Home / Browse projects / Vadodara, Gujarat / THE RISE CLASSIC

Valid until 30 Oct 2026 Mixed Development project

THE RISE CLASSIC

By THE RISE DEVELOPERS

RG-GJ-07322 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA03464/200918 · Last updated on GujRERA portal: 10 Oct 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Oct 2026Possession promisedno revision filed
24 of 36Construction stages doneacross 4 buildings; furthest along: Sanitary fittings within the flats, 99%
95 of 193Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

THE RISE CLASSIC is a Mixed Development project by THE RISE DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA03464/200918 on 20 Sep 2018. Possession is promised by 30 Oct 2026. 98 of the 193 units on this registration are recorded sold or booked, and 24 of 36 construction stages are filed complete.

At a glance

Project

  • NameTHE RISE CLASSIC
  • TypeMixed Development
  • Location
    • NR. VILLAGE BHAYLI
    • BS. PRAGATI SCHOOL
    • BHAYLI
    • Bhayli
    • Vadodara
    • 391410
  • Pincode391410
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA03464/200918
  • ReraGenie IDRG-GJ-07322

Builder

  • NameTHE RISE DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2018PromisedOct 2026

Key facts

Registration and timeline

  • StatusValid until 30 Oct 2026
  • Registered on20 Sep 2018
  • Promised completion30 Oct 2026
  • Revised completionNone
  • Buildings4 building records
  • Documents filed41 files

Current status

51%98 of 193 units booked
115.3%Of the estimated cost spent so far

Figures as on 10 Oct 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---142741
B---113546
C---254166
D---40040

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 10 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Sanitary fittings within the flats, at 99%.

A98%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats98%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing98%
B98%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats98%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing98%
C98%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
D95%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats88%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing88%

Progress on shared amenities19

As on 10 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes80%
Street lightingYes90%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,682 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 12.00 cr
Cost incurredRs 13.83 cr
Spent of the estimate115.28%
BuildingWingEstimatedIncurred
DNARs 3.97 crRs 4.57 cr
CNARs 3.17 crRs 3.66 cr
ANARs 2.43 crRs 2.80 cr
BNARs 2.43 crRs 2.80 cr

Certifying professionals and partners1

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNEEL PATEL

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA03464/200918 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)10 Oct 2025
Engineer's certificate (Form 2)10 Oct 2025
Engineer's certificate annexure10 Oct 2025
Accountant's certificate (Form 3)10 Oct 2025
Site photograph, A10 Oct 2025
Site photograph, B10 Oct 2025
Site photograph, C10 Oct 2025
Site photograph, D10 Oct 2025
RERA registration certificate20 Sep 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

51%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep THE RISE CLASSIC on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bhayli2,900+ in Vadodara

2 kmTHE RISE CLASSICOther 292Dot size: filed unitsN

Filed coordinates, straight-line distance. 292 registered projects within 2 km.

Builder: THE RISE DEVELOPERS

THE RISE DEVELOPERS has 1 registration on GujRERA, including THE RISE CLASSIC. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if THE RISE CLASSIC is delayed beyond 30 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of THE RISE CLASSIC?

The registered promoter entity is THE RISE DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in THE RISE CLASSIC?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at THE RISE CLASSIC?

The professionals named in the filing: Architect: NEEL PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE RISE CLASSIC?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE RISE CLASSIC. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE RISE CLASSIC to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.