ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / THE POSH

Valid until 28 Feb 2031 Residential/Group Housing project

THE POSH

By KESHAV CORP

RG-GJ-13646 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA16310/120126/311030 · Last updated on GujRERA portal: 29 Sep 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Feb 2031Possession promisedno revision filed
4 of 18Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 18%
43 of 44Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

THE POSH is a Residential/Group Housing project by KESHAV CORP in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA16310/120126/311030 on 12 Jan 2026. Possession is promised by 28 Feb 2031. 1 of the 44 units on this registration are recorded sold or booked, and 4 of 18 construction stages are filed complete.

At a glance

Project

  • NameTHE POSH
  • TypeResidential/Group Housing
  • Location
    • THE POSH
    • RANDESAN METRO STATIONCROSS ROAD
    • RANDESAN
    • RANDESAN
    • Gandhinagar
    • 382007
  • Pincode382007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA16310/120126/311030
  • ReraGenie IDRG-GJ-13646

Builder

  • NameKESHAV CORP
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredJan 2026PromisedFeb 2031

Key facts

Registration and timeline

  • StatusValid until 28 Feb 2031
  • Registered on12 Jan 2026
  • Promised completion28 Feb 2031
  • Revised completionNone
  • Buildings2 building records
  • Documents filed45 files

Current status

2%1 of 44 units booked
17.5%Of the estimated cost spent so far

Figures as on 29 Sep 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---22022
B---22022

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 29 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 18%.

A24%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure18%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B23%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure3%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 29 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,452 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 25.99 cr
Cost incurredRs 4.55 cr
Spent of the estimate17.5%
BuildingWingEstimatedIncurred
ANARs 12.99 crRs 2.60 cr
BNARs 12.99 crRs 1.95 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhavik Jayantilal Sheladiya
EngineerJIGISH DINESHCHANDRA PARIKH

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA16310/120126/311030 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)29 Sep 2026
Engineer's certificate (Form 2)29 Sep 2026
Engineer's certificate annexure29 Sep 2026
Accountant's certificate (Form 3)29 Sep 2026
Site photograph, A26 Sep 2026
Site photograph, B26 Sep 2026
RERA registration certificate12 Jan 2026
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

2%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep THE POSH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near RANDESAN1,600+ in Gandhinagar

2 kmTHE POSHOther 144Dot size: filed unitsN

Filed coordinates, straight-line distance. 144 registered projects within 2 km.

Builder: KESHAV CORP

KESHAV CORP has 2 registrations on GujRERA, including BALMUKUND GLORY and THE POSH. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if THE POSH is delayed beyond 28 Feb 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of THE POSH?

The registered promoter entity is KESHAV CORP, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in THE POSH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at THE POSH?

The professionals named in the filing: Architect: Bhavik Jayantilal Sheladiya; Engineer: JIGISH DINESHCHANDRA PARIKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE POSH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE POSH. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE POSH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.