWER M | - | - | - | 14 | 12 | 26 |
| TOWER A | - | - | - | 20 | 0 | 20 |
| TOWER B | - | - | - | 20 | 0 | 20 |
| TOWER C | - | - | - | 20 | 0 | 20 |
| TOWER D | - | - | - | 20 | 0 | 20 |
| TOWER E | - | - | - | 20 | 0 | 20 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building13
As on 9 Sep 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
114 of 117 construction stages are filed complete across 13 buildings. The stage furthest along is Stilt Floor, at 23%.
TOWER F100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TOWER G100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TOWER H100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TOWER I100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TOWER J91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 23% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TOWER K100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TOWER L100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TOWER M100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TOWER A89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TOWER B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TOWER C89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TOWER D100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TOWER E100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 9 Sep 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | No | Not applicable |
| Landscaping and tree planting | No | Not applicable |
| Street lighting | Yes | 100% |
| Community buildings | Yes | 100% |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | Yes | 90% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TOWER A | NA | Rs 1.48 cr | Rs 1.48 cr |
| TOWER B | NA | Rs 1.48 cr | Rs 1.48 cr |
| TOWER C | NA | Rs 1.48 cr | Rs 1.48 cr |
| TOWER D | NA | Rs 1.48 cr | Rs 1.48 cr |
| TOWER E | NA | Rs 1.48 cr | Rs 1.48 cr |
| TOWER F | NA | Rs 1.48 cr | Rs 1.48 cr |
| TOWER G | NA | Rs 1.48 cr | Rs 1.48 cr |
| TOWER H | NA | Rs 1.48 cr | Rs 1.48 cr |
| TOWER I | NA | Rs 1.48 cr | Rs 1.48 cr |
| TOWER J | NA | Rs 1.48 cr | Rs 1.48 cr |
| TOWER K | NA | Rs 1.48 cr | Rs 1.48 cr |
| TOWER L | NA | Rs 1.48 cr | Rs 1.48 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KANUBHAI PATEL |
| Engineer | NARENDRA PATEL & ASSOCIATES |
Documents filed50
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA02948/190618 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 9 Sep 2020 |
| Architect's certificate (Form 1) | 8 Sep 2020 |
| Engineer's certificate (Form 2) | 8 Sep 2020 |
| Engineer's certificate annexure | 8 Sep 2020 |
| Site photograph, TOWER F | 8 Sep 2020 |
| Site photograph, TOWER G | 8 Sep 2020 |
| Site photograph, TOWER H | 8 Sep 2020 |
| Site photograph, TOWER I | 8 Sep 2020 |
| Site photograph, TOWER J | 8 Sep 2020 |
| Site photograph, TOWER K | 8 Sep 2020 |
| Site photograph, TOWER L | 8 Sep 2020 |
| Site photograph, TOWER M | 8 Sep 2020 |
| Site photograph, TOWER A | 8 Sep 2020 |
| Site photograph, TOWER B | 8 Sep 2020 |
| Site photograph, TOWER C | 8 Sep 2020 |
| Site photograph, TOWER D | 8 Sep 2020 |
| Site photograph, TOWER E | 8 Sep 2020 |
| RERA registration certificate | 19 Jun 2018 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep HAVELI RESI CUM PLAZA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Makarpura2,900+ in Vadodara
Filed coordinates, straight-line distance. 122 registered projects within 2 km.
AATMIYA LANDMARK
AATMIYA REALTY
WINGS (TOWER A)
ONS BUILDTECH LLP
THE RISE PLAZA
THE DWARKESH INFRA
SHIVABHI LUXURIA
GURUPRASAD INFRASTRUCTURE PRIVATE LIMITED
ROSEDALE COUNTY
CALLA ASSOCIATES
DARSHANAM KINGSVILLE PHASE 1
MSK VENTURES LLP
See every Vadodara project, with the district possession charts
Builder: VRAJ ASSOCIATES
VRAJ ASSOCIATES has 2 registrations on GujRERA, including HAVELI RESI CUM PLAZA and VRAJ MANGAL. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if HAVELI RESI CUM PLAZA is delayed beyond 25 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of HAVELI RESI CUM PLAZA?
The registered promoter entity is VRAJ ASSOCIATES, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in HAVELI RESI CUM PLAZA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at HAVELI RESI CUM PLAZA?
The professionals named in the filing: Architect: KANUBHAI PATEL; Engineer: NARENDRA PATEL & ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HAVELI RESI CUM PLAZA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback