Home / Browse projects / Bengaluru Urban, Karnataka / The High Line Park

Registration approved No litigation declared Mixed Development project

The High Line Park

By Gen Y Social communities LLP

RG-KA-60540 · RERA PRM/KA/RERA/1251/310/PR/071123/006379 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2027Possession promisedno revision filed
18 of 18Construction stages doneevery applicable stage filed complete
16 of 57Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 150 documents Report an error

The High Line Park is a Mixed Development project by Gen Y Social communities LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/071123/006379 on 7 Nov 2023. Possession is promised by 31 Aug 2027. 41 of the 57 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameThe High Line Park
  • TypeMixed Development
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560060
  • Pincode560060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/071123/006379
  • ReraGenie IDRG-KA-60540

Builder

  • NameGen Y Social communities LLP
  • Entity typePartnership Firm
  • LLPINAAO-8294
  • GSTIN29AATFG9702E1Z0
  • Authorized SignatoryPramod Kumar Reddy M
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredNov 2023PromisedAug 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 Nov 2023
  • Promised completion31 Aug 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed150 files

Current status

72%41 of 57 units booked
10.2%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
The High Line Park-----57

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
Other Works100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities29

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasYes100%
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyYes100%
Common storage spacesNoNot applicable

Land and ownership7

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,398 sq m
Named landowners7
LandownerVillageDistrict
Balaram Chopra--
Shyam Chopra--
Manmohan Chopra--
Trilok Chopra--
Shefali Chopra--
Govind Gopal Chopra--
Vishnu Chopra--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 31.47 cr
Cost incurredRs 3.22 cr
Spent of the estimate10.22%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 31.47 crRs 3.22 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAjit V Jain
EngineerK. S. Arunachala
Chartered AccountantP SREENIVASULU REDDY

