Home / Browse projects / Gandhinagar, Gujarat / THE MIDAS

Valid until 30 Apr 2028 Mixed Development project

THE MIDAS

By ANJANI INFRA

RG-GJ-10174 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA13254/050424/311227 · Last updated on GujRERA portal: 8 Aug 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
14 of 27Construction stages doneacross 3 buildings; furthest along: Staircases, 98%
100 of 157Units unsoldnot recorded sold or booked
Jump to the 27 documents Report an error

THE MIDAS is a Mixed Development project by ANJANI INFRA in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA13254/050424/311227 on 5 Apr 2024. Possession is promised by 30 Apr 2028. 57 of the 157 units on this registration are recorded sold or booked, and 14 of 27 construction stages are filed complete.

At a glance

Project

  • NameTHE MIDAS
  • TypeMixed Development
  • Location
    • THE MIDAS
    • NR. SARTHAK HEAVAN
    • KUDASAN
    • KUDASAN
    • Gandhinagar
    • 382421
  • Pincode382421
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA13254/050424/311227
  • ReraGenie IDRG-GJ-10174

Builder

  • NameANJANI INFRA
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredApr 2024PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on5 Apr 2024
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings3 building records
  • Documents filed27 files

Current status

36%57 of 157 units booked
82.8%Of the estimated cost spent so far

Figures as on 8 Aug 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D---26026
A+B+C---5847105
E---26026

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 8 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 98%.

D85%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats15%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%
A+B+C78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats15%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing40%
E85%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats15%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%

Progress on shared amenities19

As on 8 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes75%
Sewerage (chamber, lines, septic tank, STP)Yes70%
Storm water drainsYes70%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes45%
Solid waste management and disposalYes40%
Water conservation, rain water harvestingYes40%
Energy managementYes0%
Fire protection and fire safety requirementsYes25%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes25%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,101 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 58.00 cr
Cost incurredRs 48.00 cr
Spent of the estimate82.76%
BuildingWingEstimatedIncurred
A+B+CNARs 35.00 crRs 28.00 cr
DNARs 11.50 crRs 10.00 cr
ENARs 11.50 crRs 10.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIPREX PANKAJBHAI CHAVDA
EngineerNITINKUMAR PATEL

Documents filed27

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA13254/050424/311227 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)8 Aug 2026
Architect's certificate (Form 1)8 Jul 2026
Engineer's certificate (Form 2)8 Jul 2026
Engineer's certificate annexure8 Jul 2026
Site photograph, D24 Jun 2026
Site photograph, A+B+C24 Jun 2026
Site photograph, E24 Jun 2026
RERA registration certificate5 Apr 2024
Proforma agreement for sale-
Project specific document-
Drainage affidavit-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-

How this compares with Gandhinagar

36%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep THE MIDAS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KUDASAN1,600+ in Gandhinagar

2 kmTHE MIDASOther 251Dot size: filed unitsN

Filed coordinates, straight-line distance. 251 registered projects within 2 km.

Builder: ANJANI INFRA

ANJANI INFRA has 1 registration on GujRERA, including THE MIDAS. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if THE MIDAS is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of THE MIDAS?

The registered promoter entity is ANJANI INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in THE MIDAS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at THE MIDAS?

The professionals named in the filing: Architect: VIPREX PANKAJBHAI CHAVDA; Engineer: NITINKUMAR PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE MIDAS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE MIDAS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE MIDAS to a free account