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed150

As listed on the registration, under the names the promoter filed them with; the newest 80 of 150 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/071123/006379 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Auditor certificate THLP.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: THLP From-5 Architect Certificate (QU) THLP.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: The High Line park Engineer certificate (2).pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q2 2026-27 Fire and Safety13 Oct 2026
Q2 2026-27 Airport Authority of India13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Auditor certificate.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: THLP From-5 Architect Certificate.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: THLP Engineering Certificate .pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Auditor certificate.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect certificate.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: THLP engineering Certificate Q4.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Rera THLP - Auditor certificate.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: THE HIGH LINE PARK - Architect certificate.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: THLP engineer certificate.pdf13 Jan 2026
BESCOMFile: BESCOM_Affidavit.pdf4 Nov 2023
Section 3(1) notarized affidavitFile: Section3-1.pdf4 Nov 2023
Architects certificate with valid COAFile: Architects certificate with valid COA number and B.pdf3 Nov 2023
Certified Carpet area calculationFile: Certified Carpet area Calculation by Architect.pdf3 Nov 2023
CDP mapFile: CDP map showing proposed site.png3 Nov 2023
Village mapFile: Village map showing proposed site.png3 Nov 2023
Copy of ZR Showing the Nala BufferFile: ZR2015.pdf3 Nov 2023
Building LicenseFile: Building License issued by BDA.pdf3 Nov 2023
Form -01File: Form1-Filled-Fixed.pdf3 Nov 2023
Self-attested Engineer certificateFile: Engineer Certificate Self attested.jpg3 Nov 2023
Engineer certificateFile: Form3-Filled-Fixed.pdf3 Nov 2023
Section 3-1 notarized affidavitFile: Notarized Affidavit1.pdf3 Nov 2023
Project specificationFile: Project Specifications with Project name and engin.pdf3 Nov 2023
STP design drawingFile: STP Design Report certified by PHE Engineer.pdf3 Nov 2023
Guidance valueFile: Land cost calculation sheet as per Guideline value.pdf3 Nov 2023
Brief estimated costFile: Cost of construction certified by Engineer.pdf3 Nov 2023
Mutation RegisterFile: Mutation Register.pdf3 Nov 2023
Khatha certificateFile: 04-Khatha certificate.pdf3 Nov 2023
Conversion Order & SketchFile: 03-Conversion Order & Sketch.pdf3 Nov 2023
Conversion Order - 13-05-2010File: Conversion Order - 13052010.pdf3 Nov 2023
Topographic map showing Nala and RoadFile: Topographic map showing Nala and Road.pdf3 Nov 2023
Sanction drawing Site Plan Legible copyFile: Sanction drawing Site Plan Legible copy.pdf3 Nov 2023
STP Design Drawing certified by ConsultantFile: STP Design Drawing certified by Consultant.pdf3 Nov 2023
Kambipura village mapFile: Kambipura village map.pdf3 Nov 2023
Mortage deed done with Bajaj Finance towards ConstFile: Mortage deed done with Bajaj Finance towards Const.pdf3 Nov 2023
EC 2004 till date revisedFile: EC2004tilldaterevised.pdf3 Nov 2023
Bajaj Finance Sanction letter for Construction FinFile: Bajaj Finance Sanction letter for Construction Fin.pdf3 Nov 2023
BDA Surveyor drawing showing the site and NalaFile: BDA Surveyor drawing showing the site and Nala.jpeg3 Nov 2023
AOSFile: AOS_GENY.pdf3 Nov 2023
MODEL ALLOTMENT LETTERFile: ALLOTMENT_LETTER.pdf3 Nov 2023
Architects certificate with valid COA number and BBMP registration as an ArchitectFile: Architects certificate with valid COA number and BBMP registration as an Architect.pdf14 Sep 2023
Bajaj Finance Sanction letter for Construction Finance for 10 CrFile: Bajaj Finance Sanction letter for Construction Finance for 10 Cr.pdf14 Sep 2023
BDA Surveyor drawing showing the site and NalaFile: BDA Surveyor drawing showing the site and Nala.jpeg14 Sep 2023
Bescom NOCFile: Bescom NOC.pdf14 Sep 2023
Building License issued by BDAFile: Building License issued by BDA.pdf14 Sep 2023
CDP map showing proposed siteFile: CDP map showing proposed site.png14 Sep 2023
Certified Carpet area Calculation by ArchitectFile: Certified Carpet area Calculation by Architect.pdf14 Sep 2023
Chartered accountant certificate in prescribed format form -01File: Chartered accountant certificate in prescribed format form -01.pdf14 Sep 2023
Cost of construction certified by EngineerFile: Cost of construction certified by Engineer.pdf14 Sep 2023
EC-2004-till-date-revisedFile: EC-2004-till-date-revised.pdf14 Sep 2023
Engineer Certificate Self attestedFile: Engineer Certificate Self attested.jpg14 Sep 2023
Kambipura village mapFile: Kambipura village map.pdf14 Sep 2023
Land cost calculation sheet as per Guideline valueFile: Land cost calculation sheet as per Guideline value.pdf14 Sep 2023
Mortage deed done with Bajaj Finance towards Construction FinanceFile: Mortage deed done with Bajaj Finance towards Construction Finance.pdf14 Sep 2023
Notarized Affidavit-1File: Notarized Affidavit-1.pdf14 Sep 2023
Notarized Affidavit-2File: Notarized Affidavit 2.pdf14 Sep 2023
Notarized Affidavit-3File: Notarized Affidavit 3.pdf14 Sep 2023
Proforma of the Agreement for SaleFile: Proforma of the Agreement for Sale .pdf14 Sep 2023
Proforma of the Allotment letterFile: Proforma of the Allotment letter.pdf14 Sep 2023
Project Specifications with Project name and engineers signatureFile: Project Specifications with Project name and engineers signature.pdf14 Sep 2023
Sanction drawing Site Plan Legible copyFile: Sanction drawing Site Plan Legible copy.pdf14 Sep 2023
Sources of funds Supporting documentFile: Sources of funds Supporting document.pdf14 Sep 2023
STP Design Drawing certified by ConsultantFile: STP Design Drawing certified by Consultant.pdf14 Sep 2023
STP Design Report certified by PHE EngineerFile: STP Design Report certified by PHE Engineer.pdf14 Sep 2023
Topographic map showing Nala and RoadFile: Topographic map showing Nala and Road.pdf14 Sep 2023
Village map showing proposed siteFile: Village map showing proposed site.png14 Sep 2023
Water source letterFile: Water source letter.pdf14 Sep 2023
ZR showing the Nala buffer Tertiary drainFile: ZR showing the Nala buffer Tertiary drain.jpeg14 Sep 2023
ITR 2020-21File: GYSC LLP ITR AY 2020-21.pdf19 Aug 2023
ITR-2021-22File: GYSC LLP ITR AY 2021-22.pdf19 Aug 2023
ITR-2022-23File: GYSC LLP ITR AY 2022-23.pdf19 Aug 2023
Architect. cost certificateFile: Architect under construction certificate.pdf19 Aug 2023
CA Cost certificateFile: Certificate from CA under approval of cost details.pdf19 Aug 2023

How this compares with Bengaluru Urban

72%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep The High Line Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmThe High Line ParkLapsed / revoked 1Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: Gen Y Social communities LLP

GEN Y SOCIAL COMMUNITIES LLP has 2 registrations on RERA Karnataka, including OASIS and The High Line Park. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if The High Line Park is delayed beyond 31 Aug 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of The High Line Park?

The registered promoter entity is Gen Y Social communities LLP, a partnership firm as per the filing. Its LLPIN AAO-8294 and GSTIN 29AATFG9702E1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in The High Line Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at The High Line Park?

The professionals named in the filing: Architect: Ajit V Jain; Engineer: K. S. Arunachala; Chartered Accountant: P SREENIVASULU REDDY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The High Line Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The High Line Park. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The High Line Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.